Cloonbannin West Mallow Co Cork

INCOMPLETED APPLICATION

Planning application 23/5602

Cork - Cork County Council

Proposed Development

A 10 year permission for a PV farm consisting of approximately 9,464 photovoltaic panels on ground mounted frames with 16 no. string inverters within a site area of 10.4764ha, 1 no. single storey transformer station, 1 no. single storey spare parts storage container, 1 no. delivery station, upgrading of existing agricultural entrance onto L1101, internal access tracks, security fencing, CCTV, landscaping and all associated development site works

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    8 Aug 2023

  2. Decision due

    2 Oct 2023

Application Details

Location
Cloonbannin West Mallow Co Cork
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Cork County Council

Timeline

Registration Date
8 August 2023
Status
INCOMPLETED APPLICATION
Decision
Pending
Decision Due
2 October 2023

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

0m
23/5719Conditional Permission25 Aug 2023

A 10-year permission for a PV farm consisting of approximately 9,464 photovoltaic panels on ground mounted frames with 16 no. string inverters within a site area of 10.4764ha, 1 no. single storey transformer station, 1 no. single storey spare parts storage container, 1 no. delivery station, upgrading of existing agricultural entrance onto L1101, internal access tracks, security fencing, CCTV landscaping and all associated development site works

Cloonbannin West Mallow Co.Cork

305m
23/6579INCOMPLETED APPLICATION21 Dec 2023

Permission to (A) Construct extensions to the side and rear of existing dwelling house and (B) Install a mechanical aeration unit and soil polishing filter.

Cloonbannin West Mallow Co. Cork

314m
24/4106CONDITIONAL25 Jan 2024

Permission to; a) construct extensions to the side and rear of existing dwelling house and, b) install a mechanical aeration unit and soil polishing filter, c) construct a new entrance & driveway to existing house.

Cloonbannin West Mallow Co.Cork

363m
07/5688CONDITIONAL6 Mar 2007

Construction of slatted unit with underground slurry tank

Cloonbannin West Mallow

463m
26/1554Invalid - Prepare Letters11 Jun 2026

Permission to construct a new entrance and passage/driveway for agricultural use.

Cloonbannin West, Mallow, Co. Cork.

465m
26/1878Awaiting Recommendation14 Jul 2026

Planning permission to construct a new entrance and passage for agricultural use.

Cloonbannin West, Mallow, Co Cork

483m
20/5312REFUSED25 Jun 2020

To construct a bellmouth forest road entrance, for trucks to access forestry plantations & associated site works.

Meenskeha East Derrinagree Mallow Co. Cork

531m
11/4354CONDITIONAL23 Feb 2011

Demolition of domestic garage attached to existing dwelling and detached shed to rear, construction of extensions to the front, side and rear and alterations to elevations of the existing dwelling, construction of domestic garage and retention of existing extension at the rear of dwellinghouse

Meenskeha East Dernagree Mallow, Co Cork

563m
12/4940CONDITIONAL4 May 2012

Retirement of the existing station and the construction of a replacement station on a site adjacent to the existing station. The new works will include; 3 no. new containerised control and switchgear modules; 2 no. new bunded power transformers with oil interceptor; 2 no. new house transformers; new internal gravel road; new 1.4m high concrete post and rail boundary fence; new 2.6m high palisade compound fence and gates; new splayed entrance and associated site works.

ESB Cloonbannin 38kV electrical transformer station Cloonbannin West Mallow

569m
07/6284CONDITIONAL21 Mar 2007

Erection of 20m high free standing wooden pole communications structure carrying antennae and communication dishes with associated ground-mounted equipment cabinets within a 2.4m high palisade compound

Cloonbannin Crossroads Cloonbannin West

Affected by this application?

Submissions can be made for 5 weeks from the date the application was received. Only material planning grounds count. Build a valid submission letter in minutes.

Make a Submission or Objection

Planning a project of your own?

Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.

Do I Need Permission?