Planning application 24/315

Cork - Cork County Council

Proposed Development

Permission for the retention of the following as built structures:

  1. 1)
    Additional car parking area comprising of 28 no. car parking spaces and a pedestrian entry/exit gate providing access to the existing public footpath
  2. 2)
    Change of use from Visitor Centre to Distillery (Visitor Centre was conditioned out through condition no. 4, Planning Ref. 19/779)
  3. 3)
    First floor offices and associated staff welfare areas in Distillery building
  4. 4)
    Distillery stack to the existing Distillery building roof
  5. 5)
    Distillery spirit bond with a maximum tank height of 12m
  6. 6)
    Machinery building and associated Electrical Room with extended canopy to side of Machinery building
  7. 7)
    Grain intake area comprising of 6 no. grain silos and associated gantries
  8. 8)
    Glan bund 9 with a maximum tank height of 10.76m
  9. 9)
    Glan bund 10 with a maximum tank height of 10.35m and associated gantries; 10) 712cu/m Firefighting water retention tank
  10. 11)
    Column still and associated gantries
  11. 12)
    Boiler house and boiler stack
  12. 13)
    Sump for fire water diversion. Permission is also sought for the construction of the following:
  13. 14)
    New 60 tonne gas tank to replace the existing 30 Tonne gas tank
  14. 15)
    Grain intake building, approximately 42m2:
  15. 16)
    Two 40-foot containers for water treatment system
  16. 17)
    Two new Combined Heating & Power plant
  17. 18)
    New Workshop building, approximately 813m2. The proposed development is for modifications to an establishment to which the Major Accidents Directive applies. The proposed development is for the purposes of an activity requiring an Integrated Pollution Prevention and Control License
View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    12 Jun 2024

  2. Decision: CONDITIONAL

    4 Mar 2025

  3. Decision due

    10 Mar 2025

  4. Grant issued

    8 Apr 2025

Application Details

Location
West Cork Distillers Ltd. Fastnet Industrial Estate Marsh Road Marsh, Skibbereen, Co. Cork
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Cork County Council

Timeline

Registration Date
12 June 2024Other applications received that week
Status
APPLICATION FINALISED
Decision
CONDITIONAL
Decision Date
4 March 2025
Grant Date
8 April 2025

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

96m
15/463CONDITIONAL12 Aug 2015

Construct a single storey extension (130m²) to the Eastern side of the existing NCT building, construct a mezzanine floor over part of the existing offices, alterations to existing elevations, revisions to existing internal layout, construct additional car parking and all associated site works

NCT site Marsh Skibbereen Co. Cork

276m
17/275CONDITIONAL11 May 2017

Permission to construct an extension and carry out alterations to an existing clubhouse

Gortnaclohy Mill Road Skibbereen Co. Cork

276m
17/113INCOMPLETED APPLICATION24 Feb 2017

Construct an extension and carry out alterations to an existing clubhouse at Gortnaclohy, Mill Road, Skibbereen

Gortnaclohy Mill Road Skibbereen

279m
24/327CONDITIONAL18 Jun 2024

Demolition of existing single-storey building currently used for equipment storage and for the construction of a prefabricated steel framed single storey sports unit with open gym, activity area, storage rooms and all associated site development works

The Riverside Complex GAA Grounds Marsh (Townlands) Marsh Road, Skibbereen, Co. Cork P81 P952

348m
26/2216Awaiting F.I. Response25 Aug 2026

Planning Permission the following: a) Construct a two-storey extension to the Western side of the existing building for 2 No. storage units on the ground floor and offices/amenities on the first floor. b) Construct a covered canopy area on the Eastern side of the existing building including all associated site works

Railway Enterprise Centre, Curragh, Skibbereen, Co. Cork, P81FV40

360m
17/372WITHDRAWN8 Jun 2017

Construction of portal framed steel building for use as commercial facility to include workshop with office and WC, store and loading facility, materials storage deport and all ancillary siteworks

The Marsh Road Curragh Skibbereen Co. Cork

360m
18/99CONDITIONAL27 Feb 2018

Construction of portal framed steel building for use as commercial facility to include workshop with office and WC, store and loading facility, materials storage depot and all ancillary siteworks

Marsh Road Curragh Skibbereen Co. Cork

372m
17/389INCOMPLETED APPLICATION23 Jun 2017

Change of use of part of existing Cope premises from day facilities use to short stay respite residential accommodation use, minor alterations and all associated site works

'The Laurels' Mill Road Gortnaclohy Skibbereen

372m
17/474CONDITIONAL17 Jul 2017

Change of use of part of existing Cope premises from day facilities use to short stay respite residential accommodation use, minor alterations and all associated site works

'The Laurels' Mill Road Gortnaclohy Skibbereen, Co. Cork

385m
12/57018CONDITIONAL23 Nov 2012

minor alterations to and change of use of existing COPE foundation building from day facility and residential use to day facility use only at "The Laurels", Mill Road and for alterations and extensions to adjoining residence for use as COPE residence, construction of new boiler house at Cork Road and connection of both properties to town drainage system plus all associated site works at Mill Road and Cork Road, Gortnaclohy, Skibbereen.

"The Laurels, Mill Road & Cork Road Gortnaclohy Skibbereen

Planning a project of your own?

Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.

Do I Need Permission?