Proposed Development
Permission to carry out the following on the site of their existing baby food production facility. Permission for (1) Construction of a new hardstanding compound to the north of the existing 38Kva substation. The compound to be secured with 2.9m high palisade fence, (2) Installation of 5MW (5x1MW) of hydrotreated vegetable oil (HVO) stationary standby generators for emergency electricity generation, each generator is enclosed in a weatherproof container (2.8m high x 0.8m Long x 5.0m wide). (3) Installation of 2 no. transformers within the compound and associated cabling. (4) Extension to the existing concrete roadway to access the compound. (5) All associated site works. The development relates to an activity in relation to which a revised Integrated Pollution Prevention and Control Licence is required
View the full application file on the council's planning portal →Application Details
- Location
- Inchinashingane Macroom Co. Cork
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Cork County Council
Timeline
- Registration Date
- 5 December 2024
- Status
- WITHDRAWN
- Decision
- Pending
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
Permission to carry out the following on the lands to the east of their existing baby food production facility. 1) construction of a new hard standing compound. The compound to be secured with 2.9m high palisade fence, 2) installation of 6MW (3x2MW) of Hydrotreated vegetable oil (HVO) stationary standby generators for emergency electricity generation, each generator is enclosed in a weatherproof container (3.710m high x 14.6m long x 3.65m wide), 3) installation of 3 no. transformers within the compound and associated cabling, 4) installation of 2 no. bunded fuel storage tanks (5.15m long x 2.3m wide x 2.4m high), 5) extension to the existing western concrete roadway within the Nutricia site to access the compound, 6) All associated site works and interconnecting underground cabling. The electricity generated will be used by the Nutricia Infant Nutrition site, during times of interrupted electrical supply from the national grid. Nutricia Infant Nutrition currently operates under an Integrated Pollution, Prevention and Control Licence
Inchinashingane, Macroom, Cork, P12XW40
[a] Construction of new extension to existing office/administration building including reception area, laboratory, meeting rooms, offices and canteen, [b] construction of high level enclosed walkway between the newly extended office/administration building and the main production facility, [c] extension to existing car parking area, [d] construction of new lorry queuing area, [e] modifications to the existing main entrance including the construction of a separate car park entrance adjacent to the existing entrance gates and all associated site works.
Inchinashingane Macroom
To carry out the following on the site of existing Baby Food Production Facility: (a) Extend 3 no. existing exhaust ducts located on the roof of the M2 drying tower by 10 metres in height together with all necessary support steelworks and access ladders and (b) extend 1 no. existing exhaust duct located on the roof of the M1 drying tower by 10 metres in height together with all necessary support steel work and access ladder. The development relates to an activity in relation to which a revised Integrated Pollution Prevention and Control Licence is required.
Inchinashingane Macroom Co. Cork
Erect a new air heater room including the installation of a new natural gas air heater and stack to replace the existing steam heater located on the eastern elevation of existing milk processing and baby food production facility
Inchinashingane Macroom
(a) Construction of new single storey extensions to the existing tank farm access corridors, (b) construction of new extension to the west elevation of the existing factory comprising of new salt store, access stairs, service hoist and transfer zone, (c) construction of new single storey extension to the west elevation of the existing factory to enclose the existing process tanks and pumps for the purposes of sound attenuation, (d) construction of new MCC room at first floor level, new process area at second floor level and access stairs to serve both of the aforementioned areas, (e) construction 2 no. new acoustic barriers for the purposes of sound attenuation of equipment located on the roof level of the existing factory comprising of 6m high steel framed cladded structures, and (f) all associated site works
Inchinashingane Macroom
Construction of extension to Western elevation of the existing powder store and associated site works
Inchinashingane Macroom Co.Cork
(a) Increase in height of the existing drying tower No.1 to incorporate an additional floor, and (b) construction of a link corridor between the new extension to drying tower No.1 and the existing drying tower No. 2
Inchinashingane Macroom
To carry out the following on the site of the existing Baby Food Production Facility (a) Construct an extension on to the existing laboratory located on the eastern elevation of the existing Administration Building, (b) Construct an extension to the northern elevation of the existing Weighbridge Office and changes to the eastern and southern elevation of the existing Weighbridge Office and (c) Associated Siteworks. The development relates to an activity in relation to which a revised Integrated Pollution, Prevention and Control License is required.
Inchinashingane Macroom Co. Cork
To carry out the following on the site of existing baby food production facility: (a) Construct a single storey process area extension on to the eastern elevation of the existing powder store (b) Installation of HVAC equipment and support steelwork for same on to the roof of the new extension (c) Construction of a galvanised pipebridge between the new extension and the existing intake lanes also located on the eastern elevation of the existing facility (d) Upgrade of the existing waste water treatment plant with the addition of an increased capacity clarifier (e) Re-route the existing underground drainage pipework to facilitate the new process area extension (f) Permission for retention of the existing air compressor room which is located on the eastern elevation of the existing services building (g) Associated siteworks. The development relates to an activity in relation to which a revised integrated pollution, prevention and control license is required.
Inchinashingane Macroom Co. Cork
(a) Construct an extension on to the existing Laboratory located on the eastern elevation of the existing Administration Building. (b) Construct an extension to the northern elevation of the existing Weighbridge Office and changes to the eastern and southern elevation of the existing Weighbridge Office and (c) Associated Siteworks. The development relates to an activity in relation to which a revised Integrated Pollution, Prevention and Control License is required.
Inchinashingane Macroom Co. Cork
The submission window has closed
Observations on this application closed on Friday 17 January 2025, five weeks after it was received. The authority cannot accept a late submission.