Proposed Development

Retention of a combined heating and power plant (CHP), consisting of a Steam boiler enclosure, a boiler flue 14.8m high, a generator and associated enclosure, a transformer and associated ancillary works, partially enclosed within a 1.8m high palisade fence at their existing facility. The facility is subject to an Integrated Pollution Prevention and Control License.

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    7 Mar 2012

  2. Decision due

    1 May 2012

Application Details

Location
Wallingstown Little Island Co. Cork
Applicant
N/A
Application Type
RETENTION
Planning Authority
Cork County Council

Timeline

Registration Date
7 March 2012
Status
INCOMPLETED APPLICATION
Decision
Pending
Decision Due
1 May 2012

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

0m
07/6210CONDITIONAL20 Mar 2007

Two storey extension to existing production building 1 and associated ancillary site works

Wallingstown Little Island

0m
07/4297CONDITIONAL19 Jan 2007

Construction of single storey extension to warehouse with associated offices, replacement of cladding to existing warehouse building and ancillary site works

Wallingstown Little Island

0m
04/6329CONDITIONAL19 Aug 2004

Alterations to permission 03/5456 to include a lift motor room on the roof of the production building and alterations to the Utilities building

Wallingstown Little Island

0m
03/5456CONDITIONAL4 Nov 2003

Construction of a 5 storey API production building, 2 storey admin and laboratory building, utility building & ancillary infrastructure

WALLINGSTOWN, WALLINGSTOWN,

0m
03/6461CONDITIONAL16 Dec 2003

Placing 2 no. air handling units on the roof of the plant 2 building

Wallingstown Little Island

0m
05/1860CONDITIONAL24 Mar 2005

Extension to Plant 2 building

Wallingstown Little Island

0m
04/5620INCOMPLETED APPLICATION21 Jul 2004

Alterations to permission 03/5456 to include a lift motor room on the roof of the production building and alterations to the utilities building

Wallingstown Little Island

0m
04/5619CONDITIONAL21 Jul 2004

Construction of water tank and pumphouse

Wallingstown Little Island

0m
11/5442CONDITIONAL1 Jul 2011

The development will consist of placing two air handling units and associated ductwork on the roof of the Plant 2 building and to upgrade part of the elevation of the Administration building with the installation of new windows and doors, the replacement of the cladding on part of the eastern elevation and ancillary site works at their existing facility

Wallingstown Little Island Co. Cork

0m
11/5386INCOMPLETED APPLICATION24 Jun 2011

Placing of two air handling units and associated ductwork on roof of the Plant 2 Building and upgrading of part of the elevation of the Administration Building with the installation of new windows and doors, replacement of cladding on part of eastern elevation and ancillary site worksat their existing facility

Wallingstown Little Island

Affected by this application?

Submissions can be made for 5 weeks from the date the application was received. Only material planning grounds count. Build a valid submission letter in minutes.

Make a Submission or Objection

Planning a project of your own?

Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.

Do I Need Permission?
Wallingstown Little Island Co. Cork - Planning Application 12/4419 | Permission.ie