Lands to the east of the R630 in the townlands of Ballincarroonig & Aghada located inside the Aghada Generating Station Ballincarroonig, Whitegate, Co. Cork
INCOMPLETED APPLICATIONPlanning application 19/4631
Cork - Cork County Council
Proposed Development
A c.159 MW capacity battery storage facility located within a secured compound, on a c. 3.2 Ha site, and will – subject to detailed design, commercial and technical considerations; include:
- (a)up to 89 No. battery container units (c.14.7 m x 3.4 m x 3.8 m)
- (b)up to 36 No. inverter units (c.12.2 m x 2.4 m x 2.9 m)
- (c)a substation compound surrounded by a 2.6 m high palisade fence with a dedicated access gate containing a single-storey control building (c. 240 sq.m.) and electrical plant including a bunded transformer (c. 200 sq.m. surrounded by a c.8m high fire wall); a bunded house transformer (c. 20 sq.m. surrounded by a c. 3 m high fire wall) and var support unit (4 m x 3 m x 3.4 m high)
- (d)a single storey battery control building (c. 156 sq.m.)
- (e)a 2.6 m high palisade fence and access gate, with primary access via the existing station and internal roadway network and temporary access via the existing boundary onto the R630
- (f)ancillary structures including lightning masts (c.18 m high) and pole mounted CCTV cameras (c. 8.3 m high)
- (g)and ancillary site works including site clearance works and the installation of site services including underground cables. The planning permission is being sought for a 10 year duration. The planning application is accompanied by a Natura Impact Statement (NIS). Licenced by the Environmental Protection Agency under an Industrial Emissions (IE) Licence [Ref.P0561-05] and a Lower Tier COMAH site and therefore falls under the requirements of the Control of Major Accident Hazard (COMAH) Regulations, 2015.
Application Timeline
Application received
14 Mar 2019
Decision due
8 May 2019
Application Details
- Location
- Lands to the east of the R630 in the townlands of Ballincarroonig & Aghada located inside the Aghada Generating Station Ballincarroonig, Whitegate, Co. Cork
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Cork County Council
Timeline
- Registration Date
- 14 March 2019
- Status
- INCOMPLETED APPLICATION
- Decision
- Pending
- Decision Due
- 8 May 2019
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
A c.159 MW capacity battery storage facility located within a secured compound, on a c. 3.2 Ha site, and will - subject to detailed design, commercial and technical considerations, include: (a) up to 89 No. battery container units (c.14.7 m x 3.4 m x 3.8 m); (b) up to 36 No. inverter units (c.12.2 m x 2.4 m x 2.9 m); (c) a substation compound surrounded by a 2.6 m high palisade fence with a dedicated access gate containing a single – storey control building (c. 240 sq.m.) and electrical plant including a bunded transformer (c. 200 sq.m. with a c. 8m high fire wall on one side); a bunded house transformer (c. 20 sq.m. surrounded on 3 sides by a c. 3 m high fire wall) and var support unit (4 m x 3 m x 3.4 m high); (d) a single storey battery control building (c. 156 sq.m.); (e) a 2.6 m high palisade fence and access gate, with primary access via the existing station and internal roadway network and temporary access via the existing boundary onto the R630; (f) ancillary structures including lightning masts (c. 18 m high) and pole mounted CCTV cameras (c. 8.3 m high); (g) and ancillary site works including site clearance works and the installation of site services including underground cables. The planning permission is being sought for a 10 year duration. A Natura Impact Statement will be submitted to the Planning Authority with the application. Licensed by the Environmental Protection Agency under an Industrial Emissions (IE) License [Ref. P0561-05] and a Lower Tier COMAH site and therefore falls under the requirements of the Control of Major Accident Hazard Regulations (COMAH) Regulations, 2015.
