← Back to search

Ballynakilla Bere Island Beara Co. Cork

CONDITIONAL

Planning application 15/512

Cork - Cork County Council

Proposed Development

Construction of agricultural shed with slatted tank for the housing of cattle

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    8 Sept 2015

  2. Decision: CONDITIONAL

    16 Dec 2015

  3. Decision due

    8 Jan 2016

  4. Grant issued

    1 Feb 2016

Application Details

Location
Ballynakilla Bere Island Beara Co. Cork
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Cork County Council

Timeline

Registration Date
8 September 2015Other applications received that week
Status
APPLICATION FINALISED
Decision
CONDITIONAL
Decision Date
16 December 2015
Grant Date
1 February 2016

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

77m
05/8556CONDITIONAL21 Nov 2005

Dwelling

Ballynakilla Bear Island Beara

137m
04/4645CONDITIONAL24 Jun 2004

2 no. dwellinghouses and waste treatment unit

Ballynakilla Bere Island

204m
99/4955WITHDRAWN10 Sept 1999

10 no. dwellinghouses for use as holiday homes/short term letting, sewage treatment plant, service unit & ancillary amenities

BALLYNAKILLA, BALLYNAKILLA,

226m
03/14REFUSED6 Jan 2003

Dwellinghouse

BALLYNAKILLA, BALLYNAKILLA,

226m
02/4170REFUSED20 Sept 2002

Dwelling

BALLYNAKILLA, BALLYNAKILLA,

229m
18/360INCOMPLETED APPLICATION20 Jun 2018

Construction of playground and ancillary site works

Ballynakilla Bere Island Co Cork

229m
18/418CONDITIONAL16 Jul 2018

Construct a playground and ancillary site works

Ballynakilla Bere Island Co. Cork

290m
03/3869CONDITIONAL1 Aug 2003

Dwellinghouse

BERE ISLAND, BERE ISLAND, BALLYNAKILLA,

294m
06/2607CONDITIONAL4 Dec 2006

Demolition of fire damaged rear extension to existing dwellinghouse and construction of new two storey extension to rear

Ballynakilla Bere Island Beara

294m
09/670WITHDRAWN12 Jun 2009

Retention of the following: (a) two storey extension to rear elevation of existing building and (b) change of fenestration to front and rear elevations of existing building and (c) new door to first floor side elevation of existing building and planning permission for the following: (a) demolition of existing ruin extension and construction of single storey extension to existing building, (b) fire escape stairs from first floor of existing building and (c) demolition of existing steel clad lean-to extension to rear of existing dwelling

Ballynakilla Bere Island Bantry Co. Cork

Planning a project of your own?

Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.

Do I Need Permission?