Proposed Development

Permission for to

  1. (i)
    demolish the existing vacant warehouse, vacant shed and associated boundary walls on the eastern side of the existing chilled storage building
  2. (ii)
    relocate existing fire escape door from the eastern corner of the existing chilled storage building to the northern side of the existing chilled storage building
  3. (iii)
    the construction of a proposed extension to the existing chilled storage building with a goods intake area with 2 no. dock levellers on the eastern side of the proposed extension and eternal plant on the northern side (rear) of the proposed extension and all associated site works
View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    25 Mar 2022

  2. Decision due

    19 May 2022

Application Details

Location
Orchard Warehousing & Cold Storage Cobh Cross Industrial Estate Killacloyne, Carrigtwohill Co.Cork
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Cork County Council

Timeline

Registration Date
25 March 2022
Status
INCOMPLETED APPLICATION
Decision
Pending
Decision Due
19 May 2022

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

0m
22/5118INCOMPLETED APPLICATION16 May 2022

(i) demolish the existing vacant warehouse, vacant shed and associated boundary walls on the eastern side of the existing chilled storage building (ii) relocate the existing fire escape door from the eastern corner of the existing chilled storage building to the northern side of the existing chilled storage building (iii) the construction of a proposed extension to the existing chilled storage building with a goods intake area with 2 no. dock levelers on the eastern side of the proposed extension and external plant on the northern side (rear) of the proposed extension and all associated site works

Cobh Cross Industrial Estate Killacloyne Carrigtwohill Co Cork

0m
22/5395Conditional Permission17 Jun 2022

(i) demolish the existing vacant warehouse, vacant shed and associated boundary walls on the eastern side of the existing chilled storage building (ii) relocate the existing fire escape door from the eastern corner of the existing chilled storage building to the northern side of the existing chilled storage building (iii) the construction of a proposed extension to the existing chilled storage building with a goods intake area with 2 no. dock levellers on the eastern side of the proposed extension and external plant on the northern side (rear) of the proposed extension and all associated site works.

Cobh Cross Industrial Estate Killacloyne Carrigtwohill Co. Cork

10m
04/700CONDITIONAL9 Feb 2004

New warehouse extension, loading area canopy, new first floor office extension over existing locker room, canteen area and ancillary works

Cobh Cross Carrigtwohill

53m
06/5558CONDITIONAL15 Mar 2006

Construction of partial single storey and partial dormer style extension to dwelling

Killacloyne Carrigtwohill

76m
15/4520CONDITIONAL16 Mar 2015

Partially demolish an industrial development (demolition to total 1,770sq.m gross floor area) and the re-development and change of use of part of the site to provide for a single building (549sq.m gross floor area) comprising an industrial unit (219sq.m) and a motor fuel service station (330sq.m) with ancillary convenience, off-licence, non-retail, staff welfare and customer back of house uses, ancillary and associated site development works all at this site of approximately 0.71 ha known as CB Forms, Cobh Cross Industrial Estate, Carrigtwohill. The proposed development consists of: (1) Demolishing of 1 no. building and associated structures (totalling 1,700sq.m) of an existing industrial development comprising 2 no. Buildings. (2) Re-development of the remaining 1 no. industrial building (totalling 549sq.m) to facilitate an industrial unit with associated facilities totalling 219sq.m GFA and the change of use of part of the building to motor fuel service station with associated convenience retail, ancillary off-licence and non-retail uses and facilities totalling 330sq.m GFA comprising: (a) Changes to external material finishes of walls, (b) Introduction of Parapet walls to create flat roof from current pitched roof form, (c) Addition of extensive glazing (windows and doors) to North and East elevations, convenience retail with ancillary off-licence and deli/hot food area, including hot food for consumption off the premises (99.5sq.m), (d) Non-retail and circulation (customer refreshment seating area, staff welfare and customer back of house services, all totalling 230.5sq.m), (e) Construction of covered forecourt facilitating 4 no. customer fuel pump stations, (f) Vehicle services area and fuel tanker parking zone, (g) Installation of underground fuel storage tanks, (h) Associated signage totalling 41.8sq.m (2 no. 5.4m high totem signs, 3 no. low level entrance/exit signs, curved entrance sign), and (i) 25 no. parking spaces to include (21 no. regular and 4 no. disabled). All other ancillary and associated site development works above and below ground level, including enhanced landscaping. The development will be accessed via a new proposed vehicular access from the existing industrial estate access road to the east of the site.

CB Forms Cobh Cross Industrial Estate Carrigtwohill

76m
17/6024INCOMPLETED APPLICATION3 Aug 2017

(1) Change of use from industrial unit to restaurant unit (202.95sqm floor area) including hot food for consumption off premises, (2) Elevational changes to South and West elevations for provision of payment and collection kiosk, (3) Alteration to estate road layout to provide drive thru facility for restaurant unit and, (4) Provision of additional site signage.

Top Oil Service Station Cobh Cross Industrial Estate Killacloyne, Carrigtwohill Co. Cork

76m
17/5756INCOMPLETED APPLICATION10 Jul 2017

(1)Change of use from industrial unit to restaurant unit (202.95sqm floor area) including hot food for consumption off the premises, (2) Elevational changes to South and West Elevations for provisions of payment and collection kiosks, (3) Alteration to estate road layout to provide drive thru facility for restaurant unit and, (4) Provision of additional site signage.

Top Oil Service Station Cobh Cross Industrial Estate, Killacloyne Carrigtwohill Co. Cork

76m
17/6498CONDITIONAL27 Sept 2017

(1) Change of use form industrial unit to restaurant unit (202.95sqm floor area) including hot food for consumption off the premises, (2) Elevation change to South and West elevations for provision of payment and collection kiosks, (3) Alteration to estate road layout to provide drive thru facility for restaurant unit and (4) Provision of additional site signage.

Top Oil Service Station Cobh Cross Industrial Estate Killacloyne Carrigtwohill Co. Cork

78m
03/1333CONDITIONAL25 Mar 2003

Construction of Industrial unit for use as wholesale/ store and change of use of existing wholesale/store to DIY/retail warehousing

EM HARDWARE, COBH CROSS INDUST.ESTATE, KILLACLOYNE,

91m
03/2196CONDITIONAL9 May 2003

6 no. light industrial units with anc. offices,2 no. office units, ESB substation,entrance roads and demolition of dwelling

KILLACLOYNE, KILLACLOYNE,

The submission window has closed

Observations on this application closed on Thursday 28 April 2022, five weeks after it was received. The authority cannot accept a late submission.

Planning a project of your own?

Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.

Do I Need Permission?