Kilpatrick Bandon Co. Cork

CONDITIONAL

Planning application 19/4384

Cork - Cork County Council

Proposed Development

Construction of domestic garage and all associated site development works on site of dwellinghouse under construction under Pl. Reg. No. 17/5504

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    20 Feb 2019

  2. Decision: CONDITIONAL

    25 Jun 2019

  3. Decision due

    2 Jul 2019

  4. Grant issued

    1 Aug 2019

Application Details

Location
Kilpatrick Bandon Co. Cork
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Cork County Council

Timeline

Registration Date
20 February 2019
Status
APPLICATION FINALISED
Decision
CONDITIONAL
Decision Date
25 June 2019
Grant Date
1 August 2019

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

3m
17/5504CONDITIONAL14 Jun 2017

Permission for dwelling house, wastewater treatment system and all associated site development works.

Kilpatrick Bandon Co.Cork

200m
10/5345INCOMPLETED APPLICATION28 May 2010

Construction of a loose shed for the purpose of housing livestock and hay storage, effluent tank and associated site development works and retention of an agricultural roadway and an excavated area

Kilpatrick Bandon

200m
10/5639CONDITIONAL2 Jul 2010

Construction of a loose shed for the purposes of housing livestock and hay storage, effluent tank and associated site development works and retention of an agricultural roadway and excavated area

Kilpatrick Bandon

211m
08/9510CONDITIONAL31 Oct 2008

Construction of loose shed for the purpose of housing livestock and hay storage, 3 no. stables for the purpose of housing horses, 3 no. silos, effluent tank, roofless horse arena, associated site works and retention of agricultural roadway and excavated area

Kilpatrick Bandon

211m
08/9034INCOMPLETED APPLICATION25 Sept 2008

Construction of loose shed for the purpose of housing livestock and hay storage, 3 no. stables for the purpose of housing horses, 3 no. silos, effluent tank, roofless horse arena, associated site works and retention of agricultural roadway and excavated area

Kilpatrick Bandon

232m
04/5657CONDITIONAL22 Jul 2004

Dwellinghouse and garage0.

Kilpatrick Bandon

256m
10/8604INCOMPLETED APPLICATION1 Dec 2010

Erection of 1 no. 500 KW wind turbine (hub height 45.00m), construction of a 25 square metre electrical sub-station, site access road and all ancillary works

Kilpatrick Bandon

256m
17/4630UNCONDITIONAL16 Mar 2017

Erection of 1 no. 500 KW wind turbine (hub height 45 metres), construction of a 25 square metre electrical sub-station, site access road and ancillary works - Extension of duration of permission granted under Planning Reg. No. 10/8695

Kilpatrick Bandon Co.Cork

256m
10/6329INCOMPLETED APPLICATION17 Sept 2010

Erection of 1 no. 500KW wind turbine (hub height 45m) and construction of 25sq.m electrical substation, site access road and all ancillary works

Kilpatrick Bandon

256m
10/8695CONDITIONAL10 Dec 2010

Erection of 1 no. 500 KW wind turbine (hub height 45 metres), construction of a 25 square metre electrical sub-station, site access road and ancillary works