← Back to search

Ballynabointra Midleton Co. Cork

CONDITIONAL

Planning application 23/5644

Cork - Cork County Council

Proposed Development

The development will consist of the installation of a replacement block production yard and block storage area within an application area of c.2hectares. The development will comprise of; 1) the construction of new block production yard, comprising a reinforced concrete ground bearing slab (c.7,155m2), 2) installation of sub-surface storm water drainage beneath the concrete slab which will discharge via a silt trap and hydrocarbon interceptor to the adjoining quarry floor (and to ground thereafter) and 3) provision of a hard standing (unpaved) area (c.2,950m2) for concrete block storage pending sale and dispatch off-site.

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    11 Aug 2023

  2. Decision: CONDITIONAL

    4 Oct 2023

  3. Decision due

    5 Oct 2023

  4. Grant issued

    10 Nov 2023

Application Details

Location
Ballynabointra Midleton Co. Cork
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Cork County Council

Timeline

Registration Date
11 August 2023
Status
APPLICATION FINALISED
Decision
CONDITIONAL
Decision Date
4 October 2023
Grant Date
10 November 2023

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

36m
08/8847CONDITIONAL11 Sept 2008

Retention of generator building, storage container, electrical switch room building, staff portacabin, diesel tank and bund, E.S.B. substation/electrical building, two-storey office/laboratory building and associated site works

Ballynabointra Midleton

135m
12/4480CONDITIONAL13 Mar 2012

Erection of a new Asphalt Plant incorporating an 18.25m above ground level emissions stack, located to the west of the existing quarry void, together with associated site works to include localised re-alignment of the internal haul road and provision of hardstanding; fuel tank; bitumen storage tanks; control cabin and containers

Ballynabointra Midleton Co. Cork

146m
25/4738Application Invalid23 Apr 2025

A 20 Year Permission for backfilling of an exhausted quarry void (quarry registration ref; QR078) and acceptance, short-term storage and processing of construction and demolition (C&D) waste on-site, within an overall application area of circa (ca) 11hectare (ha). The development will consist of the back filling of the quarry void (ca. 4.9ha) to a level of ca. 27 metres above Ordnance datum (mAOD) with either; 1) Inert soil and stone waste (imported inert greenfield and non-greenfield soils and stones, and river dredge spoil which will result in the proposed development operating as a soil recovery facility that requires a waste management licence from the Environmental Protection Agency (EPA); or 2) Soil and Stone by-product (i.e. essentially virgin soil or equivalent to virgin soil and stone) which will be notified to the EPA as an Article 27 by-product as its source of origin and transported as a by-product material to enable the site to be backfilled. The proposed C&D processing facility will cover an area of c.a 1.9ha and will operate under a waste management licence from the EPA. The development will also comprise of the construction of an inspection shed (ca.140m2) and ancillary improvements to drainage and landscaping. The development will utilise existing infrastructure on-site including weighbridge, wheel wash, garage, car parking and welfare facilities. A planning permission of 20 years is being sought for the proposed development. The planning application, Environmental Impact Assessment Report (EIAR) and Natura impact Statement (NIS) may be inspected or purchased at a fee not exceeding the reasonable cost of making a copy at the offices of the Planning Authority.

