Ballyvatta, Clash, Meeleen, Aghaduff Knockraha East and Ballynanelagh Knockraha, Leamlara Co. Cork
Conditional PermissionPlanning application 23/4564
Cork - Cork County Council
Proposed Development
Amendment of previous permission Reg. Ref: 17/5370 and ABP- 300434-17, which includes a enlarged site boundary, for alterations to an permitted solar farm to provide an additional area of 7.8ha to the south comprising photovoltaic panels on ground mounted frames, MV/inverter stations, fencing, access tracks, CCTV cameras, a weather station, landscaping and all associated ancillary development works. The development also includes a 2.25km cable route to the south to provide a link to a future substation and all associated ancillary development works. The application also seeks to amend Condition 3 of permission granted under Reg. Ref:17/5370 and ABP Ref: ABP-300434-17 to increase the lifespan of the permitted solar farm from 25 to 35 years.
Application Timeline
Application received
29 Mar 2023
Decision: Conditional Permission
6 Mar 2024
Decision due
13 Mar 2024
Grant issued
10 May 2024
Application Details
- Location
- Ballyvatta, Clash, Meeleen, Aghaduff Knockraha East and Ballynanelagh Knockraha, Leamlara Co. Cork
- Applicant
- N/A
- Application Type
- Permission
- Planning Authority
- Cork County Council
Timeline
- Registration Date
- 29 March 2023
- Status
- Application Closed
- Decision
- Conditional Permission
- Decision Date
- 6 March 2024
- Grant Date
- 10 May 2024
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
Amendment of previous permission reg ref 17/5370 and ABP-300434-17 for alterations to a permitted solar farm to provide an additional area of 7.8 ha to the south comprising of photovoltaic panels on ground mounted frames, MV/inverter stations, fencing, acces tracks, CCTV cameras, a weather station, landscaping and all associated ancillary development works. The development also includes 2.25km cable route to the south to provide a link to a future substation and all associated ancillary development works. The application also seeks to amend condition 3 of permission granted under reg. ref. 17/5370 and ABP-300434-17 to increase the lifespan of the permitted solar farm from 25 to 35 years
Ballyvatta, Clash, Meelean, Aghaduff,Knockraha Eas Knockraha Leamlara Co.Cork
Construction, operation and decommissioning of photovoltaic solar farm comprising photovoltaic panels on ground mounted frames within a site of up to 48.4ha, to include inverter stations, 1 no. DNO substation, customer substation, switcher substations, field transformers, auxiliary transformers, GRP cabinets, monitoring house, single storey storage shed, battery containers, transformer containers, WC, fencing, temporary construction compound, access tracks, CCTV cameras, landscaping and all associated ancillary development works.
Ballyvatta and Clash Knockraha Leamlara Co. Cork
Construction of sheep handling facilities with dipping tank and associated site works
Ballyvatta Leamlara
One and half storey dwellinghouse and garage
Meeleen Knockraha
Two storey dwellinghouse and garage
Meeleen Knockraha
Two storey dwellinghouse and garage
Meeleen Knockraha
Dwellinghouse and garage
Meeleen Knockraha
Construction of haybarn
Meeleen Knockraha
Construction of an animal house consisting of a straw bedded area, slatted tank and feed passage, extension to dairy and associated works
Meeleen Knockraha Co. Cork
Retention of slatted tank and Permission for construction of an animal house incorporating slatted cubicle area, straw bedded area, feed passage and associated works
Meeleen Knockraha Co. Cork