Proposed Development

38kV electricity substation and temporary construction compound at a site in the townland of Rathgaskig, ca. 3 km from Ballingeary, Co. Cork. The Substation compound will include the following; hardstanding area; a substation control building; associated electrical plant and equipment; fencing; all ancillary services and facilities and associated works including vehicular access. The proposed development is intended to replace the permitted substation compound associated with the permitted Derragh Wind Farm which consists of an up to 6 no. wind turbine development (Cork County Council Planning Ref: 12/05270 and An Bord Pleanála Reference PL04.245082

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    10 May 2017

  2. Decision: CONDITIONAL

    30 Jun 2017

  3. Decision due

    4 Jul 2017

  4. Grant issued

    11 Aug 2017

Application Details

Location
Rathgaskig near Ballingeary Co. Cork
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Cork County Council

Timeline

Registration Date
10 May 2017
Status
APPLICATION FINALISED
Decision
CONDITIONAL
Decision Date
30 June 2017
Grant Date
11 August 2017

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

424m
12/5270CONDITIONAL8 Jun 2012

The development will consist of a wind farm consisting of 6 turbines (each with a maximum hub height of 100, maximum rotor diameter of 100m, and with a total tip height of 150m), a sub-station including one control building and associated internal equipment, one borrow pit, new internal access roads, upgrading of existing internal access roads, underground cables, and ancillary work.

Derragh, Rathgaskig and Lack Beg Near Ballingeary Co. Cork

424m
12/5098INCOMPLETED APPLICATION23 May 2012

Construction of a wind farm consisting of 6 turbines (each with a maximum hub height of 100m, maximum rotor diameter of 100 m, and with a total tip height of 150m ), a sub-station including one control building and associated internal equipment, one borrow pit, new internal access roads, upgrading of existing internal access roads, underground cables, and ancillary work.

Derragh & Rathgaskig near Ballingeary Co. Cork .

996m
24/4564CONDITIONAL3 Apr 2024

Permission for the construction of a new dwelling house and domestic garage, new entrance, wastewater treatment system together with all other ancillary site works.

Rathgaskig Ballingeary Co. Cork

1.1km
06/8781CONDITIONAL11 Jul 2006

Extension to existing farm building consisting of covered loose bedding area, internal feedway and internal slatted slurry tank

Rathgaskig Ballingeary

1.1km
06/8110INCOMPLETED APPLICATION15 Jun 2006

Extension to existing farm building to include covered loose bedding area, internal feedway and covered slatted tank

Rathgaskig Ballingeary

1.1km
17/6770CONDITIONAL25 Oct 2017

Construction of dwellinghouse, domestic garage and new entrance together with all other ancillary site works

Augeris Ballingeary Co.Cork

1.2km
08/9759CONDITIONAL19 Nov 2008

Dwelling and treatment unit

Augeris Ballingeary

1.2km
08/9397INCOMPLETED APPLICATION22 Oct 2008

Dwelling & treatment unit

Augeris Ballingeary

1.2km
05/9812CONDITIONAL23 Dec 2005

Dwellinghouse and garage

Augeris Ballingeary

1.2km
12/5577CONDITIONAL18 Jul 2012

Construction of dwelling and domestic garage

Augeris Ballingeary Macroom

Planning a project of your own?

Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.

Do I Need Permission?