A 5MW solar farm comprising approximately 22,200 photovoltaic panels on ground mounted frames within a site area of 11.25 hectares, 2 no. single storey inverter / transformer stations, 1 no. single storey delivery station, security fencing, CCTV, and all associated ancillary development works.

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    26 Feb 2019

  2. Decision due

    23 Apr 2019

Application Details

Location
Demesne Cloyne Co. Cork
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Cork County Council

Timeline

Registration Date
26 February 2019
Status
INCOMPLETED APPLICATION
Decision
Pending
Decision Due
23 April 2019

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

2m
19/4869CONDITIONAL9 Apr 2019

A 5 MW solar farm comprising approximately 22,200 photovoltaic panels on ground mounted frames within a site area of 11.25 hectares, 2 no. single storey inverter/transformer stations, 1 no. single storey delivery station, security fencing, CCTV, and all associated ancillary development works.

Demesne Cloyne Co. Cork

203m
25/5257Conditional Permission27 Jun 2025

10 Year Planning Permission for a physical extension of c. 562 sq.m to the existing electricity substation compound and will include: 1) Site clearance works including removal of:- a) 1 no. MV poles and associated overhead lines. b) Existing MV busbar and associated electrical equipment. c) Existing 38 kV busbar and associated electrical equipment. d) Existing 2 no. 38 kV/MV transformers. e) All existing site fencing and gates. f) Existing lighting. g) Demolition of existing single storey control building (c. 12 sq.m), h) Existing vegetation along northern, eastern and southern site boundaries. 2) Provision of new electrical plant and equipment including:- a) 1 no. prefabricated control room, GIS and MV module and foundation (98.46 sqm). b) 1 no. prefabricated customer control room module and foundation (24.43 sq.m). c) 3 no. customer transformers and associated bunds. d) 1 no. relocated interface transformer and new bunds. e) 2 no. house transformers and associated bunds. f) Associated and ancillary electrical equipment and other apparatus, including installation of underground cables. g) Site development works including provision of lighting; resurfacing and internal access roads, new fencing and access gates (including new entrance gate onto public road). Provision of site services including drainage and all other ancillary works.

The Existing Cloyne 38kV Substation Demesne Cloyne Co Cork

337m
12/5094CONDITIONAL23 May 2012

Construction of a commercial agricultural shed for the storage and maintenance of agricultural machinery and all associated site works

Demesne Midleton Co. Cork

349m
19/5514CONDITIONAL10 Jun 2019

Construction of a dwelling house, waste water treatment system and new entrance, including all associated site works. Permission consequent on the grant of outline Permission 18/6529

Demesne Cloyne Midleton Co. Cork

349m
18/6529CONDITIONAL25 Sept 2018

Construction of a dwellinghouse, waste water treatment system and new entrance, including all associated ancillary site works

Demesne Cloyne Midleton Co. Cork

360m
24/6370Conditional Permission12 Dec 2024

Permission to 1) demolish the existing single storey extension to the north elevation, 2) demolish 2 no. existing domestic storage sheds, 3) elevational changes to their existing dwelling house, 4) construct new single storey extensions to the south, west and east of their existing dwelling house, 5) construct a car-port to the north elevation of their existing dwelling house, 6) construct a new domestic garage, 7) install a new wastewater treatment system, percolation area and all associated site works

Commons East Cloyne Co.Cork

370m
16/6097CONDITIONAL22 Aug 2016

Construction of a two storey dwelling and water treatment system and ancillary site works

Demesne Cloyne Midleton Co. Cork

412m
15/7012CONDITIONAL30 Dec 2015

Erect 2 no. detached two storey dwellings, together with all associated site development works. This is a change of plan from that submitted with the recent application 15/5962

Demesne Cloyne Co. Cork

412m
15/5962CONDITIONAL2 Sept 2015

To erect 2 no semi-detached dormer type dwellings, together with all associated site development works.

Demesne Cloyne Co. Cork

428m
15/5828CONDITIONAL18 Aug 2015

Closing up existing front door on western elevation of cottage and insert window in its place, construction of new vehicular entrance from the public roadway to the site to replace the existing vehicular entrance which will be closed up, together with all associated site works

Demesne Cloyne Co. Cork

The submission window has closed

Observations on this application closed on Monday 1 April 2019, five weeks after it was received. The authority cannot accept a late submission.

Planning a project of your own?

Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.

Do I Need Permission?