Proposed Development

Construction of a single storey dwelling with single garage, sewage treatment unit and percolation area

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    28 Apr 2014

  2. Decision due

    23 Jun 2014

Application Details

Location
Ballineadig Farran Co.Cork
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Cork County Council

Timeline

Registration Date
28 April 2014Other applications received that week
Status
INCOMPLETED APPLICATION
Decision
Pending
Decision Due
23 June 2014

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

0m
14/4999CONDITIONAL15 May 2014

Construction of single storey dwelling with single garage, sewage treatment unit and percolation area

Ballineadig Farran

192m
05/5925CONDITIONAL17 Aug 2005

Split level dwellinghouse

Ballineadig Farren

192m
05/326WITHDRAWN27 Jan 2005

Dwelling

Ballineadig Farren

277m
05/8202REFUSED8 Nov 2005

Dwelling, entrance & installation of septic tank & percolation area

Ballineadig Farran

277m
06/6301CONDITIONAL11 Apr 2006

Construction of dwellinghouse

Ballineadig Farran

332m
15/4575CONDITIONAL25 Mar 2015

Construction of a milking parlour, dairy and waiting yard, 2 no. silage pits and livestock housing comprising cubicle livestock housing and slatted slurry storage and all associated site works

Ballineadig Farran

332m
20/5044REFUSED25 May 2020

Construction of a milking parlour, dairy and waiting yard, 2 no. silage pits and livestock housing comprising cubicle livestock housing and slatted slurry storage and all associated site works. Extension of Duration of Permission granted under Planning Reference: 15/4575

Ballineadig Farran Co. Cork

332m
20/5657UNCONDITIONAL4 Aug 2020

Construction of a milking parlour, dairy and waiting yard, 2 no. silage pits and livestock housing comprising cubicle livestock housing and slatted slurry storage and all associated site works - Extension of duration of permission granted under Planning Reference: 15/4575

Ballineadig Farran Co. Cork

552m
24/6376CONDITIONAL12 Dec 2024

Permission for retention of the following completed works (change of plans previously permitted under planning reference no. 08/4490); 1)2-storey dwelling house as constructed, 2) vehicular site entrance as constructed and 3) all associated completed site works.

Oak Lodge Farran Hill, Farran Ovens Co.Cork

685m
24/5245CONDITIONAL3 Jul 2024

Permission for retention of a sun room to the front of their existing dwelling, a change of a window to a French door on the first floor of the southern elevation, the addition of timber cladding to part of the southern and western elevations & the retention of a domestic garage.

Riain Lower Farran Hill Farran Co. Cork

The submission window has closed

Observations on this application closed on Sunday 1 June 2014, five weeks after it was received. The authority cannot accept a late submission.

Planning a project of your own?

Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.

Do I Need Permission?