Ballybeg Mallow Co.Cork
INCOMPLETED APPLICATIONPlanning application 14/5532
Cork - Cork County Council
Proposed Development
Relocation of vehicular entrance to residence for continued use as vehicular entrance to residence and as new agricultural entrance to adjacent field
Application Timeline
Application received
16 Jul 2014
Decision due
9 Sept 2014
Application Details
- Location
- Ballybeg Mallow Co.Cork
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Cork County Council
Timeline
- Registration Date
- 16 July 2014
- Status
- INCOMPLETED APPLICATION
- Decision
- Pending
- Decision Due
- 9 September 2014
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
Relocate existing vehicular entrance to residence for continued use as vehicular and pedestrian entrance to residence and as new agricultural entrance to adjacent field
Ballybeg Mallow
Development of agricultural land and construction of six dwellings complete with all associated site works including installation of septic tanks and percolation areas and alteration works to improve the existing domestic and field access.
New Twopothouse Ballybeg Mallow Co. Cork, next to P51 YFX2
Development of agricultural land and construction of six dwellings complete with all associated site works including installation of septic tanks and percolation areas, access road and alteration works to improve the existing domestic and field access.
Ballybeg New Twopothouse Mallow Co. Cork
Construction of one two-storey dwelling complete with attached double garage and annex which is to be utilised as a separate dwelling ancillary to the main dwelling, all associated site works including installation of septic tank and percolation area and access road to the dwelling(s) utilising existing domestic and field access.
Ballybeg New Twopothouse Mallow Co. Cork
Construction of one two-storey dwelling complete with attached double garage and annex, all associated site works including installation of septic tank and percolation area, utilising existing domestic and field access.
Ballybeg New Twopothouse Mallow Co. Cork
Construction of single storey classroom extension to include toilet facilities, store and link corridor, installation of waste water treatment plant and associated site works and retention of existing pre-fabricated classroom
Baltydaniel East Mallow
Retention of existing pre-fabricated classroom & resource room and change of use of utility room granted under planning ref.no. 04/1974 to staff room
Baltydaniel East Mallow
Retention of existing pre-fabricated classroom & resource room, change of use of utility room granted under planning ref.no. 94/1974 to staff office
Baltydaniel East Mallow
Retention of existing pre-fabricated classroom & resource room and change of use of utility room granted under planning ref.no. 04/1974 to staff office
Baltydaniel East Mallow
Construction of single storey classroom extension including link corridor, removal of 2 no. pre-fabs and all associated site works
Baltydaniel National School Baltydaniel East Ballybeg Mallow
The submission window has closed
Observations on this application closed on Tuesday 19 August 2014, five weeks after it was received. The authority cannot accept a late submission.