← Back to search

ESB 110kV Substation St.Josephs Road Carrigoon beg Mallow, Co.Cork

Conditional

Planning application 24/5762

Cork - Cork County Council

Proposed Development

Retention permission for a temporary portacabin including holding tank, which was retained on site used for staff welfare after the construction period, and permission for the demolition of this existing portacabin and construction of a new pre-fabricated portacabin, including holding tank, for use as staff welfare and all associated site works

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    17 Sept 2024

  2. Decision due

    11 Nov 2024

  3. Decision: Conditional

    11 Nov 2024

  4. Grant issued

    16 Dec 2024

Application Details

Location
ESB 110kV Substation St.Josephs Road Carrigoon beg Mallow, Co.Cork
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Cork County Council

Timeline

Registration Date
17 September 2024
Status
APPLICATION FINALISED
Decision
Conditional
Decision Date
11 November 2024
Grant Date
16 December 2024

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

3m
24/5628Application Invalid28 Aug 2024

Retention permission for a temporary portacabin including holding tank, which was retained on site used for staff welfare after the construction period, and permission for the demolition of this existing portacabin and construction of a new pre-fabricated portacabin, including holding tank, for use as staff welfare, and all associated site development works

ESB 110kV Substation, St.Joseph's Road Carrigoon Beg Mallow Co.Cork

3m
24/4894INCOMPLETED APPLICATION17 May 2024

Retention Permission for a temporary portacabin and permission for the demolition of a temporary portacabin and construction of a new pre-fabricated portacabin of 49s.q.m., and all associated site development works.

ESB 110kv Station St. Josephs Road Carrigoon Beg Mallow, Co. Cork

3m
24/5131INCOMPLETED APPLICATION17 Jun 2024

Permission for Retention of a temporary portacabin including holding tank, which was retained on site used for staff welfare after the construction period, and Permission for the demolition of this existing portacabin and construction of a new pre-fabricated portacabin, including holding tank for use as staff welfare and all associated site development works.

ESB 110 kV Substation St. Josephs Road Carrigoon Beg Mallow, Co.Cork

71m
05/5093CONDITIONAL15 Jul 2005

Dwellinghouse and garage

Carrigoon Beg Mallow

71m
05/3919INCOMPLETED APPLICATION7 Jun 2005

Dwellinghouse and garage

Carrigoon Beg Mallow

81m
17/5011CONDITIONAL26 Apr 2017

Retention of existing domestic garage and all associated works

Carrigoon More Mallow Co. Cork

110m
04/1543CONDITIONAL9 Mar 2004

First floor extension and change of facade of front elevation of existing dwelling

St. Joseph's Road Carrigoon More Mallow

110m
07/11214INCOMPLETED APPLICATION25 Sept 2007

Erection of 36m high free standing lattice communications structure, carrying antennae and communication dishes with a 2.4m high palisade compound to existing Mallow 110kV substation

St. Josephs Rd Carrigoon Beg Mallow

110m
07/10586INCOMPLETED APPLICATION28 Aug 2007

Erection of 36m high free standing lattic communications structure, carrying antennae and communication dishes within a 2.4m high palisade compound to share with other licensed operators at existing ESB Mallow 110kV substation

St. Joseph's Rd Carrigoon Beg Mallow

112m
07/11773WITHDRAWN18 Oct 2007

Erection of 36m high free standing lattice communications structure carrying antennae and communication dishes within a 2.4m high palisade compound at existing Mallow 110kV substation

St. Joseph's Rd Carrigoon Beg Mallow