← Back to search

Lysaghtstown Curragh and Ballyleary Midleton Co. Cork

CONDITIONAL

Planning application 21/5089

Cork - Cork County Council

Proposed Development

A 10 year planning permission for 2 no.33kv underground electricity interconnector cables of c.2.59 km in length to be provided predominantly in excavated trenches and include associated underground ducting, joint bays, communication chambers and all associated site development and reinstatement works. The proposed development provides for a change of plan to part of the solar farm previously permitted under Cork County Council planning reference 18/6769 (as amended by 20/6891), 19/5729 and 19/6882 and will provide for the laying of underground interconnector cabling between inverters permitted under these applications. The works will be carried out within the solar farm boundary, on private lands and within the public road. A Natura Impact Statement (NIS) has been prepared and will be submitted to the Planning Authority with the application.

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    26 Apr 2021

  2. Decision: CONDITIONAL

    20 Oct 2021

  3. Decision due

    21 Oct 2021

  4. Grant issued

    23 Nov 2021

Application Details

Location
Lysaghtstown Curragh and Ballyleary Midleton Co. Cork
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Cork County Council

Timeline

Registration Date
26 April 2021
Status
APPLICATION FINALISED
Decision
CONDITIONAL
Decision Date
20 October 2021
Grant Date
23 November 2021

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

289m
14/4670CONDITIONAL3 Apr 2014

Extension of use of existing agricultural sheds, silage pits and slurry tanks to include the storage of wood pulp fertiliser prior to spreading on surrounding lands

Lysaghtstown Carrigtwohill Co.Cork

319m
13/4750WITHDRAWN23 Apr 2013

Change of use of existing agricultural shed to agricultural store to include the storage of agricultural machinery, organic fertilisers such as granular fertiliser, sludge fertilisers, biosolids and soil conditioners

Curragh Midleton Co.Cork

328m
21/4787INCOMPLETED APPLICATION29 Mar 2021

A 10 year planning permission for 2 no.33kv underground electricity interconnector cables of c.2.59 km in length to be provided predominantly in excavated trenches and include associated underground ducting, joint bays, communication chambers and all associated site development and reinstatement works. The proposed development provides for a change of plan to part of the solar farm previously permitted under Cork County Council planning reference 18/6769 (as amended by 20/6891), 19/5729 and 19/6882 and will provide for the laying of underground interconnector cabling between inverters permitted under these applications. The works will be carried out within the solar farm boundary, on private lands and within the L-7634 public road. A Natura Impact Statement (NIS) has been prepared and will be submitted to the Planning Authority with the application.

Lysaghtstown Curragh and Ballyleary Midleton Co. Cork

422m
16/4135CONDITIONAL29 Jan 2016

To extend single storey dwellinghouse, modify the windows and doors on the existing structure, construct a new vehicular entrance from the public roadway, install an on-site sewage treatment system, together with all associated site development works

Ballyrichard Beg Carrigtwohill Co. Cork

508m
07/11800CONDITIONAL19 Oct 2007

Two storey extension to cottage, construction of garage and installation of septic tank

Willow Tree Cottage Ballyrichard Beg Carrigtohill

512m
20/6891Conditional Permission13 Jan 2021

A 10 year planning permission for a solar farm consisting of circa 14,600 m2 of solar panels on ground mounted frames, 2 no. single storey electrical inverter/transformer stations, battery storage container, battery control unit, security fencing, satellite pole, CCTV, access tracks, upgrade to existing agricultural field entrance, temporary construction compound, landscaping and all associated ancillary development works. The proposed development is a change of plan to part of the solar farm previously permitted under Cork County Council planning reference 18/6769 and will provide for the omission of the previously permitted 38kV substation and a net decrease in overall panel area of circa 10,800 m2 from that permitted under 18/6769. Construction and operational access will be via the L-7634. The operational lifespan of the solar farm will be 35 years. A Natura Impact Statement (NIS) has been prepared and will be submitted to the Planning Authority with the application.

Lysaghtstown Midleton Co. Cork

556m
17/7440CONDITIONAL22 Dec 2017

Construction of a single storey extension to the front of the existing dwellinghouse, alterations to existing elevations and all associated site works.

Ballyrichard Beg Midleton Co. Cork

557m
08/7965CONDITIONAL18 Jul 2008

Alterations, ground floor and first floor extension with solar panels to existing single storey dwellinghouse, detached garage and associated site works

Ballyrichard Beg Carrigtohill

557m
08/7404INCOMPLETED APPLICATION20 Jun 2008

Alterations and extensions to detached dwelling to include a complete loft conversion including dormer windows, elevational alterations, single storey rear extension, the addition of solar panels, construction of detached garage and associated site works

Ballyrichard Beg Carrigtwohill

561m
18/6769CONDITIONAL19 Oct 2018

Permission for a solar farm consisting of circa 235,500 m2 of solar panels on ground mounted frames, 1 no. single storey 38 kV substation and associated electrical compound, 15 no. single storey electrical inverter/transformer stations, battery storage module and associated equipment container, security fencing, satellite pole, CCTV, landscaping and all associated ancillary development works. Construction and operational access will be via existing field entrances from the L-7634. The operational lifespan of the solar farm will be 35 years.

Lysaghtstown Co. Cork .

Planning a project of your own?

Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.

Do I Need Permission?