ALTNAPASTE , BALLYBOFEY , LIFFORD PO
CONDITIONALPlanning application 2350315
Donegal - Donegal County Council
Proposed Development
CONSTRUCTION OF AN AGRICULTURAL SLATTED SHED WITH DRY BED PEN AND ASSOCIATED SITE DEVELOPMENT WORKS
Application Timeline
Application received
13 Mar 2023
Decision: CONDITIONAL
27 Apr 2023
Decision due
7 May 2023
Appeal submitted
8 May 2023
Appeal decided: CONDITIONAL
24 Oct 2024
Application Details
- Location
- ALTNAPASTE , BALLYBOFEY , LIFFORD PO
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Donegal County Council
- Site Area
- 0.23 ha
Timeline
- Registration Date
- 13 March 2023Other applications received that week
- Status
- APPLICATION FINALISED
- Decision
- CONDITIONAL
- Decision Date
- 27 April 2023
- Permission Expires
- 23 October 2029
An Coimisiún Pleanála Appeal
- Appeal Reference
- ABP-317068-23
- Decision
- CONDITIONAL
- Submitted
- 8 May 2023
- Decided
- 24 October 2024
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
DEVELOPMENT TO EXISTING DERELICT DWELLING HOUSE CONSISTING OF (1) DEMOLITION OF EXTENSIONS TO FRONT AND REAR OF DWELLING HOUSE AND ATTACHED OUTBUILDINGS, (2) RENOVATION AND ALTERATION WORKS INCLUDING RAISING THE PERIMETER WALLS AND ROOF HEIGHT AND AMENDMENTS TO DOOR AND WINDOW OPENINGS, (3) CONSTRUCTION OF EXTENSIONS TO THE FRONT, REAR AND SIDE ELEVATIONS AND (4) INSTALLATION OF SEPTIC TANK / SEWAGE TREATMENT SYSTEM AND ASSOCIATED SITE DEVELOPMENT WORKS
ALTNAPASTE , CLOGHAN , LIFFORD PO
A 10 YEAR PLANNING PERMISSION FOR DEVELOPMENT CONSISTING OF (1) A 110KV ELECTRICITY SUBSTATION WHICH INCLUDES 2 NO. CONTROL BUILDINGS, ASSOCIATED ELECTRICAL PLANT AND EQUIPMENT, UNDERGROUND ELECTRICITY CABLING, FENCING AND ANCILLARY WORKS IN THE TOWNLAND OF CARK TO REPLACE TWO SUBSTATIONS PREVIOUSLY PERMITTED AS PART OF THE DRUMNAHOUGH WIND FARM (PL.REF.08/50687 AND EXTENDED UNDER PL. REF.13/51609) AND THE LENALEA WIND FARM (PL.REF.09/50116); (2) 33KV UNDERGROUND ELECTRICITY CABLING AND ANCILLARY WORKS FROM THE PERMITTED LENALEA WIND FARM TO THE PROPOSED SUBSTATION IN THE TOWNLAND OF CARK; (3) 110KV UNDERGROUND ELECTRICITY CABLING AND ANCILLARY WORKS FROM THE PROPOSED SUBSTATION AT CARK THROUGH THE TOWNLANDS OF CULLIAGH, MEENBOG (ED CLOGHAN), LETTERSHANBO, CORLACKY, KINNADERRY, WELCHTOWN, AGHAVEAGH, MEENAGRAUV, ALTNAPASTE, BALLYKERGAN, CARRICKMAHON, MAGHERACLOIGH, LOUGHSALLAGH, CASHELNAVEAN, CROAGHONAGH, TAWNAWULLY MOUNTAINS, KEADEW UPPER, FRIARBUSH, ARDINAWARK, KEADEW LOWER, TO THE EXISTING CLOGHER SUBSTATION IN THE TOWNLAND OF CULLIONBOY, CO. DONEGAL; (4) THE DEMOLITION OF AN EXISTING SHED AND ITS REPLACEMENT WITH A NEW SHED, BOTH IN THE TOWNLAND OF CULLIONBOY, RELOCATED TO FACILITATE THE PROPOSED UNDERGROUND CABLING WORKS. THE PLANNING APPLICATION IS ACCOMPANIED BY AN ENVIRONMENTAL IMPACT STATEMENT (EIS) AND NATURA IMPACT STATEMENT (NIS)
CARK , CO. DONEGAL
ERECTION OF A DWELLING WITH CONNECTION TO PROPOSED SEPTIC TANK & PERCOLATION AREA
ALTNAPASTE , BALLYBOFEY , LIFFORD P.O.
ERECTION OF A DWELLING WITH CONNECTION TO PROPOSED SEPTIC TANK & PERCOLATION AREA
ALTNAPASTE , BALLYBOFEY , LIFFORD P.O.
(1) FIRST FLOOR ATTIC CONVERSION AND 3 NO. WINDOWS TO FIRST FLOOR GABLES AND (2) A DETACHED DOMESTIC GARAGE AND ASSOCIATED SITE DEVELOPMENT WORKS
ALTNAPASTE , BALLYBOFEY , LIFFORD PO
Planning a project of your own?
Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.
Do I Need Permission?