Proposed Development

Construction of single storey building housing 6 no. golf practice bays (daylight only) and a ball wash and dispensing area

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    22 Oct 2009

  2. Decision: CONDITIONAL

    7 Dec 2009

  3. Decision due

    16 Dec 2009

  4. Grant issued

    15 Jan 2010

Application Details

Location
Farrangalway Kinsale
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Cork County Council

Timeline

Registration Date
22 October 2009
Status
APPLICATION FINALISED
Decision
CONDITIONAL
Decision Date
7 December 2009
Grant Date
15 January 2010

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

0m
09/7341INCOMPLETED APPLICATION15 Oct 2009

Single storey building housing 6no. golf practice bays (daylight only) and a ball wash & dispensing area

Farrangalway Kinsale

77m
08/5588CONDITIONAL20 Mar 2008

Construction of 2 no. golf holes, 1 no. tee complex, 1 no. practice ground and ancillary works

Farrangalway Kinsale

82m
08/5107INCOMPLETED APPLICATION29 Feb 2008

Construction of 2 no. gold holes, tee complex, practise groung and ancillary works

Farrangalway Kinsale

181m
11/4429CONDITIONAL7 Mar 2011

Installation of flood lighting to existing practice grounds

Farrangalway Kinsale

183m
11/4365INCOMPLETED APPLICATION24 Feb 2011

Installation of flood lighting to the existing practice grounds

Farrangalway Kinsale Co Cork

315m
25/4167Conditional Permission10 Feb 2025

10 Year Planning permission for a solar farm with a total area of circa 9 hectares. The solar farm will consist of solar panels on ground mounted frames, 2 no. single storey electrical inverter/transformer stations, 2 no. containerised energy storage modules, 1 no. single storey spare parts container, 1 no. medium voltage control/switching substation (comprising either single-storey building or 2 no. modular units), 1 no. weather station, underground electrical ducting and cabling within the development site, security fencing, CCTV, access tracks, temporary construction compound, landscaping and all associated ancillary development and drainage works. Construction and operational access will be via 1 no. existing entrance from the L7247. The operational lifespan of the solar farm will be 40 years and planning permission is requested for the duration.

Farrangalway Mellifontstown Kinsale Co.Cork

317m
18/4954INCOMPLETED APPLICATION18 Apr 2018

Dwellinghouse, treatment plant, associated site works and services.

Farrangalway Kinsale Co. Cork

329m
17/7301CONDITIONAL15 Dec 2017

1. Demolish existing timber Extension to the rear (north) of the existing cottage, 2. Restore existing old cottage – repair roof, add two roof lights to the northern roof, replace windows with new, build new porch (replacing old) to the south of the cottage. 3. To the north of the existing cottage, construct a new one-and-a-half storey dwelling extension, with single storey ‘link’ to the cottage, 4. Decommissioning existing well, drill and install a new well within the site, 5. Decommissioning existing septic tank and install a new septic tank and percolation area within the site, 6. Carry out all associated site works.

The Pink Cottage Mellifontstown Kinsale Co. Cork

336m
20/5168REFUSED9 Jun 2020

A dwelling house, treatment plant, associated site works and services.

Farrangalway Kinsale Co. Cork

336m
19/4040INCOMPLETED APPLICATION14 Jan 2019

The Retention for two timber storage sheds, well and associated site works and services.

Farrangalway Kinsale Co. Cork

Planning a project of your own?

Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.

Do I Need Permission?