← Back to search

Kilboultragh Macroom Co.Cork

CONDITIONAL

Planning application 23/5456

Cork - Cork County Council

Proposed Development

Permission to construct a new dwelling house

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    14 Jul 2023

  2. Decision: CONDITIONAL

    12 Oct 2023

  3. Decision due

    16 Oct 2023

  4. Grant issued

    17 Nov 2023

Application Details

Location
Kilboultragh Macroom Co.Cork
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Cork County Council

Timeline

Registration Date
14 July 2023
Status
APPLICATION FINALISED
Decision
CONDITIONAL
Decision Date
12 October 2023
Grant Date
17 November 2023

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

57m
08/4721CONDITIONAL13 Feb 2008

Bungalow, detached garage with boiler room/wood pellet store and installation of proprietary effluent treatment system

Kilboultragh Macroom

57m
07/7337REFUSED26 Apr 2007

Dwellinghouse, detached garage with boiler room/wood pellet store and proprietary treatment system

Kilboultragh Macroom

98m
15/4166CONDITIONAL30 Jan 2015

Construction of dwelling and ancillary works including installation of septic tank

Kilboultragh Macroom Co Cork

303m
07/6346CONDITIONAL22 Mar 2007

Construction of slatted house with underground tank

Kilboultragh Clondrohid Macroom

410m
11/4406INCOMPLETED APPLICATION2 Mar 2011

Remove two storey 80's extension from front of farmhouse and replace same with a single storey conservatory and raise tin roof section to allow addition of single room on the first floor

Mullenroe Macroom

412m
11/4590CONDITIONAL24 Mar 2011

Renovations and extensions to disused dwelling for use as dwellinghouse to include removal of existing two storey extension, alterations and construction of ground floor conservatory and first floor bedroom extension and installation of septic tank and percolation area

Mullenroe Macroom Co Cork

613m
05/2776CONDITIONAL27 Apr 2005

Retention of existing ground floor extension and raising of ridge height to provide attic acommodation with velux roof lights and side windows to dwellinghouse

Mullenroe Clondrohid

613m
07/7612CONDITIONAL8 May 2007

Constuction of porch, one and half storey extension and single storey conservatory extension to dwellinghouse and detached garage

Mullenroe Clondrohid

722m
04/8414CONDITIONAL15 Nov 2004

Dwellinghouse

Mullenroe Clondrohid

748m
26/2649Awaiting Technical Validation14 Oct 2026

Permissin for: • Demolition of 13 no. existing disused intensive agricultural structures (former piggery) comprising sheds, silos, and tanks (with a combined gross floor area (GFA) of c. 2,256.3 sq.m), located within the northeastern section of the site and site clearance works. • Construction of 3 no. digesters (c. 15.5m in height), 1 no. digestate storage tank (c. 15.5m in height), located in the northeastern portion of the main site area. • 2 no. liquid feed tanks (c. 7.2m in height), a pump house (with a GFA of c. 14 sq.m and a height of c. 2.6m), and a pump skid (c. 0.8m in height) located adjacent to the digesters. • 3 no. pasteurisation tanks (each c. 6m in height), a post pasteurisation cooling tank (c. 6m in height) a pre fertiliser manufacturing tank (c. 6m in height), ferric chloride storage tank (c. 6m in height), and rain water storage tank (c. 6m in height), located to the west of the digesters, in the central portion of the site. • An O2 generation unit (with a GFA of c. 13.9 sq.m and a height of c. 2.6m), an O2 container (with a GFA of c. 13.9 sq.m and a height of c. 2.6m), an electrical container (with a GFA of c. 13.9 sq.m and a height of c. 2.6m), and a pump container (with a GFA of c. 16.9 sq.m and a height of c. 2.6m), located within the eastern section of the main site area, between the digesters. • A part single-storey and part two-storey reception hall (with a GFA of c. 1,964.4 sq.m and an overall height of c. 16.5m) to accommodate a laboratory, panel room, tool store, workshop, storage areas, and a liquid feed intake area, with an adjacent fire water storage tank (c. 7.7m in height) and well with water treatment equipment, located north of the reception hall, all located in the north-central portion of the site, to the west and northwest of the digesters. • A single-storey solid digestate storage and nutrient recovery building (with a GFA of c. 879.9 sq.m and an overall height of c. 12.4m, a fuel tank (c. 1.6m in height), a backup generator (c. 2.3m in height), located to the south of the reception hall, in the central portion of the site. • Odour abatement plant (c. 12m in height to stack) and equipment and a digestate offtake area to the south of the solid digestate storage and nutrient recovery building. • 2 no. biogas treatment skids (c. 4.1m in height), a combined heat and power (CHP) unit and panel room (with a maximum height of c. 10m to top of flue), 2 no. biogas compression systems (c. 2.6m in height), a gas boiler (with a GFA of c. 13.1 sq.m and a height of c. 5.6m to top of flue), and a biogas upgrading module (with a GFA of c. 27.8 sq.m and a height of c. 4.6m), located in the southern portion of the main site area. • An emergency dual fuel flare (c. 11.3m in height) and 2 no. propane tanks (c. 1.3m in height), located to the west of the biogas treatment structures, within the southern portion of the main site area. • An ESB substation (with a GFA of c. 27 sq.m and a height of c. 3.4m, a grid injection unit (with a GFA of c. 21.7 sq.m and a height of c. 2.8m), which will be connected to the gas grid via an underground connection by Gas Networks Ireland, within a fenced compound, and a grid offtake skid, located in the western portion of the main site area. • Construction of a two-storey ancillary office and administration building (with an overall height of c. 8.7m and a GFA of c. 305.2 sq.m) located within the northwestern portion of the main site area. • Alterations to the L7451, the L7451 / Masseytown Road / L3417 junction, and the L3417, to the southwest of the main site area, to allow for improved access and safety, including the provision of a new site entrance, road widening, boundary setback, the trimming of overhanging tree branches and vegetation, and signage. • Construction of a site access road from the L7451 leading to the main site area, including a new entrance gate. • Provision of a discharge pipe route extending from the main anaerobic digestio

Kilboultragh, Macroom, Co. Cork

Planning a project of your own?

Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.

Do I Need Permission?