Proposed Development
Construction of a two storey extension to the existing administration building consisting of a new building entranceway, stairwells to the north and east of the building, an infill first floor within the existing building and modifications to the existing elevations with associated ancillary works at existing facility
Application Timeline
Application received
1 Aug 2014
Decision: CONDITIONAL
17 Oct 2014
Decision due
28 Oct 2014
Grant issued
24 Nov 2014
Application Details
- Location
- Wallingstown Little Island
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Cork County Council
Timeline
- Registration Date
- 1 August 2014
- Status
- APPLICATION FINALISED
- Decision
- CONDITIONAL
- Decision Date
- 17 October 2014
- Grant Date
- 24 November 2014
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
Construction of a single storey extension to rear of existing logistics building and a covered external yard with associated ancillary works at existing facility
Wallingstown Little Island
Construction of a two-storey extension 12.250m high to the existing Production Building P3 including a vent stack 17.750m high and modification to the existing elevations with associated ancillary works at existing facility
Janssen Pharmaceutical Wallingstown Little Island
Retention for a stainless steel smoking shelter and associated ancillary works at existing facility. The facility is subject to an Integrated Pollution Prevention and a Control License.
Wallingstown Little Island Co. Cork
The construction of a new two storey extension to the existing administration building consisting of an infill first floor within the existing building, a new stairwell to the east along with modifications to the existing north, west and east elevations with associated ancillary works at the existing facility. The facility is subject to an Integrated Pollution Prevention and a Control License.
Wallingstown Little Island Co. Cork
Single storey Drum Store Building (7.8m high) with associated ancillary works at existing facility
Wallingstown Little Island
Demolition of existing two-storey washroom building with an external steelwork staircase, and construction of a three-storey extension with a fourth floor stairs penthouse and plant with access located externally on the roof levels to the existing production building P1 with associated ancillary works at the existing facility
Wallingstown Little Island Co.Cork
Single storey extension, 10.850m high, to the existing Central Utilities Building with a vent stack (15.150m high) and associated ancillary works at existing facility
Wallingstown Little Island
Alterations to permission 03/5456 to include a lift motor room on the roof of the production building and alterations to the Utilities building
Wallingstown Little Island
Construction of a 5 storey API production building, 2 storey admin and laboratory building, utility building & ancillary infrastructure
WALLINGSTOWN, WALLINGSTOWN,
Placing 2 no. air handling units on the roof of the plant 2 building
Wallingstown Little Island
Planning a project of your own?
Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.
Do I Need Permission?