Proposed Development

Permission for extensions to existing calcareous Marine Algae facility to provide 1- additional ground floor product storage and handling facilities, 2 - first floor office and amenities facilities, 3 - truck loading and dock levelling facility and ancillary site works

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    27 Mar 2014

  2. Decision: CONDITIONAL

    18 Jul 2014

  3. Decision due

    29 Jul 2014

  4. Grant issued

    26 Aug 2014

Application Details

Location
Dinish Island Castletownbere Beara Co. Cork
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Cork County Council

Timeline

Registration Date
27 March 2014Other applications received that week
Status
APPLICATION FINALISED
Decision
CONDITIONAL
Decision Date
18 July 2014
Grant Date
26 August 2014

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

0m
14/153INCOMPLETED APPLICATION28 Feb 2014

Permission for extensions to existing calcareous Marine Algae facility to provide 1 - additional ground floor product storage and handling facilities, 2 - first floor office and amenities facilities, 3 - truck loading and dock levelling facility and ancillary site works

Dinish Island Castletownbere Beara Co. Cork

0m
14/202INCOMPLETED APPLICATION20 Mar 2014

Permission for extensions to existing calcareous Marine Algae facility to provide 1 - additional ground floor product storage and handling facilities, 2 - first floor office and amenities facilities, 3 - truck loading and dock levelling facility and ancillary site works

Dinish Island Castletownbere Beara Co. Cork

3m
26/1266Invalid - Case Closed13 May 2026

Planning permission for existing and proposed works at the existing marine sourced feed & nutritional material processing and storage facility, as follows: Permission is sought for the retention and removal of 1) existing twin containers and 2) storage cabin, the retention of 3) the existing meeting room cabin, 4) maintenance cabin, 5) a maintenance container and of 6) a production lean-to extension. Permission is sought for 7) the demolition of the west loading dock and ramp. Permission is further sought for the construction of 8) a lean-to maintenance workshop, 9) enclosure to existing silos to north elevation, 10) raising of part of the production area roof by 3m, 11) northwest extension of production area, 12) sample store lean-to extension to west, 13) lean-to loading canopy to southwest, 14) additional loading dock to south, 15) enclosure to proposed tanker filling silos to existing alley, and 16) all associated site works.

Dinish Island, Castletownbere, Beara, Co Cork, P75 NY52

3m
26/1740Grant with Conditions29 Jun 2026

Planning permission for existing and proposed works at the existing marine sourced feed & nutritional material processing and storage facility, as follows: Permission is sought for the retention and removal of 1) existing twin containers and 2) storage cabin, the retention of 3) the existing meeting room cabin, 4) maintenance cabin, 5) a maintenance container and of 6) a production lean-to extension. Permission is sought for 7) the demolition of the west loading dock and ramp. Permission is further sought for the construction of 8) a lean-to maintenance workshop, 9) enclosure to existing silos to north elevation, 10) raising of part of the production area roof by 3m, 11) northwest extension of production area, 12) sample store lean-to extension to west, 13) lean-to loading canopy to southwest, 14) additional loading dock to south, 15) enclosure to proposed tanker filling silos to existing alley, and 16) all associated site works.

Dinish Island, Castletownbere, Beara, Co Cork, P75 NY52

3m
18/352CONDITIONAL19 Jun 2018

Retention of construction of detached Compressor House and of alterations to elevations of Calcareous Marine Algae facility and Permission for additions to same to include (a) lean-to canopy to east, (b) lean-to pallet store to north and (c) loading dock to south

Dinish Island Castletownbere Beara Co Cork

3m
17/548CONDITIONAL23 Aug 2017

Construction of additional warehouse for extension to existing Calcareous Marine Algae facility to provide additional ground floor product storage and ancillary site works and alterations to roof line of existing production building

Dinish Island Castletownbere Co Cork

8m
98/1559NEW APPLICATION17 Apr 1998

Construction of food production facility

DINISH ISLAND, DINISH ISLAND,

8m
98/1560NEW APPLICATION17 Apr 1998

Construct pier, access road, rock armour wall, open and covered storage facilities

DINISH ISLAND, DINISH ISLAND,

11m
07/2670INCOMPLETED APPLICATION18 Oct 2007

Construction of extensions to existing production facility

Dinish Island Castletownbere Beara

11m
07/2799CONDITIONAL5 Nov 2007

Construction of extensions to existing production facility