Ballynabointra Burgesland Midleton Co.Cork

146m
25/4899Refused15 May 2025

A 20 Year permission for the backfilling of an exhausted quarry void (quarry registration ref: QR078) and acceptance, short-term storage and processing of construction and demolition (C&D) waste on-site, within an overall application area circa (ca) 11 hectare (ha). The development will consist of the backfilling of the quarry void (ca. 4.9ha) to a level of ca. 27 metres above Ordance Datum (MAOD) with either; 1) Inert soil and stone waste (imported inert greenfield and non-greenfield soils and stones and river dredge spoil which will result in the proposed development operating as a soil recovery facility that requires a waste management licence from the Environmental Protection Agency (EPA); or 2) Soil and stone by-product (i.e. essentially virgin soil or equivalent to virgin soil and stone) which will be notified to the EPA as an Article 27 by-product at its source of origin and transported as a by-product material to enable the site to be backfilled. The proposed C&D processing facility will cover an area of ca. 1.9ha and will operate under a waste management licence from the EPA. The development will also comprise of the construction of an inspection shed (ca. 140m2) and ancillary improvements to drainage and landscaping. The development will utilise existing infrastructure on-site including weighbridge, wheelwash, garage, car parking and welfare facilities. The application relates to development which involves an activity requiring a waste licence from the EPA. A planning permission of 20 years is being sought for the proposed development. An Environmental Impact Assessment Report (EIAR) and a Natura Impact Statement (NIS) will be submitted to the planning authority with the application.

Ballynabointra Burgesland Midleton Co. Cork

146m
25/4497INCOMPLETED APPLICATION21 Mar 2025

Permission for backfilling of an exhausted quarry void (quarry registration ref; QR078) and acceptance, short-term storage and processing of construction and demolition (C&D) waste on-site, within an overall application area of circa (ca) 11hectare (ha). The development will consist of the back filling of the quarry void (ca. 4.9ha) to a level of ca. 27 metres above Ordnance datum (mAOD) with either; 1) Inert soil and stone waste (imported inert greenfield and non-greenfield soils and stones, and river dredge spoil which will result in the proposed development operating as a soil recovery facility that requires a waste management licence from the environmental protection agency (EPA); or 2) Soil and stone by-product (i.e. essentially virgin soil or equivalent to virgin soil and stone) which will be notified to the EPA as an Article 27 by-product at its source of origin and transported as a by-product material to enable the site to be backfilled. The proposed C&D processing facility will cover an area of ca. 1.9ha and will operate under a waste management licence from the EPA. The development will also comprise of the construction of an inspection shed (ca. 140m2) and ancillary improvements to drainage and landscaping. The development will utilise existing infrastructure on-site including weighbridge, wheelwash, garage, car parking and welfare facilities. A planning permission of 20 years is being sought for the proposed development. The planning application, Environmental Impact Assessment Report (EIAR) and Natura Impact Statement (NIS) may be inspected or purchased at a fee not exceeding the reasonable cost of making a copy at the offices of the Planning Authoririty.

Ballynabointra Midleton Co.Cork

168m
23/6118Conditional Permission20 Oct 2023

The development will consist of the construction of a new storage shed and an external paved yard to facilitate the importation, storage and processing of road planings with an application site of c. 1.0 hectares. The development will comprise- Construction of an external yard comprising a reinforced concrete ground bearing slab (c.2032m2) to store and process imported road planings. Construction of a portal frame storage shed (c.2053m2) to store processed road planings. Installation of sub-surface drainage to collect surface water run-off which will discharge via a silt trap and hydrocarbon interceptor to the adjoining quarry floor (and to the ground thereafter).

Burgesland and Ballynabointra Midleton Co. Cork

356m
09/5812REFUSED3 Jun 2009

Two-storey dwellinghouse, septic tank and associated site works

Ballynabointra Midleton

358m
09/7297CONDITIONAL12 Oct 2009

Two-storey dwellinghouse, septic tank and associated site works

Ballynabointra Midleton

369m
15/4529CONDITIONAL19 Mar 2015

Construction of new gated access to serve the Lagan Concrete site off the Ballynabointra Road. The proposed works include the provision of a wheelwash, 2.4 metre high palisade fencing, traffic signs, road markings, public lighting and all associated site works and services

Milebush Ballynabointra Midleton, Co Cork

369m
15/4390INCOMPLETED APPLICATION27 Feb 2015

Construction of a new access to the south of the Lagan site on the Ballynabointra Road. The proposed works include for the provision of all traffic signs, road markings, public lighting and all associated site works and services

Milebush Midleton Co Cork