← Back to search

Ballintaggart Ringaskiddy

CONDITIONAL

Planning application 10/4483

Cork - Cork County Council

Proposed Development

Retention of a 60m high 300mm diameter steel mast mounted with instruments to collect meteorological data

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    3 Mar 2010

  2. Decision due

    27 Apr 2010

  3. Decision: CONDITIONAL

    27 Apr 2010

  4. Grant issued

    28 May 2010

Application Details

Location
Ballintaggart Ringaskiddy
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Cork County Council

Timeline

Registration Date
3 March 2010
Status
APPLICATION FINALISED
Decision
CONDITIONAL
Decision Date
27 April 2010
Grant Date
28 May 2010

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

0m
10/4336INCOMPLETED APPLICATION17 Feb 2010

Retention of 60m high 300mm diameter steel mast mounted with instruments to collect meteorological data

Ballintaggart Ringaskiddy

87m
18/6401INCOMPLETED APPLICATION11 Sept 2018

The works will include (1) A 4-storey extension to the east of the existing manufacturing building, (2) A 2-storey extension to the north of the existing warehouse, (3) relocation of the existing eastern car park and rationalisation and relocation of the previously granted car park spaces (Planning Reg. Nos. 15/5818 and 17/5791) to a proposed new site car park to the west of the existing manufacturing building, (4) A single storey extension to the south of the existing warehouse to support warehouse operations and (5) part demolition of the existing temporary modular building (Planning Reg. No. 14/5337) to facilitate construction works and the erection of a new temporary modular building to the east of the existing manufacturing building for office use with link into the part-demolished existing modular building. The construction will also include associated site development works including internal roads and drainage. The proposed development is covered by an existing Industrial Emissions License No. P0864-01.

Ballintaggart Shanbally Ringaskiddy Co. Cork

87m
18/6603Conditional Permission5 Oct 2018

The works will include (1) A 4 storey extension to the east of the existing Manufacturing building, (2) A 2 storey extension to the north of the existing warehouse, (3) Relocation of the existing eastern car park and rationalisation and relocation of the previously granted car park spaces (Planning Reference 15/5818 and 17/5797) to a proposed new site car park to the west of the existing Manufacturing Building, (4) A single storey extension to the south of the Existing Warehouse to support warehouse operations and (5) part demolition of the existing temporary modular building (Planning Reference 14/5337) to facilitate construction works and the erection of a new temporary modular building to the east of the existing Manufacturing Building for office use with link into the part-demolished existing modular building. The construction will also include associated site development works including internal roads and drainage. The proposed development is covered by an Industrial Emissions Licence No. P0864-01.

Ballintaggart Shanbally Ringaskiddy Co. Cork

117m
26/2077Awaiting Recommendation6 Aug 2026

The development shall include the construction of a new two-storey electrical substation building, access platforms and stairs, foundations and ground works, electrical ducting and associated works. The proposed development is covered by an existing Industrial Emissions License No. P0864-01.

Ballintaggart, Shanbally, Ringaskiddy, P43 R298

160m
15/6909CONDITIONAL21 Dec 2015

The construction of a 4 storey extension to the north east corner of the existing manufacturing building. The works will also include associated site development works, including internal road realignment and demolition of an existing stair core.

Ballintaggart Shanbally Ringaskiddy Co. Cork

160m
15/5727INCOMPLETED APPLICATION4 Aug 2015

Construction of a New Administration Headblock Building and Atrium, a South Expansion to the existing Laboratory/Administration Building, a Warehouse Building extension and a car park. The works will also include associated site development works, including internal road realignment and the provision of new fencing, gate and barriers, and the demolition of an existing guard house and an existing staircore. (The development is covered by an existing Industrial Emissions Licence No. P0864-01)

Ballintaggart Shanbally Ringaskiddy

161m
13/5400CONDITIONAL19 Jul 2013

Construction of an electrical substation building.

Ballintaggart Shanbally

161m
14/5337CONDITIONAL23 Jun 2014

Construction of temporary office accommodation with link corridor to existing building and relocation of existing fence.

Ballintaggart Shanbally Co.Cork

161m
15/5818CONDITIONAL17 Aug 2015

Extension to existing manufacturing building consisting of: (1) Extension with atrium for office/administrative use to part of western and to southern elevation, (2) 3 no. separate extensions on western and southern elevations of warehouse area of building for lobby use, airlock area and general warehouse use and associated site development works including car park, internal road realignment and the provision of new fencing, gate and barriers and the demolition of an existing security building (guard house) and existing staircase area to southern elevation of main building.

Ballintaggart Townland Shanbally Ringaskiddy Co. Cork

167m
07/8150CONDITIONAL25 May 2007

Construction of Monoclonal Antibodies, Small Scale biotechnology facility comprising of three storey manufacturing building with penthouse plant room on third floor level, two storey administration/laboratory wing and warehouse wing, external utilities yard to west of facility, a detached station/guard house , internal ring road, upgrading of existing car park to provide 187 no. staff car parking spaces, provision for 14 no. visitor car parking spaces, landscaping, palisade fencing to site perimeter and decorative fence to South building facade ,signage , sewage treatment unit and all associated site works and services

Ballintaggart