Silver Pail Dairy, Dublin Road, Carrignagroghera, Fermoy, Co. Cork, P61 TN28
Awaiting RecommendationPlanning application 26/2531
Cork - Cork County Council
Proposed Development
To construct a single storey extension, for ice cream manufacturing use, to the north side of the existing manufacturing building, and ancillary site works.
Application Timeline
Application received
30 Sept 2026
Decision due (upcoming)
24 Nov 2026
Application Details
- Location
- Silver Pail Dairy, Dublin Road, Carrignagroghera, Fermoy, Co. Cork, P61 TN28
- Applicant
- N/A
- Application Type
- Permission
- Planning Authority
- Cork County Council
Timeline
- Registration Date
- 30 September 2026Other applications received that week
- Status
- Awaiting Recommendation
- Decision
- Pending
- Decision Due
- 24 November 2026
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
Permission for extension to existing warehouse and offices at Fermoy Enterprise Park, Carrignagrohera, Fermoy
Co. Cork
The construction of motor display canopy, 32.22mts long by 5mts wide and 4.5mts high. The canopy will consist of galvanized steel structure of 5 posts, steel frame and PVC coated textile tarpaulin as roofing material.
Blackwater Motors Dublin Road Carrignagroghera Fermoy Co. Cork
Retention of 48 linear meters of 1 mt high stainless steel bollards that currently form the existing boundary treatment onto the Dublin Road.
Blackwater Motors Dublin Road Carrignagroghera Fermoy Co Cork
Retention of 50 linear meter of stainless steel bollards that currently form the existing boundary treatment onto the Dublin Road
Blackwater Motors Carrignagroghera Dublin Road, Fermoy Co Cork
Construction of retail trade warehouse, distribution and service centre for building and construction materials, furnishings and fittings with associated facilities, security office, signage, car park and associated site works
Carrignagroghera Fermoy
Construction of retail trade warehouse, distribution and service centre for building and construction materials with associated facilities, security office, signage, car park and associated site works
Carrignagroghera Fermoy
To amalgamate unit 2 and 3 of Faber Castell Business Campus for use as one unit for printing and design works.
Unit 2 and 3 Faber Castell Business Campus Carrignagroghera Td. Fermoy Co. Cork
Refurbishment and subdivision of the old Faber Castell building for the development of Industrial Units, change of traffic circulation and car park layout, and ancillary works.
Carrignagroghera
Construction of 4 no. commercial units, 2 no. retail warehouse units, provision of 82 no. car parking spaces, ESB substation, ancillary landscaping and all associated site works
Carrignagroghera Fermoy
3 no. retail warehouse units, 77 no. parking spaces, ESB sub-station, ancillary landscaping and associated site works
Carrignagroghera Fermoy
The submission window has closed
Observations on this application closed on Tuesday 3 November 2026, five weeks after it was received. The authority cannot accept a late submission.
Planning a project of your own?
Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.
Do I Need Permission?