Boherbue Co op Stores and Supervalu, Gneeves Boherbue Mallow Co. Cork
INCOMPLETED APPLICATIONPlanning application 20/6979
Cork - Cork County Council
Proposed Development
The installation of a rooftop photovoltaic solar panel array totalling 1172 sqm. and all associated site works.
View the full application file on the council's planning portal →Application Timeline
Application received
22 Dec 2020
Decision due
24 Feb 2021
Application Details
- Location
- Boherbue Co op Stores and Supervalu, Gneeves Boherbue Mallow Co. Cork
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Cork County Council
Timeline
- Registration Date
- 22 December 2020
- Status
- INCOMPLETED APPLICATION
- Decision
- Pending
- Decision Due
- 24 February 2021
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
i) demolition of part of the existing canopy at the front/side of the existing shop/forecourt and demolition of the existing trolley bay at the side of the existing shop ii) to construct extension to the front and side of the existing supervalu shop consisting of new entrance, coffee dock and trolley zone with side entrance along with new canopy along part of the western side of the shop and iii) demolish existing wall between existing carpark at the west and extend the carparking area into the storage yard at the side/back of the complex and construct new wall/fence between the carpark and the storage yard all within their existing retail complex. Extension of Duration to Permission granted under Pl.Ref.No. 17/7335.
Gneeves Boherbue Mallow Co Cork
i) Demolition of part of the existing canopy at the front/side of the existing shop/forecourt, ii) to construct extension to the front and side of the existing Supervalu shop consisting of new entrance, coffee dock and trolley zone with side entrance along with new canopy along part of the western side of the shop and iii)demolish existing wall between existing carpark at the west and extend the carparking area into the storage yard at the side/back of the complex and construct new fence between the carpark and the storage yard all within their existing retail complex.
Gneeves Boherbue Mallow Co. Cork
Permission for I) demolition of part of the existing canopy at the front/side of the existing shop/forecourt and demolition of the existing trolley bay at the side of the existing shop ii) to construct extension to the front and side of the existing supervalu shop consisting of new entrance, coffee dock and trolley zone with side entrance along with new canopy along part of the western side of the shop and iii) demolish existing wall between existing carpark at the west and extend the carparking area into the storage yard at the side/back of the complex and construct new wall/fence between the carpark and the storage yard all within their existing retail complex
Gneeves Boherbue Mallow Co. Cork
Retention of the change of use of 3 no. existing retail units and access corridor within their existing retail complex to postal sorting office and changes to the internal layout of the units.
Gneeves Boherbue Mallow Co. Cork
The installation of a rooftop photovoltaic solar panel array totalling 1172 sqm and all associated site works.
Boherbue Co Op Stores and Supervalu Gneeves Boherbue Mallow, Co. Cork
Construction of two storey extension to shop premises/dwelling and retention of existing single storey extension
Gneeves Boherbue Mallow
Erection of a covered bus shelter
Gneeves Boherbue Co. Cork
To demolish disused dwelling house and domestic garage.
Gneeves Boherbue Mallow Co. Cork
To demolish disused dwelling house and domestic garage.
Gneeves Boherbue Mallow Co. Cork
Retention of i) enclosed cold room within existing basement, ii) cold room constructed at the side of the existing building (majority of the cold room is under an existing flat roofed area) & iii) canopy at the front of the building.
Gneeves Boherbue Mallow Co. Cork
Affected by this application?
Submissions can be made for 5 weeks from the date the application was received. Only material planning grounds count. Build a valid submission letter in minutes.
Make a Submission or ObjectionPlanning a project of your own?
Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.
Do I Need Permission?