← Back to search

Fiddane Ballyhea Charleville Co.Cork

CONDITIONAL

Planning application 22/6536

Cork - Cork County Council

Proposed Development

Permission to amend the design of the previously approved development (planning reference: Cork County Council 17/5799 & an Bord Pleanála ABP-306915-20)which comprises consent for a 67.8 hectare Solar PV farm at Fiddane, Ballyhea Charleville, Co.Cork. The proposed amendments include

  1. (1)
    increase in number of transformers
  2. (2)
    reduction in the spacing of Solar PV rows (strings)
  3. (3)
    increase in size and configuration of solar panels
  4. (4)
    overall increase in solar power generation
  5. (5)
    change in solar panels tilt (degree)
  6. (6)
    minor reduction in the height of solar array
  7. (7)
    operational period proposed to be extended from 30 to 40 years. A Natura Impact Statement will be submitted to the planning authority with this application.
View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    14 Nov 2022

  2. Decision due

    15 Jun 2023

  3. Decision: CONDITIONAL

    15 Jun 2023

  4. Grant issued

    20 Jul 2023

Application Details

Location
Fiddane Ballyhea Charleville Co.Cork
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Cork County Council

Timeline

Registration Date
14 November 2022Other applications received that week
Status
APPLICATION FINALISED
Decision
CONDITIONAL
Decision Date
15 June 2023
Grant Date
20 July 2023

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

0m
19/6965WITHDRAWN13 Dec 2019

The development of a 67.8 hectare solar PV farm. The proposed solar farm will consist of the installation of a 40 year operation and subsequent decommissioning of a series of ground mounted solar photovoltaic (PV) panels, mounted on steel support structures 2.1m in height, together with 1 single storey ESB control room, 9 electrical transformation enclosures, underground cabling, CCTV poles and cameras, deer type security fencing, site entrance, hardstanding area, landscaping along part of the northern site boundary and other associated development works, for the purpose of generating renewable energy electricity. A Natura Impact Statement will be submitted to the planning authority with this application.

Fiddane Townland Ballyhea Charleville Co. Cork

1m
17/5799CONDITIONAL13 Jul 2017

Development of a 67.8 hectare Solar PV Farm. The proposed solar farm will consist of the installation of a 30 year operation and subsequent decommissioning of a series of ground mounted solar photovoltaic (PV) panels, mounted on steel support structures 2.1m in height, together with 1 single storey ESB control room, 14 electrical transformation enclosures, underground cabling, CCTV poles and cameras, deer type security fencing, site entrance, hardstanding area, landscaping along part of the northern site boundary and other associated development works, for the purpose of generating renewable energy electricity.

Fiddane Ballyhea Co. Cork Co. Cork

3m
19/6816INCOMPLETED APPLICATION25 Nov 2019

The development of a 67.8 hectare solar PV farm. The proposed solar farm will consist of the installation of a 40 year operation and subsequent decommissioning of a series of ground mounted solar photovoltaic (PV) panels, mounted on steel support structures 2.1m in height, together with 1 single storey ESB control room, 9 electrical transformation enclosures, underground cabling, CCTV poles and cameras, deer type security fencing, site entrance, hardstanding area, landscaping along part of the northern site boundary and other associated development works, for the purpose of generating renewable energy electricity. A Natura Impact Statement will be submitted to the planning authority with this application.

Fiddane Townland Ballyhea Charleville Co. Cork

428m
20/5460CONDITIONAL13 Jul 2020

Retention and completion of an extension to gable end of existing dwelling and permission for construction of a new vehicular entrance

Ardglass Charleville Co. Cork

567m
04/4320CONDITIONAL14 Jun 2004

Dwellinghouse

Fiddane Ballyhea Charleville

626m
05/5834CONDITIONAL15 Aug 2005

Dwelling

Ardglass Charleville

626m
06/12606CONDITIONAL23 Nov 2006

Demolition of part of stable and part of dwellinghouse (original cottage) and construction of detached boiler house, installation of bay window to dwellinghouse and retention of sunroom, 2 no. bay windows, rear hip roof to gable, use of utility roof as balcony and change of balcony railing to concrete balstrade

Ardglass Charleville

626m
06/11859INCOMPLETED APPLICATION31 Oct 2006

Demolition of cottage and part of stable and construction of new bay window and boiler house and retention of sunroom and 2 no. bay windows, change of back addition hiproof to gable and use of utility roof as balcony and change of balcony railing to concrete balustrade

Ardglass Charleville

627m
11/4151CONDITIONAL31 Jan 2011

Construction of garage to rear of dwelling and retention of raising level of roof and conversion of attic to living accommodation with 3 no. velux rooflights to rear and 2 no. dormer windows to front of dwelling and septic tank and percolation area to rear

Ardglass Charleville Co Cork

627m
10/8167INCOMPLETED APPLICATION8 Oct 2010

Permission to construct garage to rear of dwelling and retention of raising level of roof and conversion of attic to living accommodation with 3 no. velux rooflights to rear and 2 no. dormer windows to front of dwelling

Ardglass Charleville

Planning a project of your own?

Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.

Do I Need Permission?