← Back to search

CARROWMORE OR GLENTOGHER , QUIGLEY'S POINT , LIFFORD PO

REFUSED

Planning application 1850380

Donegal - Donegal County Council

Proposed Development

A 10 YEAR PLANNING PERMISSION CONSISTING OF THE CONSTRUCTION OF A SINGLE WIND TURBINE COMPRISING STEEL TOWER, NACELLE AND COMPOSITE FIBRE ROTOR BLADES WITH A BLADE TIP HEIGHT OF UP TO 124.9 METRES, INCLUDING EXTERNAL WIND TURBINE TRANSFORMER, TURBINE FOUNDATION, HARDSTAND AND ASSEMBLY AREA,NEW SITE ENTRANCE AND ACCESS TRACK, ASSOCIATED DRAINAGE WORKS, UNDERGROUND ELECTRICAL CABLE AND ASSOCIATED COMMUNICATION CABLES, WITH ALL ANCILLARY DEVELOPMENT AND ASSOCIATED WORKS

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    16 Mar 2018

  2. Decision: REFUSED

    3 May 2018

  3. Decision due

    10 May 2018

Application Details

Location
CARROWMORE OR GLENTOGHER , QUIGLEY'S POINT , LIFFORD PO
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Donegal County Council
Site Area
7.6 ha

Timeline

Registration Date
16 March 2018Other applications received that week
Status
APPLICATION FINALISED
Decision
REFUSED
Decision Date
3 May 2018

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

478m
1851230REFUSED10 Aug 2018

10 YEAR DURATION FOR A PROPOSED WIND ENERGY AND GRID CONNECTION PROJECT WITH A 30-YEAR OPERATIONAL LIFE FROM THE DATE OF COMMISSIONING. THE PROPOSED WIND ENERGY SITE WILL BE LOCATED WITHIN THE TOWNLAND OF CARROWMORE OR GLENTOGHER, QUIGLEY'S POINT, INISHOWEN, CO DONEGAL. THE PROPOSED WIND ENERGY SITE WILL CONSIST OF 6 NO. THREE BLADED WIND TURBINES WITH A MAXIMUM BASE TO BLADE TIP HEIGHT OF UP TO 124.9 METRES AND WILL INCLUDE TURBINE TRANSFORMERS; TURBINE BASES AND FOUNDATIONS, TURBINE HARDSTANDS AND TEMPORARY SET-DOWN AREAS; 1 NO. PERMANENT LATTICE ANEMOMETER "MET" MAST OF 80 METRES HEIGHT WITH FOUNDATIONS AND HARDSTANDING AREA; WIDENING AND STRENGTHENING OF EXISTING ACCESS TRACKS AND CONSTRUCTION OF NEW FLOATED AND EXCAVATED ACCESS TRACKS, JUNCTIONS AND TURNING AREAS; 1 NO. ELECTRICAL 38KV SUBSTATION WITH CONTROL BUILDING, CAR PARKING AND COMPOUND AREA WITH RELATED COMMUNICATIONS AND ELECTRICAL EQUIPMENT/PLANT WITH UNDERGROUNDED ELECTRICAL FEEDER CABLES AND COMMUNICATIONS LINES CONNECTING WIND TURBINES TO THE SWITCH ROOM CONTROL BUILDING; 2 NO. SPOIL DEPOSITION AREAS; DEDICATED HABITATE MANAGEMENT AREA; ON-SITE DRAINAGE MANAGEMENT WORKS; UPGRADE OF 3 NO. EXISTING SITE ENTRANCES; 2 NO. TEMPORARY CONSTRUCTION COMPOUNDS; 2 NO. TEMPORARY BORROW PITS AND WITH ALL OTHER ANCILLARY AND ASSOCIATED DEVELOPMENT AND INFRASTRUCTURE INCLUDING GENERAL AND EXACAVATION WORKS. THE PROPOSED UNDERGROUNDED GRID CONNECTION ROUTE WILL FACILITATE CONNECTION TO THE NATIONAL GRID AND WILL CONSIST OF THE LAYING OF A 38KV UNDERGROUND ELECTRICAL CABLE INCLUDING ALL ASSOCIATED INFRASTRUCTURE, UP-GRADING OF EXISTING TRACKS, CONSTRUCTION OF NEW ACCESS TRACKS, DRAINAGE, EXCAVATIONS, JOINT BAYS, JUNCTION BOXES/CHAMBERS, MARKER POSTS/PLATES AND ALL RELATED ACCOMMODATION WORKS, EXTENDING CIRCA. 17,620 METRES IN LENGTH, FROM THE WIND ENERGY SITE CONTROL BUILDING/ELECTRICAL COMPOUND TO THE EXISTING ESB OWNED 110KV TRILLICK SUBSTATION, IN BALLYNAHONE TOWNLAND, BUNCRANA. THE GRID ROUTE WILL PASS ALONG EXISTING PUBLIC ROADS AND PRIVATE ACCESS TRACKS WITHIN THE TOWNLANDS OF CARROWMORE OR GLENTOGHER, ILLIES, CONNAGHKINNAGOE, BALLYNAKEELOGE, FOFFENAGH, MEENAMULLAGAN, STRANACLEA, MEENKEERAGH, SORNE, OWENAKILLEW AND BARNAHONE, TULLYDUSH UPPER, ANNASLEE AND BALLYNAHONE ALL INISHOWEN, CO. DONEGAL. THE PLANNING APPLICATION IS ACCOMPANIED BY AN ENVIRONMENTAL IMPACT ASSESSMENT REPORT (EIAR) AND BY A NATURA IMPACT STATEMENT (NIS).

CARROWMORE , QUIGLEY'S POINT , INISHOWEN

1.2km
1850471N/A29 Mar 2018

A 10 YEAR PLANNING PERMISSION CONSISTING OF THE CONSTRUCTION OF A SINGLE WIND TURBINE COMPRISING STEEL TOWER, NACELLE AND COMPOSITE FIBRE ROTOR BLADES WITH A BLADE TIP HEIGHT OF UP TO 124.9 METRES. THE DEVELOPMENT ALSO INCLUDES EXTERNAL WIND TURBINE TRANSFORMER, TURBINE FOUNDATION, HARDSTAND AND ASSEMBLY AREA, NEW SITE ENTRANCE AND ACCESS TRACK, ASSOCIATED DRAINAGE WORKS, UNDERGROUND ELECTRICAL CABLE AND ASSOCIATED COMMUNICATION CABLES, WITH ALL ANCILLARY DEVELOPMENT AND ASSOCIATED SITE WORKS

CARROWMORE OR GLENTOGHER , QUIGLEY'S POINT , LIFFORD PO

1.8km
1751204REFUSED27 Jul 2017

TWO NO. EXISTING ADVERTISING SIGNS AND ASSOCIATED SITE WORKS

CARROWMORE OR GLENTOGHER , CARNDONAGH , LIFFORD PO