← Back to search

Clash West Leamlara Co. Cork

CONDITIONAL

Planning application 18/7393

Cork - Cork County Council

Proposed Development

The construction of a calf house, silage slab, effluent tanks and ancillary works.

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    20 Dec 2018

  2. Decision: CONDITIONAL

    21 Feb 2019

  3. Decision due

    22 Feb 2019

  4. Grant issued

    29 Mar 2019

Application Details

Location
Clash West Leamlara Co. Cork
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Cork County Council

Timeline

Registration Date
20 December 2018
Status
APPLICATION FINALISED
Decision
CONDITIONAL
Decision Date
21 February 2019
Grant Date
29 March 2019

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

2m
12/4441CONDITIONAL9 Mar 2012

Construction of a milking parlour and dairy, cubicle house, loose housing area, effluent tanks, silage slab and ancillary works

Clash West Leamlara

125m
25/4879Conditional Permission12 May 2025

Permission for construction of a dwelling, garage, wastewater treatment unit, percolation area and associated works

Clash West Leamlara Co.Cork

157m
09/6631CONDITIONAL5 Aug 2009

Extension to existing buildings consisting of additional classroom & indoor recreational area, together with associated ancillary works

Clash West Leamlara

157m
17/6802INCOMPLETED APPLICATION27 Oct 2017

Construction of an extension to the existing school, together with all associated ancillary works. The extension will consist of 2 resource rooms with an adjoining corridor including an entrance lobby for the school to the west of existing buildings.

Bishop Ahern National School Clash Leamlara Co.Cork

157m
17/6979CONDITIONAL17 Nov 2017

Construction of an extension to the existing school, together with all associated ancillary works. The extension will consist of 2 resource rooms with an adjoining corridor including an entrance lobby for the school to the west of existing buildings

Bishop Ahern National School Clash West Leamlara Co.Cork

157m
15/5811INCOMPLETED APPLICATION14 Aug 2015

Construction of an extension to the existing school, together with all associated ancillary works. The extension will consist of a classroom with an adjoining corridor to the north of existing buildings.

Bishop Ahern National School Clash Leamlara Co. Cork

157m
15/5915CONDITIONAL26 Aug 2015

Construction of an extension to the existing school, together with all associated ancillary works. The extension will consist of a classroom with an adjoining corridor to the north of existing buildings.

Bishop Ahern National School Clash Leamlara

157m
15/4968INCOMPLETED APPLICATION8 May 2015

Demolition of existing roadside fence and entrance walls, construction of a concrete footpath, retaining wall and new fence and ancillary works including safety signage and road markings

Clash West Leamlara

157m
19/6411CONDITIONAL4 Oct 2019

Construction of an extension to the existing school and all associated ancillary works. The extension will consist of a mainstream classroom and resource room to the north of existing buildings with an adjoining corridor along the west linking the existing buildings

Bishop Ahern National School Clash West Leamlara Co. Cork

157m
12/5797CONDITIONAL21 Aug 2012

Extension to existing school together with associated ancillary works. The extension will consist of a resource room.

Clash West Leamlara

Planning a project of your own?

Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.

Do I Need Permission?