BARNESMORE WINDFARM SITE , KEADOW UPPER , CLOGHER
CONDITIONALPlanning application 2150554
Donegal - Donegal County Council
Proposed Development
70-METRE-HIGH TEMPORARY METEROLOGICAL MAST AND ALL ASSOCIATED WORKS FOR A PERIOD OF 3 YEARS
View the full application file on the council's planning portal →Application Timeline
Application received
30 Mar 2021
Decision: CONDITIONAL
20 May 2021
Decision due
24 May 2021
Grant issued
30 Jun 2021
Application Details
- Location
- BARNESMORE WINDFARM SITE , KEADOW UPPER , CLOGHER
- Applicant
- N/A
- Application Type
- RETENTION
- Planning Authority
- Donegal County Council
- Site Area
- 0.145 ha
Timeline
- Registration Date
- 30 March 2021
- Status
- APPLICATION FINALISED
- Decision
- CONDITIONAL
- Decision Date
- 20 May 2021
- Grant Date
- 30 June 2021
- Permission Expires
- 29 June 2024
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
A 70 METRE HIGH TEMPORARY METEOROLOGICAL MAST AND ALL ASSOCIATED WORKS FOR A PERIOD OF 21 MONTHS WITHIN THE EXISTING BARNESMORE WINDFARM SITE
KEADEW UPPER , CLOGHER , DONEGAL PO
UPGRADING OF EXISTING INFRASTRUCTURE TO PROVIDE AN EXTERNAL TRANSFORMER AT TURBINE NO.22 AT THE EXISTING BARNESMORE WINDFARM SITE, THE DEVELOPMENT WILL CONSIST OF UPGRADING OF EXISTING INFRASTRUCTURE INCLUDING A GRP TRANSFORMER ENCLOSURE HOUSING TRANSFORMER EQUIPMENT, TRANSFORMER PLINTH AND ALL OTHER ASSOCIATED SITE DEVELOPMENT WORKS. THE PROPOSED TRANSFORMER ENCLOSURE WILL BE 2 METRES IN HEIGHT, 3.55 METRES IN LENGTH AND 2.44 METRES IN WIDTH. THE TRANSFORMER ENCLOSURE WILL BE LOCATED ON A NEW TRANSFORMER CONCRETE PLINTH ON THE EXISTING WIND TURBINE HARD STAND AREA. DUCTING WILL BE INSTALLED BETWEEN THE PROPOSED PLINTH AND THE EXISTING TURBINE
BARNESMORE WINDFARM SITE , KEADOW UPPER , CLOGHER BARNESMORE
UPGRADING OF EXISTING INFRASTRUCTURE INCLUDING A GRP TRANSFORMER ENCLOSURE HOUSING TRANSFORMER EQUIPMENT, TRANSFORMER PLINTH AND ALL OTHER ASSOCIATED SITE DEVELOPMENT WORKS TO FACILITATE THE DEVELOPMENT. THE PROPOSED TRANSFORMER ENCLOSURE WILL BE 2 METRES IN HEIGHT, 3.55 METRES IN LENGTH AND 2.44 METRES IN WIDTH. THE TRANSFORMER ENCLOSURE WILL BE LOCATED ON A NEW TRANSFORMER CONCRETE PLINTH ON THE EXISTING WIND TURBINE HARD STAND AREA. DUCTING WILL BE INSTALLED BETWEEN THE PROPOSED PLINTH AND THE EXISTING TURBINE
BARNESMORE WINDFARM SITE , CULLIONBUOY , BARNESMORE
UPGRADING OF EXISTING INFRASTRUCTURE TO PROVIDE AN EXTERNAL TRANSFORMER AT TURBINE NO.22 AT THE EXISTING BARNESMORE WINDFARM SITE, THE DEVELOPMENT WILL CONSIST OF UPGRADING OF EXISTING INFRASTRUCTURE INCLUDING A GRP TRANSFORMER ENCLOSURE HOUSING, TRANSFORMER EQUIPMENT, TRANSFORMER PLINTH AND ALL OTHER ASSOCIATED SITE DEVELOPMENT WORKS. THE PROPOSED TRANSFORMER ENCLOSURE WILL BE 2 METRES IN HEIGHT, 3.55 METRES IN LENGTH AND 2.44 METRES IN WIDTH. THE TRANSFORMER ENCLOSURE WILL BE LOCATED ON A NEW TRANSFORMER CONCRETE PLINTH ON THE EXISTING WIND TURBINE HARD STAND AREA. DUCTING WILL BE INSTALLED BETWEEN THE PROPOSED PLINTH AND THE EXISTING TURBINE
BARNESMORE WINDFARM SITE , CULLIONBUOY , CLOGHER BARNESMORE
Planning a project of your own?
Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.
Do I Need Permission?