← Back to search

Gortnalicky Clondrohid Macroom Co. Cork

CONDITIONAL

Planning application 20/6150

Cork - Cork County Council

Proposed Development

The construction of (1) new storage warehouse, (2) canopy and (3) associated siteworks all located at the west of their site.

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    2 Oct 2020

  2. Decision: CONDITIONAL

    16 Apr 2021

  3. Decision due

    19 Apr 2021

  4. Grant issued

    20 May 2021

Application Details

Location
Gortnalicky Clondrohid Macroom Co. Cork
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Cork County Council

Timeline

Registration Date
2 October 2020
Status
APPLICATION FINALISED
Decision
CONDITIONAL
Decision Date
16 April 2021
Grant Date
20 May 2021

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

53m
18/5367CONDITIONAL25 May 2018

Construction of combined heat and power plant consisting of a generator house, electrical room, external boiler and ancillary equipment.

Gortnalicky Clondrohid Macroom Co. Cork

86m
12/6469INCOMPLETED APPLICATION4 Dec 2012

Retention of existing agricultural entrance

Gortnalicky Clondrohid Macroom Co.Cork

86m
12/6611CONDITIONAL21 Dec 2012

Retention of existing agricultural entrance

Gortnalicky Clondrohid Macroom Co.Cork

120m
12/4319INCOMPLETED APPLICATION24 Feb 2012

Erection of an extension to the existing pallet making facility, incorporating pallet stores, packaging store, timber planing room and associated site works

Gortnalicky Clondrohid Macroom Co. Cork

151m
12/5714CONDITIONAL9 Aug 2012

(a) Permission to erect extensions to the existing pallet making facility/buildings, incorporating pallet store areas and packaging store area, extension to existing saw/pallet making shed for timber planing room area, extension to existing kiln building to house 2 no. additional drying kilns, construction of new offices and amenities building (b) permission for construction of new site entrance including access road, new road side wall and railings to close off existing site entrance at the western side of the site, new percolation area to dispose of waste water from existing waste water treatment plant, concrete yard areas, internal roads, car parking areas and associated site works. (c) Retention of existing storage and manufacturing facility consisting of mulch building, existing kiln building with attached services building, saw/pallet making shed, pallet repairing building with attached canteen and store areas, detached toilet block building, (d) Retention of use of existing dwelling as offices, (e) Retention of existing fire fighting water storage tank, associated pump house and adjoining storage shed, (f) Retention of amalgamated building areas including kiln areas, service corridor, canopies, ESB sub-station, storage areas, pallet making and machine areas, timber planing areas, sawdust baling area, workshop area with overhead canteen/store/I.T. area, (g) Retention of storage yard and concrete areas, drainage systems and retaining walls, existing waste water treatment unit, re-contoured ground used to store excavated subsoil, (h) Retention of 9 no. existing prefabricated cabins comprising of 5 no. offices, 1 no. store, 1 no. canteen and 2 no. toilets and all associated siteworks and services

Gortnalicky Clondrohid Macroom Co. Cork

151m
12/5543INCOMPLETED APPLICATION13 Jul 2012

(a) Retention of existing storage and manufacturing buildings, (b) retention of existing storage yards, roads, drainage systems and retaining walls, (c) retention of existing waste water treatment unit, (d) retention of existing dwelling for use as offices, (e)retention of recontoured ground used to store excavated subsoil, (f) retention of existing prefabricated offices on a temporary basis for a maximum period of five years, (g) retention of existing fire fighting water storage tank and associated pump house, (h) permission to erect an extension to the existing pallet making facility, incorporating pallet stores, packaging store, timber planning room, 2 no. additional drying kilns, concrete yards and roads, (i) construction of new offices and amenities block including car parking area, (j) construction of new site entrance including access road and construction of new road side wall and railings to close the existing site entrance at the western end of the site, (k) construction of new percolation area to dispose of waste water from the existing waste water treatment unit, (I )landscaping and associated site works

Gortnalicky Clondrohid Macroom Co. Cork

192m
18/7023CONDITIONAL19 Nov 2018

Construction of the following: (a) electrical sub-station (b) 4 no. timber drying kilns and (c) associated siteworks at existing pallet making facility

Gortnalicky Clondrohid Macroom Co. Cork

201m
22/5326CONDITIONAL8 Jun 2022

(1) Construction of the following (a) New Pallet Storage Warehouse (Building A), (b) Hard Standing Areas, (c) Surface Water Attenuation System and Associated Siteworks and (2) Retention of the following buildings: (a) Storage Building (Building B), (b) Storage Canopy (Building C), (c) Storage Building (Building D), (d) Single Storey Office Building (Building E), all located at their site.

Gortnalicky and Caherkeegane Clondrohid Macroom Co. Cork

241m
04/2309CONDITIONAL7 Apr 2004

Construction of slatted cattle shed and retention of machinery storage shed

Gortnalicky Clondrohid Macroom

241m
23/4373CONDITIONAL3 Mar 2023

Permission for (1) retention and completion of the pallet storage warehouse (building A), (change of warehouse location, building moved circa 25m to the west and 10m to the north, and retention of a single storey extension attached to the northern elevation of the warehouse to that permitted under Pl.Reg.No. 22/5326). (2) Permission for the construction of (a) New Storage Warehouse, (b) Canopy, (c) Surface Water Attenuation system and associated site works, all located at their site.

Gortnalicky & Caherkeegane Clondrohid Macroom Co.Cork

Planning a project of your own?

Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.

Do I Need Permission?