Lands to the east of the R630 in the townlands of Ballincarroonig and Aghada located inside the Aghada Generating Station, Ballincarroonig Whitegate, Co. Cork
Minor modifications and reconfigurations to the previously permitted Battery Energy Storage System (BESS) development (Cork County Council Reg Ref. 19/04891), primarily comprising: (1) Updated layout of the substation compound based on revised electrical requirements to facilitate grid connection; (2) revised battery equipment based on updated battery technology; and (3) ancillary equipment to support the BESS development. The amended design incorporates: a 159 MW capacity BESS facility located within a secured compound, on a c. 3.3 Ha site, and will include: (a) 36 No. battery container unit arrangements on concrete plinths (95 sq.m.; height of 3m); (b) 36 No. inverter / transformer / RMU unit arrangements on concrete plinths (50 sq.m.; height of 4.2m); (c) a substation compound surrounded by a 2.6 m high palisade fence with a dedicated access gate containing: 2 No. control building (c. 240 sq.m. 5.1m high ) and electrical plant including: 2 No. bunded house transformers (c. 200 sq.m. surrounded by 8m high fire wall); 2 No. bunded house transformers (c. 19.8 sq.m. surrounded by 3 m high fire wall) and 2 No. VAR support units on concrete plinths (24 sq.m., 3.4 m high); (d) a 2.6 m high palisade fence and access gate, with primary access via the existing station and internal roadway network and temporary access via the existing boundary onto the R630; (e) ancillary plant equipment and structures including lightning masts (c. 18 m high) and pole mounted CCTV cameras (c. 8.3 m high) and ancillary site works including site clearance works and the installation of site services including underground cables. The planning permission is being sought for a 10 year duration. Licensed by the Environmental Protection Agency under an Industrial Emissions (IE) License [Ref. P0561-05] and a Lower Tier COMAH site and therefore falls under the requirements of the Control of Major Accident Hazard Regulations (COMAH) Regulations, 2015.
Lands to the east of the R630 in the townlands of Ballincarroonig, located inside the Aghada Generating Station, Ballincarroonig, Whitegate Co. Cork
Permission to erect a 36 metre high, free standing lattice telecommunication structure to facilitate the relocation of the existing cellular telemetry equipment from the rooftop of Boiler House No. 1 onto the proposed structure, enclosed within a 2.4 metre high palisade compound
ESB's Aghada Generating Station Ballincarroonig Strand Road Whitegate
Electricity Supply Board (ESB) intend to apply for planning permission for the development of the "Aghada LDES" (Aghada Long Duration Energy Storage) project comprising a Battery Energy Storage System (BESS) with a capacity of up to 300 MW on 4.65 Ha of lands located in the townland of Ballincarroonig, Aghada, County Cork, within the wider ESB landholding. The proposed development will consist of a fenced compound containing a BESS compound and Customer HV Compound. Specifically, the BESS compound will feature up to 200 No. 20 ft battery energy storage system (BESS) enclosures and up to 20 No. Medium Voltage (MV) Skids / Twin Inverter Skids and associated bunds. Associated ancillary equipment includes 1 no. MV switchgear building consisting of 2 no. adjoining prefabricated buildings, 1 no. Control Building, 5 no. LV Switchgear Containers, a fire water tank and pumphouse, Operation and Maintenance site offices (O&M portacabin) including welfare facilities, 3 no. spare parts stores (20-40 ft containers), 1 no. backup diesel generator plinth, an underground fire water retention tank, a surface water soakaway, harmonics structure (if required following testing of equipment), all services connections including electrical, potable water and connections to surface water drains, external lighting poles, CCTV, lighting monopole. The proposed Customer HV Compound will comprise Grid Step-up Transformers and associated bunds and fire walls, 5 No. Auxiliary Transformers and associated bunds, associated electrical equipment including current transformers/voltage transformers (CT/VT) Circuit Breakers, Neutral Earth Resistors, Cable Chairs, and Line Earth Disconnects, external lighting poles, CCTV, lightning monopole. The development proposal also includes a new site access road from the existing Aghada station, access gate, palisade fencing to secure both compounds (2.6m high) and all ancillary site clearance and development works including provision of areas of hard standing, internal access roads, laydown area, car parking and connections to site services and networks.
