MEENKEERAGH , BUNCRANA , LIFFORD PO
CONDITIONALPlanning application 1850746
Donegal - Donegal County Council
Proposed Development
AMENDMENT TO A PERMITTED WIND TURBINE (PA REG . REF. 10/70075) TO CHANGE TURBINE GEOMETRY FROM AN APPROVED: HUB HEIGHT FROM 80M UP TO A MAXIMUM PROPOSED 84M; AN OVERALL BLADE DIAMETER FROM 82M TO UP TO A MAXIMUM OF 100M; AND A PROPOSED BLADE TIP HEIGHT FROM THAT APPROVED OF 121M UP TO , AND NOT EXCEEDING THROUGH SELECTED COMBINATION OF THE HUB HEIGHT AND BLADE DIAMETER DIMENSIONS, OF A PROPOSED MAXIMUM 125M; AND FOR POWER MEGAWATT OUTPUT OF 2.5 MW
Application Timeline
Application received
14 May 2018
Decision: CONDITIONAL
6 Jul 2018
Decision due
8 Jul 2018
Grant issued
13 Aug 2018
Application Details
- Location
- MEENKEERAGH , BUNCRANA , LIFFORD PO
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Donegal County Council
- Site Area
- 2.46 ha
Timeline
- Registration Date
- 14 May 2018
- Status
- APPLICATION FINALISED
- Decision
- CONDITIONAL
- Decision Date
- 6 July 2018
- Grant Date
- 13 August 2018
- Permission Expires
- 28 November 2020
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
A 10 YEAR PLANNING PERMISSION FOR A PROPOSED WIND TURBINE WITH A 30 YEAR OPERATIONAL LIFE FROM THE DATE OF COMMISSIONING. THE PROPOSED WIND TURBINE SITE WILL CONSIST OF 1 NO. THREE BLADED WIND TURBINE WITH A MAXIMUM BASE TO BLADE TIP HEIGHT OF UP TO 119.33 METRES AND WILL INCLUDE TURBINE TRANSFORMER, TURBINE BASE AND FOUNDATION, TURBINE HARDSTAND AND TEMPORARY SET-DOWN AREA, CONSTRUCTION OF NEW ACCESS TRACK, JUNCTION AND TURNING AREA, ON-SITE DRAINAGE MANAGEMENT WORKS , 1 NO. NEW SITE ENTRANCE WITHIN SORNE WIND FARM AND WITH ALL OTHER ANCILLARY AND ASSOCIATED DEVELOPMENT AND INFRASTRUCTURE INCLUDING GENERAL AND EXCAVATION WORKS
MEENKEERAGH , BUNCRANA , LIFFORD PO
CONSTRUCTION OF A DWELLING HOUSE WITH DETACHED GARAGE AND WASTEWATER TREATMENT PLANT
SORNE , BUNCRANA , LIFFORD PO
A PERIOD OF 10 YEARS FOR UPGRADES TO THE EXISTING ILLIES WATER TREATMENT PLANT CONSISTING OF: (1) NEW DISSOLVED AIR FLOTATION BUILDING TO BE CONSTRUCTED ADJACENT TO THE EXISTING DISSOLVED AIR FLOTATION BUILDING, HOUSING A FOURTH DISSOLVED AIR FLOTATION STREAM OF SIMILAR HEIGHT BUT WITH A SMALLER FOOTPRINT THAN THE EXISTING DISSOLVED AIR FLOTATION BUILDING, (2) TWO NEW FIRST STAGE RAPID GRAVITY FILTERS TO BE CONSTRUCTED AS AN EXTENSION TO THE EXISTING SIX RAPID GRAVITY FILTERS, (3) UPGRADE OF THE EXISTING SECOND STAGE RAPID GRAVITY FILTERS TO DUAL-MEDIA CONFIGURATION, INCLUDING MODIFICATIONS TO WEIRS, UNDERDRAINS, AND AIR SYSTEMS, (4) NEW SLUDGE CONCENTRATOR TANK (258M³) TO BE INSTALLED ADJACENT TO THE EXISTING SLUDGE CONCENTRATORS, (5) UPGRADE OF THE EXISTING SLUDGE DEWATERING SYSTEM, INCLUDING PROVISION OF A HIGH-CAPACITY FILTER PRESS, AUTOMATED CONVEYOR SYSTEM, AND A COVERED TRAILER LOADING BAY, (6) DEMOLITION OF THE EXISTING WORKSHOP, AND CONSTRUCTION OF A NEW WORKSHOP AT AN ALTERNATE LOCATION WITHIN THE SITE, (7) NEW EXTERNAL ALUMINIUM SULPHATE (ALUM) BULK STORAGE, COMPRISING TWO 86M³ BUNDED TANKS, (8) MODIFICATION OF THE EXISTING ALUM STORAGE BUILDING TO HOUSE A NEW SODA ASH SILO. BUILDING HEIGHT WILL BE INCREASED TO MATCH THE EXISTING ADJACENT STRUCTURE HOUSING SODA ASH SILOS, (9) INTERNAL MODIFICATIONS TO EXISTING BUILDINGS (I.E., REMOVAL OF WALL) TO ACCOMMODATE NEW AND UPGRADED SYSTEMS, INCLUDING DOSING ARRANGEMENTS, BACKWASH PUMPS, AND AIR BLOWERS, (10) ELECTRICAL, INSTRUMENTATION, CONTROL AND AUTOMATION SYSTEM UPGRADES, INCLUDING A NEW SUPERVISORY CONTROL AND DATA ACQUISITION SYSTEM, NEW PANELS, AND INPUT AND OUTPUT SIGNAL MODIFICATIONS TO SUPPORT ADDITIONAL EQUIPMENT, (11) SOLAR PHOTOVOLTAIC PANELS TO BE INSTALLED ON ROOF AREAS TO SUPPORT ENERGY EFFICIENCY AND RENEWABLE ENERGY TARGETS, (12) IMPROVEMENT OF INTERNAL ROAD LAYOUT AND ACCESS ROUTES TO FACILITATE OPERATIONAL EFFICIENCY AND SITE DELIVERIES, (13) NEW FENCING AND GATES TO BE INSTALLED WHERE REQUIRED (MAXIMUM HEIGHT 2.4M), (14) LANDSCAPING, SCREENING, PLANTING AND BIODIVERSITY IMPROVEMENT MEASURES AND (15) ALL ANCILLARY SITE DEVELOPMENT WORKS
ILLIES , LIFFORD PO , CO. DONEGAL
ERECTION OF AN EXTENSION TO EXISTING COTTAGE, ALTERATIONS TO ELEVATIONS, CONNECTION TO EXISTING PUBLIC SERVICES AND ALL ASSOCIATED WORKS
STRANACLEA , ILLIES , CO. DONEGAL
Planning a project of your own?
Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.
Do I Need Permission?