Proposed Development
The construction of a two storey value added seafood factory building with R&D and ancillary office accommodation to the first floor, complete with the following
- (i)signage
- (ii)car, cycle and motorcycle parking
- (iii)internal access roadways, yard area with dock levellers, w.c. and shower facilities, back-up generators, and bunded fuel tanks
- (iv)fire water storage tank and associated pumps
- (v)substation
- (vi)security gates and fencing (vii) 1 no. access to the estate road
- (viii)underground storm water attenuation, and all associated site development and landscaping works.
Application Timeline
Application received
23 Mar 2022
Decision: CONDITIONAL
5 Aug 2022
Decision due
8 Aug 2022
Grant issued
20 Sept 2022
Application Details
- Location
- Barnahely Ringaskiddy Co. Cork
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Cork County Council
Timeline
- Registration Date
- 23 March 2022
- Status
- APPLICATION FINALISED
- Decision
- CONDITIONAL
- Decision Date
- 5 August 2022
- Grant Date
- 20 September 2022
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
The construction of a two storey value added seafood factory building with R&D and ancillary office accommodation to the first floor, complete with the following (i) signage (ii) car, cycle and motorcycle parking; (iii) internal access roadways, yard area with dock levelers, w.c. and shower facilities, back-up generator, pump house and water storage tank; (iv) substation; (v) security gates and fencing (vi) 1 no. access to the estate road; (vii) effluent treatment system, and all associated site and development and landscaping works
Barnahely Ringaskiddy Co.Cork
Permission for retention of an ESB substation and generator in revised position to that permitted as per reg. ref 22/4629
Barnahely Ringaskiddy Co.Cork
Works will include the construction of a new 2 storey L-shaped building to the east of the existing Manufacturing Building. The new building will be connected to the existing Manufacturing Building via a new link corridor and will comprise of storage areas, engineering workshop and parts storage with limited office and sanitary accommodation. The works will also include associated site development works, including underground service modifications, provision of new internal yard area fencing, internal car park construction, modification to existing to internal car park and demolition of 122sq.m of single storey temporary office accommodation. The proposed development is covered by an existing Industrial Emissions License No. P08640-01.
Ballintaggart Shanbally Ringaskiddy Co. Cork
Retention of a 70.2 square metre single storey security building with a maximum height of 3.78m and associated site development works. The proposed development is covered by an existing Industrial Emissions License No. PO864-01
Ballintaggart Shanbally Ringaskiddy Co. Cork
Permission for 1) The demolition of part section of the existing laboratory and existing carpark spaces, 2) The construction of a new four storey laboratory expansion to the south of the existing site buildings, new entrance canopy and associated site works. Permission for retention is sought to retain an existing single storey modular building to the east of the site for use as a wellness centre. The proposed development is covered by an existing Industrial Emissions Licence no. P0864-01.
Ballintaggart Shanbally Ringaskiddy Co.Cork
The works will include the construction of a new electrical building, emergency back-up electrical power generation, an associated containment bund, screening and associated site development works including minor modifications to internal roads and drainage. The proposed development is covered by an external industrial emissions license no. P0864-01
Ballintaggart Shanbally Ringaskiddy Co.Cork
Works will include the construction of a new 2 storey L-shaped building to the east of the existing Manufacturing Building. The new building will be connected to the existing Manufacturing Building via a new link corridor and will comprise of storage areas, engineering workshop and parts storage with limited office and sanitary accommodation. The works will also include associated site development works, including underground service modifications, provision of new internal yard are and fencing, internal car park construction and the demolition of 122sq.m of single storey temporary office accommodation. The proposed development is covered by an existing Industrial Emissions License No. P08640-01.
Ballintaggart Shanbally Ringaskiddy Co. Cork
The development shall include the construction of a new two-storey electrical substation building, access platforms and stairs, foundations and ground works, electrical ducting and associated works. The proposed development is covered by an existing Industrial Emissions License No. P0864-01.
Ballintaggart, Shanbally, Ringaskiddy, P43 R298
Construction of Monoclonal Antibodies, Small Scale biotechnology facility comprising of three storey manufacturing building with penthouse plant room on third floor level, two storey administration/laboratory wing and warehouse wing, external utilities yard to west of facility, a detached station/guard house , internal ring road, upgrading of existing car park to provide 187 no. staff car parking spaces, provision for 14 no. visitor car parking spaces, landscaping, palisade fencing to site perimeter and decorative fence to South building facade ,signage , sewage treatment unit and all associated site works and services
Ballintaggart
Extension to existing manufacturing building consisting of: (1) Extension with atrium for office/administrative use to part of western and to southern elevation, (2) 3 no. separate extensions on western and southern elevations of warehouse area of building for lobby use, airlock area and general warehouse use and associated site development works including car park, internal road realignment and the provision of new fencing, gate and barriers and the demolition of an existing security building (guard house) and existing staircase area to southern elevation of main building.
Ballintaggart Townland Shanbally Ringaskiddy Co. Cork
Planning a project of your own?
Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.
Do I Need Permission?