Glentanemacelligot Newmarket Co.Cork
CONDITIONALPlanning application 14/5023
Cork - Cork County Council
Proposed Development
Erection of a permanent 80 metre high meteorological mast and all ancillary site works at the site of the Glentanemacelligot Windfarm (Planning Ref. No’s 02/4283, 06/4077, 10/8034 and 11/4736)
View the full application file on the council's planning portal →Application Timeline
Application received
16 May 2014
Decision: CONDITIONAL
18 Sept 2014
Decision due
25 Sept 2014
Grant issued
24 Oct 2014
Application Details
- Location
- Glentanemacelligot Newmarket Co.Cork
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Cork County Council
Timeline
- Registration Date
- 16 May 2014
- Status
- APPLICATION FINALISED
- Decision
- CONDITIONAL
- Decision Date
- 18 September 2014
- Grant Date
- 24 October 2014
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
Modification to permitted development 02/4283 to include 6 no. turbines, hub height of 80m and blade diameter of 90m and blade tip height of 125m, 2 no. 80m high wind monitoring masts, ESB substation compound with control building, site tracks and associated site development works
Glentanemacelligot Newmarket
An increase of the turbine hub height from 60m to 80m and an increase of the blade tip height from 100m to 125m in the existing planning permission fro a wind farm (planning reference no. N/02/4283)
Glentanemacelligot Glenakeel South Newmarket
Completion of 6 no. turbines of hub height 80m and blade diameter of 90m and blade tip height of 125m, 2 no. 80m high wind monitoring masts, ESB substation compound with control building, site tracks and associated site development works as granted under Planning Reg. no. 06/4077
Glentanemacelligot Glenakeel South Newmarket Co. Cork
Dwellinghouse
Glentanemacelligot Ballydesmond
Modifications to the internal site tracks and site access associated with permitted Glentanemacelligot Windfarm Phase 1 (Planning Reg. Nos. 06/4077 and 02/4283) and construction and upgrading of an additional site access track and entrance from public road (utilising an existing forestry track).
Glentanemacelligot Glennakeel South Newmarket
Construction of single storey extension to side and front elevations and alterations to rear elevation of dwellinghouse and ancillary works
Glentanemacelligot Ballydesmond
(a) Construction of 2no. sections of forest road (of approx.25m and 98m in length) along with associated turning circles, to facilitate clearfelling, (b) the clearfelling, fallowing and replanting of existing conifer plantation within 5no. felling coupes on a cumulative afforested area of approximately 62.62ha to prevent turbulence effects on the permitted phase 2 of Glentanemacelligot Windfarm (Planning Ref. No. 08/10245 and An Bórd Pleanála Ref. No. 04.235930) and (c) all ancillary site works including drainage works, temporary compound and temporary spoil stockpile area, all on an overall site of 73.9ha.
Glennakeel West, Glennakeel South Glentanemacelligot Glenmucklagh West Newmarket, Co. Cork
(a) Construction of 2no. sections of forest road (of approx.25m and 98m in length) along with associated turning circles, to facilitate clearfelling, (b) the clearfelling, fallowing and replanting of existing conifer plantation within 5no. felling coupes on a cumulative afforested area of approximately 62.62ha to prevent turbulence effects on the permitted phase 2 of Glentanemacelligot Windfarm (Planning Ref. No. 08/10245 and An Bórd Pleanála Ref. No. 04.235930) and (c) all ancillary site works including drainage works, temporary compound and temporary spoil stockpile area, all on an overall site of 73.9ha. - Extension of duration of permission granted under planning reference: 14/06578 - An Bord Pleanala reference: PL04.245644
Glennakeel West, Glennakeel South Glentanemacelligot Glenmucklagh West Newmarket Co. Cork
Dwelling and garage
Glennamucklagh West Newmarket
Dwelling and garage
GLENNAMUCKLAGH WEST, GLENNAMUCKLAGH WEST,
Planning a project of your own?
Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.
Do I Need Permission?