The townland of Ballincarroonig, Aghada, County Cork, within the wider ESB landholding
The development will consist of: development on a 0.8ha site of a c. 2MW capacity edge computing facility located within a secured compound, and will, subject to a detailed design, commercial and technical considerations, include: (a) 1 no. modular control building (c. 116sq.m. and c .4.1m high). (b) Electrical and computing plant and equipment comprising: (1) 20 No. IT modules (c. 45 sq.m. and c. 3.9 sq.m high with additional roof mounted cooling units), (2) 2 No. LV modules (c. 59 sq.m. and c. 3.8m high), (3) 2 No. battery modules (c.25 sq.m and c. 3.8m high), (4) 1 No. MV module containing bunded and ventilated transformer (c. 29.7 sq.m. and c. 3.8m high) and (5) 7 no. standby generator units (c. 10 sq. m. c. 2.3m high), surrounded by c. 2.6 m high palisade fencing and gates (d) Ancillary site clearance and development works including provision of areas of hard standing, car park area, covered walkway linking all modules and connections to site services networks. Licenced by the Environmental Protection Agency under an Industrial Emissions (IE) Licence [Ref. P0561-05] and a Lower Tier (COMAH) site and therefore falls under the requirements of the Control of Major Accident Hazard Regulations (COMAH) Regulations, 2015
ESB lands to the east of the R630 in the townlands located inside the Aghada Generating Station Ballincarroonig Whitegate, Co. Cork
Development on a a c. 0.8 ha site on ESB lands. The proposed development will consist of: a c. 2 MW capacity edge computing facility located within a secured compound, and will, subject to detailed design, commercial and technical considerations, include: (a) 1 no. modular control building (c. 116 sq. m. and c. 4.1 m high). (b) Electrical and computing plant and equipment comprising: (1) 20 no. IT modules (c. 45 sq. m. and c. 3.9 m high with additional roof mounted cooling units), (2) 2 no. LV modules (c. 59 sq. m. and c. 3.8 m high), (3) 2 no. battery modules (c. 25 sq. m. and c. 3.8 m high), (4) 1 no. MV module containing bunded and ventilated transformer (c. 29.7 sq. m. and c. 3.8m high) and (5) 7 no. standby generator units (c. 10 sq. m. c. 2.3 m high), surrounded by c. 2.6 m high palisade fencing and gates. (d) Ancillary site clearance and development works including provision of areas of hard standing, car park area, covered walkway linking all modules and connections to site services networks. Licensed by the Environmental Protection Agency under an Industrial Emissions (IE) License [Ref. P0561-05] and a Lower Tier COMAH site and therefore falls under the requirements of the Control of Major Accident Hazard Regulations (COMAH) Regulations 2015.
Lands to the east of the R630 in the townlands of Ballincarroonig and Aghada located inside the Aghada Generating Station, Ballincarroonig Whitegate, Co. Cork
the development will consist of replacing approximately 316m of existing 2.4 m high chain link Fence and associated access/emergency gates with 316m of new 2.4m green palisade security fencing/gates and all associated site works
Aghada AGI (Above Ground Installation) Ballincarroonig Aghada Co.Cork
Permission for the replacement of approximately 324m of existing 2.4m high chainlink fencing and associated gates with 324m of new 2.4m high green palisade security fencing/gates and all associated site works.
Aghada Above Ground Installation (AGI) Ballincarroonig Aghada Co. Cork
Single storey store building
Aghada Generating Station Ballincarroonig Whitegate
Construction of first floor extension to side of existing dwellinghouse, extension of duration to permission granted under Planning Ref. No. 09/7304
53 Careystown Woods Ballincarroonig Whitegate
The submission window has closed
Observations on this application closed on Wednesday 17 April 2019, five weeks after it was received. The authority cannot accept a late submission.