Proposed Development

The development will consist of: a c.189m long, c.10m wide approachway and ramp; 1 no. office and staff facilities building (c.193 sq.m and 7.7m in height); 1 no. control kiosk (c.6 sq.m and 2.3m in height); 1 no. control cabin (c.20 sq.m and 2.3m in height); new lighting (including 18 no. lighting columns 10m high); demolition of 5 no. existing staff facilities buildings with a combined area of c.329 sq.m; building 1 has an area of c.198 sq.m, building 2 has an area of c.10.7 sq.m, building 3 has an area of c.35.5 sq.m, building 4 has an area of c.42.4 sq.m, building 5 has an area of c.42.4 sq.m; and associated site works to include 15 no. tug parking spaces, drainage, utility services, fencing 2.4m in height and pedestrian gate 2.4m in height on a site of approx. 1.3 hectares. A Natura Impact Statement (NIS) will be submitted to the Planning Authority with the planning application.

Application Timeline

  1. Application received

    4 Jun 2019

  2. Decision due

    29 Jul 2019

  3. Decision: GRANT PERMISSION

    29 Jul 2019

  4. Grant issued

    9 Sept 2019

Application Details

Location
Adjacent to Berth 49, Ferryport Terminal 1, Dublin Port, Dublin 1
Applicant
N/A
Application Type
Permission
Planning Authority
Dublin City Council
Site Area
13627.17 ha

Timeline

Registration Date
4 June 2019
Status
Decision Notice Issued
Decision
GRANT PERMISSION
Decision Date
29 July 2019
Grant Date
9 September 2019

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

0m
2756/19APPLICATION DECLARED INVA15 Apr 2019

The development will consist of: a c.189m long, c.10m wide approach way and ramp; 1 no. office and staff facilities building (c.193 sq.m and 7.7m in height); 1 no. control kiosk (c.6sq.m and 2.3m in height); 1 no. control cabin (c.20sq.m and 2.3m in height); new lighting (including 18 no. lighting columns 10m high); demolition of 5 no. existing staff facilities buildings with a combined area of c.329sq.m; building 1 has an area of c.198sq.m, building 2 has an area of c.10.7sq.m, building 3 has an area of c.35.5sq.m, building 4 has an area of c.42.4sq.m, building 5 has an area of c.42.4sq.m; and associated site works to include 15 no. tug parking spaces, drainage, utility services, fencing 2.4m in height and pedestrian gate 2.4m in height on a site of approx. 1.3 hectares.

Berth 49, Terminal 1, Dublin Port, Dublin 1

294m
3174/24GRANT PERMISSION12 Feb 2024

The development will consist of : partial demolition of an electrical substation building to include an ESB room the north-east of the overall existing building which contains an electrical substation (10kV) together with the removal of associated raised access, steps and railings (total demolition of area c.32 sq.m) and reinstatement works; Installation of a new package substation (10kV) (c.6.2 sq.m and c. 2.8 in height) separate and to the north of existing substation building on an elevated platform (c. 30 sq.m and c. 1m in height); installation of new sheet piles on the landside to mitigate wash-out of sediment through the existing rock armour; adjustments to the existing surface parking layout; removal, relocation and replacement of a portion of existing fencing and gates (2.7m high); provision of 2 no. portable storage containers to support tugboats operations; site clearance, resurfacing, line marking, service trench excavation for electrical and communication duct installation, sub-surface remedial work and all associated site development works.

A site located north of Berth 50, Alexandra Road, Dublin Port, Dublin 1

500m
3041/24GRANT PERMISSION AND RETE15 Jan 2024

PERMISSION & RETENTION : Permission for development consisting of the construction of plant, comprising silos and blender, compressor room, cooling tank and pump room, storage, feed conveyors, retaining walls, new palisade fencing encompassing an increased site area, incorporating both a new vehicular sliding access gate, replacing the existing vehicular swing gates and the repositioning of the existing vehicular exit gate, creating a new vehicular entrance to the east of the site, revision of car park layout, together with associated site works. Retention permission is also sought for silos, office and laboratory together with permission for the demolition of structures, both permanent and temporary to include cooling tanks, compressor room, mill feed, silo and blender, retaining wall and palisade fencing and wall.

