Proposed Development

  1. (1)
    The construction of a two storey site services building IE40 with roof top plant enclosures.
  2. (2)
    Extension to the existing staff car park to provide an additional 150 permanent car parking spaces
  3. (3)
    The creation of a new vehicular car park entrance gate on the Ballyvrin Road (L3215) northern boundary.
  4. (4)
    All associated site development works including modifications to the internal site roads and site services, construction of external hard standing areas and a single ancillary kitchen store, site lighting and fencing and the formation of landscaping areas, including berms and visual screening with tree planting and contractor’s temporary car park. The new development is on a site to which the Chemicals Act (Control of Major Accident Hazards Involving dangerous Substances) regulations 2015 (S.I 209 of 2015) applies.
View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    18 Jul 2018

  2. Decision due

    11 Sept 2018

Application Details

Location
Ballythomas East, Ballythomas West Horsehill More North, Ballyvrin Lower Dunderrow, Kinsale Co. Cork
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Cork County Council

Timeline

Registration Date
18 July 2018Other applications received that week
Status
INCOMPLETED APPLICATION
Decision
Pending
Decision Due
11 September 2018

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

35m
25/5133Conditional Permission12 Jun 2025

Permission to construct a Biomass Steam Boiler Facility that includes: A) Demolition of existing single storey temporary warehouse building. B) Construction of single storey building with parapet height of 20.3m with part mezzanine floors within. C) A chimney stack with height of 23.15m. D) Above ground pipe rack measuring 55m long x 3.5m wide with an overall height of 11.58m. E) Underground services, drainage and other associated site development works. The proposed development is covered by an existing Industrial Emissions (IE) Directive Licence No. P0009-05 under Part IV of the Environmental Protection Agency Act 1992 (as amended). The proposed development refers to a modification to an establishment to which Major Accident Regulations applies.

Ballythomas East, Ballythomas West, Horsehill More North and Ballyvrin Lower, Dunderrow, Kinsale, Co. Cork.

194m
25/4269INCOMPLETED APPLICATION21 Feb 2025

Permission for construction of an expansion to the existing waste water treatment plant, that includes (a) three number buildings consisting of (1) a single storey precipitation building (8.6m high) that including an open storage area, (2) single storey electrical building (5.4m high), (3) two storey filter press building (9.6m high), (b) process vessels and associated access stairs and platforms, (c) structural steel service racking, (d) underground services, drainage and other associated siteworks. The proposed development is covered by an existing industrial emissions (IE) licence no. P0009-05. The development refers to a modification to an establishment to which a major accident regulation applies.

Ballythomas East, Ballythomas West Horsehill More North, Ballyvrin Lower Dunderrow Kinsale, Co.Cork

286m
16/4320INCOMPLETED APPLICATION16 Feb 2016

(1) A new external boiler flue of height not exceeding 21m above ground level adjacent to the existing IE04 building, (2) Construction of a new external support platform of height not exceeding 9.15m above ground level around the new boiler flue. All associated site development works. The proposed development is covered by the existing Integrated Pollution Control Licence (Licence Register P0009-03). The proposed development is located in an Establishment to which the Major Accidents Directive applies.

Ballythomas East, Ballythomas West Horsehill More, Dunderrow Kinsale Co. Cork

286m
16/4799UNCONDITIONAL12 Apr 2016

(1) A new external boiler flue of height not exceeding 21m above ground level adjacent to the existing IE04 building, (2) Construction of a new external support platform of height not exceeding 9.15m above ground level around the new boiler flue, and all associated site development works. The proposed development is covered by the existing Integrated Pollution Control Licence (Licence Register P0009-03). The proposed development is located in an Establishment to which the Major Accidents Directive applies.

Ballythomas East, Ballythomas West Horsehill More Dunderrow Kinsale

332m
14/6065CONDITIONAL1 Oct 2014

Demolition of existing idled IE3 Production building and ancillary plant and equipment

Ballythomas East, Ballythomas West Horsehill More Dunderrow Kinsale

351m
23/5763CONDITIONAL30 Aug 2023

Permission for the construction of a pedestrian footbridge across an existing stream within the Eli Lily pharmaceutical facility, and associated works. The bridge will have a length of approx. 17.9m (13.1 span plus landing areas of 2.4m at either end) and a two-way 2.4m wide walkway and will be located on a site area of approx. 0.23ha. The application site falls within the Eli Lilly industrial complex, which operates under an Industrial Emissions (IE) licence (P0009-04) under part IV of the Environmental Protection Agency Act 1992 (as amended by the protection of the Environmental Act, 2003) and is also an establishment to which the Chemicals Act (Control of Major Accident Hazards involving Dangerous Substances) Regulations 2015 (S.I. 209 of 2015) applies

Eli Lilly Pharmaceutical Complex Ballythomas East & Ballythomas West Dunderrow Kinsale, Co. Cork

351m
23/5673INCOMPLETED APPLICATION16 Aug 2023

Permission for the construction of a pedestrian footbridge across an existing stream within the Eli Lilly pharmaceutical facility, and associated site works. The bridge will have a length of approx. 17.9m (13.1m span plus landing areas of 2.4m at either end) and a two-way 2.4m wide walkway and will be located on a site area of approx. 0.23ha. The application site falls within the Eli Lilly industrial complex, which operates under an Industrial Emissions (IE) Licence (P0009-04) under Part IV of the Environmental Protection Agency Act 1992 (as amended by the Protection of the Environment Act, 2003) and is also an establishment to which the Chemicals Act (Control of Major Accident Hazards involving Dangerous Substances) Regulations 2015 (S.I. 209 of 2015) applies.

Eli Lilly Pharmaceutical Complex Ballythomas East & Ballythomas West Dunderrow Kinsale Co Cork

510m
24/4715CONDITIONAL24 Apr 2024

Permission for a) A 15.3m high two storey cold storage building, comprising of cold storage warehousing and freezer storage, dock leveller, goods in and out areas with associated mechanical and electrical room on the first floor b) Single storey sub-station, c) Structural steel service racking, d) All road circulation, underground services, drainage and other associated site works. The proposed development is covered by an existing Industrial Emissions (IE) Licence No. P0009-05. The development refers to a modification to an establishment to which a Major Accident Regulation applies.

Ballythomas East Ballythomas West Horsehill More North & Ballyvrin Lower Dunderrow Kinsale Co Cork

540m
03/2560CONDITIONAL29 May 2003

Dwellinghouse

BALLYTHOMAS EAST, BALLYTHOMAS EAST,

581m
23/6601INCOMPLETED APPLICATION21 Dec 2023

Permission for construction of a 2.5 metre wide artificial running track to the perimeter of an existing grassed area adjacent to the main security entrance and a set-down parking area offset from the existing entrance road for 4 vans and 5 cars along with 4 disability parking spaces to include the provision of an electric vehicle charging point and an illuminated directional sign at the entrance to the set-down parking area. The development will include all site works including the provision of underground services and hard landscaping. The proposed development is covered by an existing Industrial Emissions (IE) Licence No. P0009-05. The development refers to a modification to an establishment to which the Major Accident Regulations applies.

Ballythomas East, Ballythomas West, Horsehill More North and Ballyvrin Lower, Dunderrow, Kinsale Co.Cork

The submission window has closed

Observations on this application closed on Tuesday 21 August 2018, five weeks after it was received. The authority cannot accept a late submission.

Planning a project of your own?

Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.

Do I Need Permission?