Proposed Development
Construction of extension to existing school comprising of 2 no. mainstream classrooms, alterations to existing elevations to accommodate new fire doors and alterations and relocation of boundary walls and fences and retention of existing car park and vehicular entrance.
Application Timeline
Application received
23 Dec 2011
Decision: CONDITIONAL
16 Apr 2012
Decision due
19 Apr 2012
Grant issued
22 May 2012
Application Details
- Location
- Ballycoskery Ballyhea Charleville
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Cork County Council
Timeline
- Registration Date
- 23 December 2011
- Status
- APPLICATION FINALISED
- Decision
- CONDITIONAL
- Decision Date
- 16 April 2012
- Grant Date
- 22 May 2012
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
Construction of pre-fabricated pre-school, waste water treatment system and pedestrian access
BALLYCOSKERY, BALLYCOSKERY,
Demolition of prefabricated building and construction of a two classroom extension, office and entrance lobby to school, construction of a new sand polishing filter and proprietary wastewater treatment unit, realignment of front boundary wall, provision of additional staff parking area, new set down area and all associated site works
Ballyhea Ballycoskery Charleville
Construction of detached general purpose room incorporating storage, meeting room and toilets
Ballyhea National School Ballycoskery Charleville Co. Cork
Demolition of existing prefabricated building and construction of extension to existing school comprising of 2 no. classrooms, construction of office and entrance lobby, installation of septic tank, realignment of front boundary wall, provision for additional staff parking, new set down area and all ancillary site works
Ballyhea Ballycoskery Charleville
Permission for the construction of a hurling wall and all associated site works.
Ballycoskery Ballyhea Charleville Co. Cork
Demolition of existing portacabin and construction of new childcare building in place of existing portacabin structures and all associated site works.
Ballycoskery Ballyhea Co. Cork
Construction of new childcare building in place of existing portacabin structures and all associated site works.
Ballycoskery Ballyhea Co. Cork
3no. two-storey detached dwellings with detached domestic garages, individual proprietary treatment units, entrances from the public road & all associated site works
Ballycoskery Ballyhea Charleville
Retention of 2 no. dormer windows to front of dwellinghouse
No.7 Beechwood Drive Ballycoskery Ballyhae
2 no. velux windows to roof and 1 no. window to gable of dwellinghouse