← Back to search

Carrigcleena More Bweeng Co. Cork

CONDITIONAL

Planning application 16/5808

Cork - Cork County Council

Proposed Development

The application site comprises an existing asphalt plant (permitted under planning reg no. 06/4390). The proposed development seeks to provide for the occasional operation of the asphalt plant outside normal working hours up to a maximum of 40 no. days per annum. The proposed development also provides for additions/alterations to the existing asphalt plant including the reorientation of the existing cold feed bins and the provision of a hot storage unit.

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    20 Jul 2016

  2. Decision due

    29 Mar 2017

  3. Decision: CONDITIONAL

    29 Mar 2017

  4. Grant issued

    4 May 2017

Application Details

Location
Carrigcleena More Bweeng Co. Cork
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Cork County Council

Timeline

Registration Date
20 July 2016
Status
APPLICATION FINALISED
Decision
CONDITIONAL
Decision Date
29 March 2017
Grant Date
4 May 2017

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

4m
16/5639INCOMPLETED APPLICATION4 Jul 2016

The application site comprises an existing asphalt plant (permitted under planning reg. 06/4390). The proposed development seeks to provide for the occasional operation of the asphalt pant outside normal working hours up to a maximum of 40 no. days per annum. The proposed development also provides foe additions / alterations to the existing asphalt plant including the reorientation of the existing cold feed bins and the provision of hot storage unit.

Carrigcleena More Bweeg Co. Cork

13m
05/8072INCOMPLETED APPLICATION2 Nov 2005

Retention of asphalt plant with associated feed hoppers, bitumen storage tanks, bunded diesel tank and generator

Carrigcleena Quarry Carrigcleena More Bweeng Mallow

20m
06/4390CONDITIONAL30 Jan 2006

Retention of change of use from quarry to asphalt plant

Carrigcleena Quarry Carrigcleena More Bweeng Mallow

124m
18/7244CONDITIONAL10 Dec 2018

The development consists of the retention of demolition of structures previously used for aggregate storage purposes, comprising of an aggregate storage structure measuring approx. 1,130m2, an aggregate storage structure measuring approx. 135m2 and an aggregate storage structure measuring approx. 180m2. Permission for retention of demolition of a canteen building measuring approx. 109m2 is also being sought, all within an application area of c. 0.164ha.

Carrigcleena More Bweeng Co. Cork

140m
18/5035WITHDRAWN26 Apr 2018

The development will consist of a readymix concrete batching plant and a concrete block production facility comprising of a concrete batching plant, mobile block making machine, block production area (4,285m2), block storage area (1457m2), closed circuit settlement system and all ancillary works within an application area of c. 1.1ha.

Carrigcleena More Bweeng Co. Cork

140m
19/5704INCOMPLETED APPLICATION4 Jul 2019

The development will consist of a readymix concrete batching plant and a concrete block production facility comprising of a concrete batching plant, mobile block making machine, block production area (4,285m2), block storage area (1,457m2), closed circuit settlement system and all ancillary works within an application area of c. 1.1ha.

Carrigcleena More Bweeng Co. Cork

140m
19/5902CONDITIONAL29 Jul 2019

The development will consist of a readymix concrete batching plant and a concrete block production facility comprising of a concrete batching plant, mobile block making machine, block production area (4,285m2), block storage area (1,457m2), closed circuit settlement system and all ancillary works within an application area of c.1.1ha.

Carrigcleena More Bweeng Co. Cork

195m
24/6453Refused23 Dec 2024

Permission for the development will consist of continued use of the existing permitted quarry, ancillary processing plant and facilities, and access beyond 2034 (the existing permitted duration); lateral extension of the existing permitted quarry area to a depth of c.110mOD ( the permitted quarry floor level in the existing quarry) over c.3.7 hectares; construction of a new settlement pond (1000m²) and upgrade of the existing surface water management and settlement pond system at site; realignment of a section of the existing local road to the south of the proposed extension area; overburden storage; operation landscaping including perimeter screening berms around the proposed extension area; restoration of the quarry to natural habitat after-uses; and all related ancillary site works within an overall application area of c.28.8 hectares, all for a period of 20 years and a further 2 years to complete final restoration of the site. The planning application will be accompanied by an Environmental Impact Assessment Report (EIAR) and a Natura Impact Statement (NIS).

Carrigcleena More Bweeng Co. Cork

196m
24/4069WITHDRAWN19 Jan 2024

Permission for the development will consist of continued use of the existing quarry, ancillary processing plant and facilities, and access beyond 2034 (the existing permitted duration); lateral extension of the existing permitted quarry area to a depth of c.110mOD over an extraction area of c. 3.7 hectares; realignment of a section of the existing local road to the South of the proposed extension area; perimeter screening berms; operation landscaping including perimeter screening berms around the proposed extension area; restoration of the quarry to natural habitat after-uses; and all related ancillary site works within an overall application area of c.28.8 hectares and all for a period of 20 years and a further 2 years to complete final restoration of the site. The planning application will be accompanied by an Environmental Impact Assessment Report (EIAR) and a Natura Impact Statement (NIS).

Carrigcleena More Bweeng Co.Cork

205m
19/5031CONDITIONAL25 Apr 2019

Creation of a site access into a forestry plantation to facilitate a timber harvest and haulage operation, the proposed development consists of the creation of a bellmouth/back in loading bay