← Back to search

No. 1 Deer Park Castlelands Mallow Co. Cork

CONDITIONAL

Planning application 16/6848

Cork - Cork County Council

Proposed Development

Construct a dormer bungalow, detached domestic garage and all associated site works

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    15 Nov 2016

  2. Decision due

    11 Apr 2017

  3. Decision: CONDITIONAL

    11 Apr 2017

  4. Grant issued

    18 May 2017

Application Details

Location
No. 1 Deer Park Castlelands Mallow Co. Cork
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Cork County Council

Timeline

Registration Date
15 November 2016Other applications received that week
Status
APPLICATION FINALISED
Decision
CONDITIONAL
Decision Date
11 April 2017
Grant Date
18 May 2017

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

112m
14/5844CONDITIONAL29 Aug 2014

Extension to existing dwelling to provide a self contained single storey, 'granny flat'. The proposed works will include the conversion of the existing garage to residential accommodation and the construction of a new storage shed as well as all associated site works

Plot No. 4, The Deerpark Castlelands St. Joseph's Road Mallow

233m
06/55095REFUSED22 Dec 2006

Construct a dwelling and associated services

Castlelands Td Mallow Co Cork

404m
07/55086CONDITIONAL26 Nov 2007

Permission to retain (1) sun room on the southern gable (2) porch on the front elevation (3) en-suite on the first floor (4) relocation of chimney in living room

Elgannook Bearforest Lower Mallow Co. Cork.

417m
08/55050CONDITIONAL15 Jul 2008

change of house design and layout of site to ref. no. P.D. 55,055/06 for 12 no. 2 storey semi-detached dwellings in accordance with plans and documents submitted

Cortigan Bearforest Lower Td., Mallow Co. Cork.

474m
05/55003Awaiting F.I. Response18 Jan 2005

Construction of 27 dwellings consisting of 5x4 bed detached and 22x3 bed semi-detached units and associated site works, adjacent to permitted development P.D. 2260/PL 70.128878 currently under construction

Collegewood, Ballyellis Mallow Co. Cork.

559m
22/4041INCOMPLETED APPLICATION14 Jan 2022

The construction of 36 no. residential units comprising of 6 no. 3 bed townhouses, 15 no. 2. bed and 15 no. 1 bed units (the 30 no. 1 and 2 bed units are a mix of apartments/ duplex units and simplex units). The units ranging in height from 2 to 3 storeys. Permission is also sought for the construction for the construction of 2 no. commercial units (Unit 01 GFA 200m2 and Unit 02 GFA 125m2) at ground level. The development also includes landscaping, drainage, boundary treatments, 60 no. bicycle spaces, 40 no. car parking spaces (36 to serve the residential units and 4 to serve retail), bin storage, play area, planting/ screening and all associated site works.

Ballydaheen Road/Mill Street Ballydaheen, Ballydahin Td. Mallow Co.Cork

559m
22/4274WITHDRAWN11 Feb 2022

The construction of 36 no. residential units comprising of 6 no. 3 bed townhouses, 15 no. 2. bed and 15 no. 1 bed units (the 30 no. 1 and 2 bed units are a mix of apartments/ duplex units and simplex units). The units ranging in height from 2 to 3 storeys. Permission is also sought for the construction of 2 no. retail units [café and beauty salon] at ground floor level. The development also includes landscaping, drainage, boundary treatments, 60 no. bicycle parking spaces, 40 no. car parking spaces (36 to serve the residential units and 4 to serve the retail), bin storage, play area, planting/ screening and all associated site development works. A Natura Impact Statement will be submitted to the planning authority with this application.

Ballydaheen Road/Mill Street Ballydahin Mallow Co. Cork

562m
10/55012CONDITIONAL3 Mar 2010

Permission is sought for the re-development works to incorporate the demolition of the exiting dwellings, site clearance works and the construction of mixed use development consisting of 2 no. buildings, Car park and associated works. The development shall consist of the following: The demolition of 2 no. dwelling houses on Ballydaheen Road. Building No 1 which will consist of a single storey retail outlet containing a gross floor area of 1747m sq. incorporating goods loading bay and storage to the rear. Building No. 2 is a 2 storey building consisting of 505m sq. of retail floor space subdivided into 3 no. units on the ground floor and 505m sq. of class 2 and 3 office space on the first floor. The car park shall consist of a 2 tier open deck car park to the rear of the site providing 110 no. car parking spaces incorporating lift and stairs access. The construction of ESB substation and meter room building. The development of a new vehicular entrance onto Ballydaheen Road including the alteration of the existing road layout on Ballydaheen Road. The construction of an underground storm water annuation tank, wet well and associated works. All ancillary site landscaping development works including public open space, circulation roads, pavements, public lighting and associated works.

Ballydaheen Mallow Co. Cork.

571m
08/55058WITHDRAWN8 Aug 2008

The demolition of the existing Willis Flats building which bounds the Western boundary of the site and the 2 no. dwelling houses on the Eastern Boundary. Permisson for building No. 1 which faces onto Ballydaheen Road consisting of a four storey building containing a total gross floor area of 10,055m2 incorporating 2,270m2 of retail on the ground floor and a combined total GFA 7,785m2 of both office space class 2 & 3 on the first, second and third floors as shown on the enclosed drawings. Building No. 2 which is the internal courtyard building consisting of five storey building containing a total GFA of 1,645m2 incorporating a 340m2 restaurant on the ground floor and a combined total 1,305mc of office Class 3 space on the first, second, third & fourth floors. Building No. 3 which is the building facing onto Harolds Place consisting of a five storey building of 4,525m2 incorporating 1,395m2 of retail use on the ground floor. The remainder of the building shall consist of 32 no. residential units broke down as follows: 25 no. 2 bed apartments, 6 no. 3 bed apartments and 1 no. 4 bed townhouse. The construction of a two tier underground carpark providing 451 no. car parking spaces, which will exit through a new entrance onto Ballydaheen Road including the alteration of the existing road layout on Ballydaheen Road. All ancillary site landscaping development works including switch building, ESB substation, public & private open space, lift shafts and entrance onto Ballydaheen Road.

Ballydaheen

575m
07/55077CONDITIONAL22 Oct 2007

the construction of a commercial building of 3417.65m sq to include 12 no. retail units (1971 m sq) at basement and ground floors, 10 no. office units (836.5 m sq) at first floor, stores, toilets, circulation areas, 1st floor open terrace and all associated site works including retaining walls and connection to existing foul water, surface water and mains water system

Castlepark Res. Dev. St. Josephs Road Mallow Co. Cork.

Planning a project of your own?

Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.

Do I Need Permission?