Ballygown Mallow

REFUSED

Planning application 09/7783

Cork - Cork County Council

Proposed Development

Alterations to site layout granted under Pl. Reg. No. 07/11150 including the omission of building 'C' previously granted under 07/11150 and retention of existing building for the maintenance of refuse trucks, skips, and wheelie bins

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    30 Nov 2009

  2. Decision: REFUSED

    2 Mar 2010

  3. Decision due

    3 Mar 2010

Application Details

Location
Ballygown Mallow
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Cork County Council

Timeline

Registration Date
30 November 2009
Status
APPLICATION FINALISED
Decision
REFUSED
Decision Date
2 March 2010

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

0m
07/11150CONDITIONAL21 Sept 2007

Construction of truck storage and maintenance depot consisting of access road, Building "A" for storage of new skips and wheelie bins, Building "B" for maintenance of refuse trucks, skips and wheelie bins, Building C for truck and maintenance staff, construction of truck parking area, truck wash area, truck re-fueling area, mechanical aeration system and polishing filter and all associated site works

Ballygown Mallow

0m
09/5483CONDITIONAL8 May 2009

Raising of floor and site levels of administration building, maintenance building, storage building, ancillary service areas and associated site works from permitted levels granted under Pl. Reg. No. 07/11150 at proposed truck storage and maintenance depot

Ballygown Mallow

0m
07/10898INCOMPLETED APPLICATION10 Sept 2007

Construction of truck storage and maintenance depot comprising of access road, Building A for storage of new skips and wheelie bins, Building B for maintenance of refuse trucks, skips and wheelie bins, Building C for use as administration, provision for car park for administration staff and visitors, provision for car park for truck and maintenance staff, truck parking area, truck wash area, truck re-fueling area,k mechanical aeration system and polishing filter and all associated site works

Ballygown Mallow

0m
11/4119CONDITIONAL27 Jan 2011

Permission for alterations to site layout previously granted permission under Planning Reg. No. 07/11150 and 10/4551. The application to include permission for (a) Omission of two storey administration office building 'C' and associated car park previously granted permission under Planning Reg. No. 07/11150, (b) Construction of a single storey administration office building and associated car parking area, (c) Construction of a 6m canopy to the northern side of the existing maintenance building, (d) Construction of an extension to truck parking area together with alterations to the associated site works

Ballygown Mallow Co Cork

0m
13/4540CONDITIONAL28 Mar 2013

(1) Change of use of part of existing maintenance building to truck driver's compound use at ground floor level, (2) construction of a mezzanine floor overhead to facilitate storage of truck parts, and (3) alterations to elevations, and permission for retention of 2 no. doors to south elevation of existing maintenance building

Ballygown Mallow

0m
10/4551CONDITIONAL10 Mar 2010

Alterations to site layout granted permission under Pl. Reg. No. 07/11150 to include retention of existing building for the maintenance of refuse trucks, skips and wheelie bins and permission for the omission of building B previously granted permission under Pl. Reg. No. 07/11150 together with alterations to the associated site works

Ballygown Mallow

5m
16/5185CONDITIONAL18 May 2016

Construct a building which is proposed to be partly used as a truck maintenance garage and partly used as a store for new skips and new wheelie bins associated with an existing truck storage and maintenance depot (previously granted under Planning Reg. No. 07/11150, 10/4551 and 11/4119) and ancillary site works

Ballygown Mallow Co. Cork

5m
22/6336INCOMPLETED APPLICATION18 Oct 2022

The construction of an underground storage tank and amendments to a permitted development at the existing truck storage and maintenance depot (previously permitted under Planning Reg. No. 16/5185 as amended by 21/6510). The proposed development seeks an amendment to condition no. 29 of the development permitted under Planning Reg. No. 16/5185 which states that the developer / operator of the site shall ensure that all vehicles, skips, tankers, trailers and/ or containers/bins/receptacles shall be devoid of waste prior to entry onto the site. The proposed amendment will allow for vehicles carrying waste to enter onto the site under limited circumstances for the purposes of carrying out essential maintenance.

Ballygown Mallow Co. Cork

5m
17/7456CONDITIONAL22 Dec 2017

To construct a single storey extension (126 sqm) to the rear of the existing single storey administration office building together with associated site works.

Ballygown Mallow Co. Cork

63m
22/5263CONDITIONAL31 May 2022

Permission to install photovoltaic solar panel arrays, consisting of approximately 528 sqm of photovoltaic solar panels on ground mounted frames within a site area of 0.97 ha (2.39 Acres)

Ballygown Mallow Co.Cork