← Back to search

Leaselands Mallow Co. Cork

CONDITIONAL

Planning application 18/4308

Cork - Cork County Council

Proposed Development

To construct a two storey dwelling and all associated services and siteworks consisting of the removal of an existing entrance and for the relocation of same to form a new shared entrance

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    7 Feb 2018

  2. Decision: CONDITIONAL

    9 Oct 2018

  3. Decision due

    11 Oct 2018

  4. Grant issued

    15 Nov 2018

Application Details

Location
Leaselands Mallow Co. Cork
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Cork County Council

Timeline

Registration Date
7 February 2018
Status
APPLICATION FINALISED
Decision
CONDITIONAL
Decision Date
9 October 2018
Grant Date
15 November 2018

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

38m
06/55087CONDITIONAL18 Dec 2006

Demolition of existing dwelling and the construction of a two storey development consisting of three no apartments, two no one bedroom apartments, on ground floor and one no one bedroom apartment on first floor

Bachelors Walk Mallow Co Cork

38m
06/55050NEW APPLICATION26 Jun 2006

the demolition of existing dwelling. The construction of atwo storey development of four one bedroom apartments, consiting of two no. one bedroom on ground floor

Batchelors Walk Mallow Co. Cork.

38m
08/55016CONDITIONAL14 Mar 2008

permission for the demolition of existing dwelling and the construction of two no. semi-detached two storey style dwellings

Bachelors Walk Mallow Co. Cork.

71m
03/5503CONDITIONAL5 Nov 2003

Residential development- 14 no. dwellinghouses

SPAGLEN RURAL, SPAGLEN RURAL,

114m
08/55014CONDITIONAL7 Mar 2008

permission for alterations and extension to existing dwelling

No. 14 St. Anthonys Park Mallow Co. Cork.

122m
07/55004NEW APPLICATION23 Jan 2007

Construct a dwelling and associated services

No 13 Anthonys Park Mallow Co Cork

122m
06/55005CONDITIONAL2 Feb 2006

to construct a garage and ancillary works

No. 13 St. Anthonys Park Mallow Co. Cork.

127m
22/6814CONDITIONAL19 Dec 2022

Permission for retention of (1) an existing refuse shed (25.3 sqm), (2) Electric vehicle charge point cabinet, (3) above ground 1600 litre LPG tank with associated works. Permission is also sought for (1) an AD BLUE fuel pump cabinet and ancillary 5000 litre above ground AD BLUE tank, (2) the construction of 2.5m high hit and miss fencing to screen existing 2 no. sheds and refuse shed and (3) the removal of condition no.3 attached to planning ref no. 20/4178, which called for the removal of the two sheds, (29 sqm) containing plant associated with the car wash operations on the expiration of the period of 3 no. years beginning on date of the grant of this permission, to allow for the 2 no. sheds to remain on site.

O'Mahony's Centra Spa Glen, Spaglen Td. Mallow Co.Cork

127m
22/6445INCOMPLETED APPLICATION28 Oct 2022

Retention of (1) an existing refuse shed (25.3 Sqm), (2) Electric vehicle charging point cabinet, (3) above ground 1600 litre LPG tank with associated works. Permission is also sought for (1) an AD Blue fuel pump cabinet and ancillary 5000 litre above ground AD Blue fuel tank, (2) the construction of 2.5m high hit and miss fencing to screen existing 2 no. sheds and refuse shed and (3) the removal of condition no. 3 attached to Planning Ref. No. 20/4178, which called for the removal of the two sheds (29 Sqm) containing plant associated with the car wash operations on the expiration of the period of 3 no. years beginning on the date of the grant of this permission, to allow for the 2 no. sheds to remain on site.

O' Mahony's Centra Spa Glen, Spaglen Td Mallow Co. Cork

150m
08/7665CONDITIONAL2 Jul 2008

Demolition of existing Centra supermarket and dwellinghouse, relocation and construction of new supermarket with off licence, storage area, loading dock, ancillary offices, staff facilities, and including plant/service areas, substation and 4 no. individual retail units. All associated site works including car parking, attenuation tank, signage and blocking up existing site entrance and constructing new entrance

Spaglen Mallow

Planning a project of your own?