Proposed Development
To construct a dwelling house and all associated site works.
Application Timeline
Application received
2 Oct 2020
Decision: CONDITIONAL
5 Feb 2021
Decision due
10 Feb 2021
Grant issued
11 Mar 2021
Application Details
- Location
- Coomnaclohy Ballyvourney Co. Cork
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Cork County Council
Timeline
- Registration Date
- 2 October 2020
- Status
- APPLICATION FINALISED
- Decision
- CONDITIONAL
- Decision Date
- 5 February 2021
- Grant Date
- 11 March 2021
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
To construct a dwelling house and associated site works.
Coomnaclohy Ballyvourney Co. Cork
Permission for the construction of an agricultural storage shed and all ancillary site works
Coomnaclohy Ballyvourney Co. Cork
Dwellinghouse, detached garage and installation of sewage treatment unit
Coomnaclohy Ballyvourney
Dwellinghouse (change of plan from that granted under Pl. Reg. No. 08/4457)
Coomnaclohy Ballyvourney
Dwellinghouse
Coomnaclohy Ballyvourney
Dwellinghouse
Coomnaclohy Ballyvourney
Completion of dwellinghouse as permitted under Pl. Reg. No. 06/10068
Coomnaclohy Ballyvourney Co. Cork
Planning permission to construct a new dwelling house
Coomnaclohy, Ballyvourney, Co.Cork
Construction of new dwelling house, domestic garage, proprietary treatment unit, polishing filter, new entrance together with all other ancillary site works.
Slievereagh Ballyvourney Co. Cork
Renewable energy development consisting of the provision of a 7 turbine wind farm, solar photovoltaic array, electricity substation, battery storage compound and all associated works consisting of the following, i. Up to 7 wind turbines with an overall blade tip height of up to 150 metres and all associated foundations and hard-standing areas; ii. Up to 70,000sq.m solar photovoltaic array, with up to 17 associated inverters and 2 no. control cabins; iii. 1 no. borrow pit, iv. 1 No. permanent meteorological mast with a maximum height of up to 100 meters; v. Upgrade of existing and provision of new site access roads, vi. 1 no. 38kV electrical substation with 1 no. control building with welfare facilities, associated electrical plant and equipment security fencing and waste water holding tank; vii battery storage compound accommodating 4 no. battery storage containers, security fencing, and associated electrical plant and equipment, viii. Forestry felling ix. 1 no. temporary construction compound, x. Site drainage xi. All associated internal underground cabling; xii. 38kV underground grid connection cabling; xiii. All associated site development and ancillary works. The proposed development will have an operational life of 30 years from the date of commissioning of the development and the application seeks a ten year planning permission. An Environmental Impact Assessment Report (EIAR) and a Natura Impact Statement (NIS) have been prepared in respect of the proposed development.
Slievereagh and Coomnaclohy Ballyvourney Co. Cork
Planning a project of your own?
Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.
Do I Need Permission?