Pigeon House Road, Dublin 4, D04 FP28

500m
4853/23APPLICATION DECLARED INVA27 Nov 2023

RETENTION & PERMISSION: Permission for development consisting of the construction of plant, comprising silos and blender, compressor room, cooling tank and pump room, storage, feed conveyors, retaining walls, new palisade fence and gates, the revision of existing entrance and egress and car park layout, together with associated site works. Retention permission is also sought for silos, office and laboratory together with permission for the demolition of structures, both permanent and temporary, to include cooling tanks, compressor room, mill feed, silo and blender, retaining wall and palisade fencing and wall.

Pigeon House Road, Dublin 4, D04 FP28

553m
3872/20GRANT PERMISSION4 Dec 2020

The site is adjacent to Breakwater Road and Jetty Road. The development consists of removal of twelve bitumen & lubricant oil storage tanks with total capacity 3,105m3, removal of the associated equipment and removal of a control room building, followed by the installation of a new bitumen storage tank of 28m in diameter and 13.45m in height with a volume of approximately 8,275m3 and installation of a pump platform.

Irish Bitumen Storage Limited, Alexandra Road, Dublin Port, Dublin 1, D01 V0V2

616m
WEB5107/25GRANT PERMISSION10 Sept 2025

Modifications to existing workshop, ancillary office and welfare facilities to provide additional accommodation on existing site. Construction of 264 sq.m, 9.565m high extension to existing industrial building for additional workshop space. Construction of 246sq.m enclosed mezzanine office area with associated access lift, internal and external stairways, and additional windows to northern and western facades. Relocation of existing access ladder to roof on southern facade. Installation of 132sq.m of solar panels to extension roof. All associated diversions to existing drainage and water supply within the site.

Dublin Ferryport Terminals (DFT), Breakwater Road North, Dublin 1, D01 V3H3

682m
4574/19GRANT PERMISSION28 Nov 2019

The development will consist of: The construction of a 3 bay maintenance facility comprising of 2 no. single storey drive-in garages with pitched roofs and 1 no. single storey canteen / toilet / stores / workshop area with mono pitch roof (approx.. 436m2/6.8m high), building signage, associated site works, 9 no. lighting columns (approx.. 6m); removal of existing fencing and replacement with a 2m high boundary fence along the west, north and east boundaries; modifications to the existing boundary wall/fence along Tolka Quay Road to close one access and add one pedestrian gate and; car parking for 36 cars. The development also includes reconfiguration and widening of existing entrances / exits and connection to existing services on Tolka Quay Road, Dublin Port, Dublin 1. All development to take place on a site of aprrox. 0.2 hectares. The proposed development replaces the permission previously granted to Dublin Port Company for the construction of replacement offices and maintenance shed (Reg. Ref: 3143/18) on the same site. The site of the proposed development is a SEVESO site.

Calor, Tolka Quay Road, Dublin 1

702m
2071/20GRANT PERMISSION20 Jan 2020

Planning Permission for development at this site address: Circle K Yard 3, Alexandra Road, Dublin Port, Dublin 1. This site is regulated by the Major Accidents Directive. The development will consist of: Increasing the containment volume of the existing bund. Modifications will include raising the height of the existing bund wall by circa 0.5m, extending the bund to the east and lowering the ground level in the area of this bund extension from approximately 4.07m to 3.8m. The site's storm water, fresh water and foul sewer drainage will be modified to accommodate the bund extension.

Circle K, Yard 3, Alexandra Road, Dublin Port, Dublin 1

702m
3249/23APPLICATION DECLARED INVA22 Feb 2023

PROTECTED STRUCTURE: PERMISSION: For a sorting building at their construction and demolition recycling facility. The northern and western boundary wall of the permises are within the curtilage of a listed Protected Structure in the current City Development Plan. The facility has a current Waste Licence (WFP-DC-10-0020-01).

84, Pigeon House Road, Ringsend

702m
3417/23GRANT PERMISSION22 Mar 2023

PROTECTED STRUCTURE: permission for a single storey sorting building and canopy to the rear of the site of their construction and demolition recycling facility. The northern and western boundary walls of the premises are within the curtilage of a listed protected structure in the currently City Development Plan. The facility has a current waste licence ( WFP-DC-10-0020-01).

84 Pigeon House Road, Ringsend, Dublin 4

Planning a project of your own?

Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.

Do I Need Permission?