Whitegate Refinery Corkbeg Whitegate Midleton, Co. Cork

CONDITIONAL

Planning application 20/4572

Cork - Cork County Council

Proposed Development

The construction of an extension to an existing containment basin and all ancillary development works at their existing oil refinery facility. Ancillary site works to include a temporary stockpile, gabion wall along the northern boundary of the proposed catchbasin slope and pipe rack for an existing pipeline. Access to the proposed development will be via the existing entrances to the refinery facility from the R630. A Natura Impact Statement (NIS) has been prepared and will be submitted to the Planning Authority with the application. The proposed development is for modifications to an establishment to which the Major Accident Directive applies. The proposed development is for the purposes of an activity requiring an Integrated pollution control licence [Industrial emissions Directive (IED) Licence].

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    19 Mar 2020

  2. Decision due

    1 Feb 2021

  3. Decision: CONDITIONAL

    1 Feb 2021

  4. Grant issued

    8 Mar 2021

Application Details

Location
Whitegate Refinery Corkbeg Whitegate Midleton, Co. Cork
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Cork County Council

Timeline

Registration Date
19 March 2020Other applications received that week
Status
APPLICATION FINALISED
Decision
CONDITIONAL
Decision Date
1 February 2021
Grant Date
8 March 2021

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

40m
22/5173CONDITIONAL20 May 2022

The construction of a containment basin, pipework with associated pipe platforms and all ancillary development works at the existing oil refinery facility. A Natura Impact Statement (NIS) has been prepared and will be submitted to the Planning Authority with the application. The proposed development is for modifications to an establishment to which the Major Accident Directive applies. The proposed development is for the purposes of an activity requiring an integrated pollution control licence [Industrial Emissions Directive (IED) Licence].

Whitegate Refinery Corkbeg Whitegate Midleton, Co. Cork

965m
07/9925INCOMPLETED APPLICATION27 Jul 2007

Construction of 220kV switching station compound comprising surge arrestors, voltage transformers, line earth disconnects, circuit breaker, associated single storey control building, site roads, entrance gate and fencing

Aghada Generating Station Aghada

965m
07/10507CONDITIONAL24 Aug 2007

Construction of 220kV switching station (tail station) compound comprising of surge arrestors, voltage transformers, line earth disconnects, circuit breaker, single storey control building, site roads, entrance gate and fencing

Generating Station Ballincarroonig Aghada

980m
03/2705CONDITIONAL4 Jun 2003

Dwellinghouse

CORKBEG, CORKBEG,

1.0km
10/8114CONDITIONAL4 Oct 2010

Construction of a new Amine and Sulphuric Acid Plant consisting of a 28 metre high (including pipework) above ground level open steel structure incorporating an exhaust stack of 40 metres height above ground level and a stand-alone aluminium clad steel tower, T-1003, 30metres in height (including pipework) above ground level. The proposed development is for the purposes of an activity which requires an integrated pollution prevention and control licence. The proposed development relates to modifications to an establishment within the meaning of Part 11 of thses Regulations (Major Accident Directive)

Corkbeg Whitegate

1.1km
09/4798REFUSED13 Mar 2009

Retention of existing tyre/puncture repair unit & associated signage

Main Street Corkbeg Whitegate

1.1km
21/6867INCOMPLETED APPLICATION21 Oct 2021

1) The rebuilding of an existing weather damaged and dilapidated pier; 2) the construction of new perimeter pier walls and a new ground surface to the new pier; 3) the placement of a prefabricated kiosk for casual, take-away retail, on the new pier surface; 4) the preparation of a Natura Impact Statement including all associated site works.

Middle Pier Mosestown Whitegate Midleton, Co. Cork

1.1km
21/7032CONDITIONAL10 Nov 2021

1)The rebuilding of an existing disused and damaged pier; 2) the construction of new perimeter pier walls and a new ground surface to the new pier; 3) the placement of a prefabricated kiosk on the new pier surface for casual retail in the form of take-away barista coffee and food snacks prepared off-site; 4) an external seating area; 5) the preparation of a Natura Impact Statement. The Natura Impact Statement will be submitted to the planning authority. The development will include all associated site works.

Middle Pier Mosestown Whitegate Midleton, Co. Cork

1.1km
23/4013Conditional Permission11 Jan 2023

Change of plan to planning application granted under planning reference 21/7032. the change of plan allows for ; 1) the addition of a customer toilet and associated floor plan and elevational changes to accommodate same; 2) the placement of a prefabricated permanent building on the existing pier surface for café retail use; 3) an external seating area; 4) A Natura Impact Statement will be submitted to the Planning Authority with the application.

Middle Pier, Mosestown Whitegate Midleton Co.Cork

1.1km
26/0703Grant with Conditions20 Mar 2026

Permission for the construction of a modest glass/aluminum structure to enable covered outdoor seating (18m2). The proposed development is ancillary to the existing café use permitted under planning ref 23/4013 and 21/7032. Permission is sought for the development described and all associated site works

Middle Pier, Mosestown, Whitegate, Monkstown, Cork, P25F5T6

Planning a project of your own?

Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.

Do I Need Permission?