Dromourneen, Lognagappul & Barryroe Bantry Co. Cork
CONDITIONALPlanning application 09/849
Cork - Cork County Council
Proposed Development
Ten year planning permission for a wind farm of up to 6 wind turbines (hub height 64m and rotor diameter of 71m - tip height of 99.5m), access roads, hardstandings, underground cabling, rock borrow pit and ancillary site works - forming an extension to the existing Glanta Commons Windfarm
View the full application file on the council's planning portal →Application Timeline
Application received
27 Jul 2009
Decision: CONDITIONAL
18 Sept 2009
Decision due
20 Sept 2009
Application Details
- Location
- Dromourneen, Lognagappul & Barryroe Bantry Co. Cork
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Cork County Council
Timeline
- Registration Date
- 27 July 2009
- Status
- APPLICATION FINALISED
- Decision
- CONDITIONAL
- Decision Date
- 18 September 2009
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
Modification to the ten year planning permission for up to six turbines forming an extension to the Glanta Commons Wind Farm granted under An Bord Pleanala reference number PL 88.235028 (County Council number 09/849). The modification is to increase the turbine hub heights from 64m to 74.5m. Turbine locations and wind farm access roads to remain the same as granted by An Bord Pleanala
Dromourneen, Lognagappul Barryroe, Bantry, Co. Cork West and adjacent to existing Glanta Commons Wind Farm
A ten year planning permission for up to two wind turbines with a tip height of up to 110 metres, site access roads, hardstanding areas, underground cabling and all ancillary site works - forming an extension to the existing Glanta Commons Wind Farm, consisting of nineteen wind turbines. An environmental impact statement (EIS) has been prepared and will be submitted to the Planning Authority with this application
Lognagappul & Barryroe Bantry Co Cork
Erection of 40m high wind monitoring mast
DROMOURNEEN, DROMOURNEEN,
The upgrade of the existing site entrance at Derreennacno and amendment of Condition 1 of An Bord Pleanala Reference PL 04.216875 (a permission for 13 no. turbines) to specify that the structures should be removed at the expiration of a 25 year period instead of the 20 years permitted. Permission is also sought for the amendment of Condition 4 of An Bord Pleanala Reference PL 88. 235028, (a permission for 6 no. turbines) to specify that the permission is for a period of 25 years from the date of commissioning instead of the 20 years specified in the condition. An environmental impact statement (EIS) has been prepared and will be submitted to the planning authority with this application
Townlands of Lognagappul, Lackenafasoge, Glanaphuca-Caheragh Drimoleague, and Townlands of Dromourneen,Derreennacno and Barryroe-Bantry-Glanta Commons Wind Farm
Dwellinghouse, domestic garage and stables for private use
Barryroe Bantry
The construction of a loose open Livestock shed for the housing of sheep and cattle, a dungstead and a slurry/soiler water tank
Barryroe Bantry Co. Cork
Construction of a loose livestock shed with dungstead to the rear and to carry out all associated site works
Barryroe Bantry Co Cork
Extension to dwelling
Dromourneen Bantry
Dwellinghouse
Dromourneen Bantry Co. Cork
Wind farm to consist of 13 no. wind turbines with blade tip height of up to 100m, electrical substation and control building, 60m high meteorological mast, site entrances, access tracks, hardstandings and ancillary site works
Dromoureen Bantry