Permission for the construction of a new utilities enclosure and associated works. The proposed development consists of the construction of a permanent prefabricated utilities enclosure within the pharmaceutical production site, of approx. 24.5sqm with a height of up to 4.5m, to the south of the existing IE42 production building with external equipment located adjacent to the enclosure, associated with the operation of the chiller. The proposed development is covered by an existing Industrial Emissions (IE) Directive License N0009-05. The proposed development refers to a modification to an establishment to which the Major Accident Regulations applies.

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    13 Feb 2025

  2. Decision due

    9 Apr 2025

  3. Decision: CONDITIONAL

    9 Apr 2025

  4. Grant issued

    20 May 2025

Application Details

Location
Ballythomas West Dunderrow Kinsale Co.Cork
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Cork County Council

Timeline

Registration Date
13 February 2025Other applications received that week
Status
APPLICATION FINALISED
Decision
CONDITIONAL
Decision Date
9 April 2025
Grant Date
20 May 2025

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

145m
25/5133Conditional Permission12 Jun 2025

Permission to construct a Biomass Steam Boiler Facility that includes: A) Demolition of existing single storey temporary warehouse building. B) Construction of single storey building with parapet height of 20.3m with part mezzanine floors within. C) A chimney stack with height of 23.15m. D) Above ground pipe rack measuring 55m long x 3.5m wide with an overall height of 11.58m. E) Underground services, drainage and other associated site development works. The proposed development is covered by an existing Industrial Emissions (IE) Directive Licence No. P0009-05 under Part IV of the Environmental Protection Agency Act 1992 (as amended). The proposed development refers to a modification to an establishment to which Major Accident Regulations applies.

Ballythomas East, Ballythomas West, Horsehill More North and Ballyvrin Lower, Dunderrow, Kinsale, Co. Cork.

341m
25/4269INCOMPLETED APPLICATION21 Feb 2025

Permission for construction of an expansion to the existing waste water treatment plant, that includes (a) three number buildings consisting of (1) a single storey precipitation building (8.6m high) that including an open storage area, (2) single storey electrical building (5.4m high), (3) two storey filter press building (9.6m high), (b) process vessels and associated access stairs and platforms, (c) structural steel service racking, (d) underground services, drainage and other associated siteworks. The proposed development is covered by an existing industrial emissions (IE) licence no. P0009-05. The development refers to a modification to an establishment to which a major accident regulation applies.

Ballythomas East, Ballythomas West Horsehill More North, Ballyvrin Lower Dunderrow Kinsale, Co.Cork

407m
16/4320INCOMPLETED APPLICATION16 Feb 2016

(1) A new external boiler flue of height not exceeding 21m above ground level adjacent to the existing IE04 building, (2) Construction of a new external support platform of height not exceeding 9.15m above ground level around the new boiler flue. All associated site development works. The proposed development is covered by the existing Integrated Pollution Control Licence (Licence Register P0009-03). The proposed development is located in an Establishment to which the Major Accidents Directive applies.

Ballythomas East, Ballythomas West Horsehill More, Dunderrow Kinsale Co. Cork

407m
16/4799UNCONDITIONAL12 Apr 2016

(1) A new external boiler flue of height not exceeding 21m above ground level adjacent to the existing IE04 building, (2) Construction of a new external support platform of height not exceeding 9.15m above ground level around the new boiler flue, and all associated site development works. The proposed development is covered by the existing Integrated Pollution Control Licence (Licence Register P0009-03). The proposed development is located in an Establishment to which the Major Accidents Directive applies.

Ballythomas East, Ballythomas West Horsehill More Dunderrow Kinsale

464m
14/6065CONDITIONAL1 Oct 2014

Demolition of existing idled IE3 Production building and ancillary plant and equipment

Ballythomas East, Ballythomas West Horsehill More Dunderrow Kinsale

482m
23/5763CONDITIONAL30 Aug 2023

Permission for the construction of a pedestrian footbridge across an existing stream within the Eli Lily pharmaceutical facility, and associated works. The bridge will have a length of approx. 17.9m (13.1 span plus landing areas of 2.4m at either end) and a two-way 2.4m wide walkway and will be located on a site area of approx. 0.23ha. The application site falls within the Eli Lilly industrial complex, which operates under an Industrial Emissions (IE) licence (P0009-04) under part IV of the Environmental Protection Agency Act 1992 (as amended by the protection of the Environmental Act, 2003) and is also an establishment to which the Chemicals Act (Control of Major Accident Hazards involving Dangerous Substances) Regulations 2015 (S.I. 209 of 2015) applies

Eli Lilly Pharmaceutical Complex Ballythomas East & Ballythomas West Dunderrow Kinsale, Co. Cork

482m
23/5673INCOMPLETED APPLICATION16 Aug 2023

Permission for the construction of a pedestrian footbridge across an existing stream within the Eli Lilly pharmaceutical facility, and associated site works. The bridge will have a length of approx. 17.9m (13.1m span plus landing areas of 2.4m at either end) and a two-way 2.4m wide walkway and will be located on a site area of approx. 0.23ha. The application site falls within the Eli Lilly industrial complex, which operates under an Industrial Emissions (IE) Licence (P0009-04) under Part IV of the Environmental Protection Agency Act 1992 (as amended by the Protection of the Environment Act, 2003) and is also an establishment to which the Chemicals Act (Control of Major Accident Hazards involving Dangerous Substances) Regulations 2015 (S.I. 209 of 2015) applies.

Eli Lilly Pharmaceutical Complex Ballythomas East & Ballythomas West Dunderrow Kinsale Co Cork

599m
04/7901REFUSED22 Oct 2004

Dwellinghouse

Ballythomas East Kinsale

599m
04/7490INCOMPLETED APPLICATION4 Oct 2004

Dwellinghouse

Ballythomas East Kinsale

599m
05/8511REFUSED18 Nov 2005

One and half storey dwellinghouse

Ballythomas East Kinsale

Planning a project of your own?

Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.

Do I Need Permission?