Dunisky Lissarda Macroom Co. Cork

REFUSED

Planning application 20/6151

Cork - Cork County Council

Proposed Development

  1. (1)
    The development of a new storage yard for composite pallet blocks located to the west of the existing composite pallet block factory to include the following:
    1. (a)
      new entrance
    2. (b)
      surface water attenuation tank
    3. (c)
      weighbridge
    4. (d)
      associated roads, siteworks and drainage
  2. (2)
    the installation of a fire water tank in the main factory yard
  3. (3)
    the installation of new air drying system and filters located on the main factory yard including a roof over same.
View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    2 Oct 2020

  2. Decision due

    21 Jan 2021

  3. Decision: REFUSED

    21 Jan 2021

Application Details

Location
Dunisky Lissarda Macroom Co. Cork
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Cork County Council

Timeline

Registration Date
2 October 2020Other applications received that week
Status
APPLICATION FINALISED
Decision
REFUSED
Decision Date
21 January 2021

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

41m
19/5187WITHDRAWN13 May 2019

A new storage yard for pallet spacer blocks located to the west of the existing pallet spacer block factory to include the following: (a) new entrance (b) surface water attenuation tank, (c) weighbridge and (d) associated roads, siteworks and drainage.

Dunisky Lissarda Macroom Co. Cork

43m
10/5963CONDITIONAL3 Aug 2010

Timber sound barrier with structural support on western site boundary, toilet & pump house on eastern elevation at existing wood chip processsing plant

Dunisky Lissarda Macroom

43m
09/6182CONDITIONAL1 Jul 2009

Retention of canopy over intake area on eastern elevation, electrical room/ESB substation, relocation of fire water reserve tank, additional filters and machinery on the western elevation and surface water separator at existing wood chip processing plant

Dunisky Lissarda Macroom

43m
09/5894INCOMPLETED APPLICATION9 Jun 2009

Retention of canopy over intake area on eastern elevation, electrical room/ESB substation, relocation of fire water reserve tank, additional filters & machinery on the western elevation & surface water separator

Dunisky Lissarda Macroom

43m
06/9614CONDITIONAL9 Aug 2006

Construction of factory for manufacturing of pallet spacer blocks from wood chips to include hardstanding area, car parking, lorry parking, weighbridge, office and installation of proprietary treatment unit

Dunisky Lissarda

46m
17/5076INCOMPLETED APPLICATION3 May 2017

Construction of a new office.

Dunisky Lissarda Macroom Co. Cork

46m
17/5623CONDITIONAL28 Jun 2017

(1)Construction of a new office and (2) Retention of concrete base foundation for new office

Dunisky, Lissarda Macroom Co.Cork

46m
16/5219CONDITIONAL20 May 2016

New canopy to cover recycled wood raw materials in existing yard

Dunisky Lissarda Macroom Co. Cork

50m
17/5213INCOMPLETED APPLICATION17 May 2017

(1) New canopy to cover recycled wood in existing yard and (2) Extension to existing canopy on eastern elevation.

Dunisky Lissarda Macroom Co. Cork

50m
17/5449INCOMPLETED APPLICATION9 Jun 2017

(1) New canopy to cover recycled wood in existing yard and, ( 2) Extension to existing canopy on eastern elevation of existing factory building

Dunisky Lissarda Macroom Co. Cork

Planning a project of your own?