3 & 4 Railway Cottages (formerly Peg's Pub) Carrigaloe, Donegal Td. Cobh Co. Cork

INCOMPLETED APPLICATION

Planning application 22/5651

Cork - Cork County Council

Proposed Development

Permission for retention of change of plans and elevational changes to dwellings permitted under Planning Reg No. 17/6844

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    14 Jul 2022

  2. Decision due

    7 Sept 2022

Application Details

Location
3 & 4 Railway Cottages (formerly Peg's Pub) Carrigaloe, Donegal Td. Cobh Co. Cork
Applicant
N/A
Application Type
RETENTION
Planning Authority
Cork County Council

Timeline

Registration Date
14 July 2022Other applications received that week
Status
INCOMPLETED APPLICATION
Decision
Pending
Decision Due
7 September 2022

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

495m
20/6670CONDITIONAL27 Nov 2020

The demolition of ‘Summerlea Lodge’ (also known as ‘Summerlea House’, ‘Cluneveen’, or ‘Kilty House’) and adjacent outbuilding including associated site works.

Donegal (Townland) Carrigaloe Cobh Co. Cork

504m
08/9457CONDITIONAL24 Oct 2008

Site clearance and change of use of former bus depot to a mixed use development comprising 2 no. blocks ranging in height from three to four storeys consisting of 23 no. residential units (3 no. one bed apartments, 17 no. two bed apartments and 3 no. three bed townhouses), 121sqm retail unit at ground level, 19 no. car parking spaces and loading bay at ground level fronting the public road, 42 no. car parking spaces at sub-ground level (basement), access ramp to basement car park, hard and soft landscaping, bin stores and associated works and services including effluent treatment unit

Old Bus Depot Glenbrook Maulbaun Passage West

504m
10/4466CONDITIONAL2 Mar 2010

Site clearance & change of use of former bus depot to a residential development of 14no. three-storey terraced dwellings set out in 2no. blocks consisting of 10no. three-bed dwelings, 4no. two-bed dwellings, & 24no. surface car parking spaces fronting the public road. The development includes hard & soft landscaping, bin stores & all associated site works & services including effluent treatment unit.

Old Bus Depot Glenbrook Maulbaun Passage West

504m
10/4243INCOMPLETED APPLICATION9 Feb 2010

Site clearance & change of use of the dormer Bus Depot to a residential development of 14no. three-storey terraced dwellings set out in 2no. blocks consisting of 10no. three-bed dwellings & 4no. two-bed dwellings & 24no. surface carparking spaces fronting the public road. The development includes hard & soft landscaping, bin stores, & associated site works including effluent treatment unit

Old Bus Depot Maulbaun Glenbrook Passage West

504m
08/8951INCOMPLETED APPLICATION18 Sept 2008

Site clearance & change of use of former bus depot to a mixed use development comprising 2no. blocksranging in height from two to three storeys (excluding set back at roof level)consisting of 23no. residential units (3no. one bed apts, 17no. two bed apts, & 3no. three bed townhouses), 121sqm GFA retail unit at grade level, 19 no. car parking spaces & loading bay at grade level fronting the public road, 42no. car parking spaces at sub-grade level (basement). Development includes widening of existing public road, new footpaths on both sides of the public road, access ramp to basement car park, hard & soft landscaping, bin stores & all associated works including associated on-site services

Old Bus Depot Glenbrook Maulbaun Passage West

505m
07/12444REFUSED16 Nov 2007

Change of use from existing bus depot to mixed use commercial/retail/residential development comprising of 2 no. blocks, Block A, five storey building consisting of ground and first floor offices and 5 no. apartments on second, third and fourth floors, Block B, a four storey building consisting of ground floor retail units, 2 no. gated covered parking areas for cars and bicycles, stores, service yards and ESB substation and 26 no. apartments on first, second and third floors with shared terrace at first floor level, construction of basement level car park, widening of existing street and construction of footpaths and amenity area

Glenbrook Maulbaun Passage West

648m
07/6850CONDITIONAL5 Apr 2007

Two storey dwellinghouse

Donegal Cobh

648m
07/5728INCOMPLETED APPLICATION7 Mar 2007

Two storey dwellinghouse

Donegal Cobh

649m
15/4122CONDITIONAL23 Jan 2015

Construct a one and a half storey dwelling, incorporating existing foundations constructed under planning permission ref: 07/6850, install a waste water treatment plant and carry out ancillary site works

Donegal Cobh Co Cork

668m
16/5285CONDITIONAL27 May 2016

The development of 26 no. residential units and all ancillary car parking, fencing and walls, cycle spaces, bin stores, landscaping and site development works. The proposed development includes the construction of 6 no. 2 storey terraced houses and 20 no. apartments over 3 storeys consisting of 10 no. duplex apartments with first floor terraces over 10 no. ground floor apartments. The proposed site development works includes the demolition of existing walls, the demolition and site clearance of the remnants of 2 no former outbuildings, and modifications to the existing vehicle access at Mariner’s View.

Maulbaun Passage West Co. Cork

The submission window has closed

Observations on this application closed on Wednesday 17 August 2022, five weeks after it was received. The authority cannot accept a late submission.

Planning a project of your own?

Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.

Do I Need Permission?