← Back to search

Gist Distribution, Willsborough Industiral Estate, Oscar Traynor Road, Clonshaugh, Dublin 17, D17 FV58

APPLICATION DECLARED INVA

Planning application 3256/23

Dublin - Dublin City Council

Proposed Development

The development will consist of the construction of additional staff car parking, yard extension and all associated site works.

Application Timeline

  1. Application received

    22 Feb 2023

  2. Decision: APPLICATION DECLARED INVA

    7 Mar 2023

  3. Decision due

    18 Apr 2023

Application Details

Location
Gist Distribution, Willsborough Industiral Estate, Oscar Traynor Road, Clonshaugh, Dublin 17, D17 FV58
Applicant
N/A
Application Type
Permission
Planning Authority
Dublin City Council
Site Area
6816 ha

Timeline

Registration Date
22 February 2023
Status
Decision Notice Issued
Decision
APPLICATION DECLARED INVA
Decision Date
7 March 2023

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

0m
3416/23GRANT PERMISSION22 Mar 2023

The development will consist of the creation of new vehicular entrance, construction of additional staff car parking, yard extension and all associated site works.

Gist Distribution, Willsborough Industrial Estate, Oscar Traynor Road, Clonshaugh, Co. Dublin, D17 FV58

127m
3600/21APPLICATION DECLARED INVA29 Sept 2021

The development will consist of: 1) the change of use of the warehouse/storage space within the existing building to data storage use; 2)the construction of a 980 sq. m. extension on the western elevation of the existing building for data storage use; 3) the installation of 16 no. condenser units and 2 no. air handling units on the roof of the extension; 4) the installation of 2 no. generator units in the north west corner of the site; 48 no. dry air cooler units on a steel frame with 4 no. transformer units beneath on the northern side of the building and: 5)the installation of a sliding gate and raising arm barrier gate across the internal access road within the site.

Unit B, Willsborough Industrial Estate, Clonshaugh Business and Technology Park, Dublin 17

127m
3640/21WITHDRAWN ARTICLE 33 (NO6 Oct 2021

Planning permission for the development will consist of : 1) the change of use of the warehouse/storage space within the existing building to data storage use; 2) the construction of a 980 sq.m. two storey extension on the western elevation of the existing building for data storage use; 3) the installation of 16 no. condenser units and 2 no. air handling units on the roof of the extension; 4) the installation of 2 no. generator units in the north west corner of the site; 48 no. dry air cooler units on a steel frame with 4 no. transformer units beneath on the northern side of the building; 5) the installation of a sliding gate and raising arm barrier gate across the internal access road within the site.

Unit B, Willsborough Industrial Estate, Clonshaugh Business and Technology Park, Dublin 17, D17 TH94

187m
4367/19GRANT PERMISSION5 Nov 2019

The development will consist of: A c. 200m long medium/low voltage (MV/LV) underground cable (UGC), to be installed in underground cable ducting in a c. 1m wide trench of depth c. 1m within an area of c.200sq.m., connecting the existing ESB network within the former Diamond Innovations site to the existing ESB Darndale substation. The UGC also includes ancillary electrical equipment. The development includes all associated and ancillary works. An Environmental Impact Assessment Report (EIAR) which complies with the European Union (Planning and Development) (Environmental Impact Assessment) Regulations 2018 (S.I> 296 of 2018) will be submitted to the Planning Authority with the application. The EIAR will be available for inspection or purchase at a fee not exceeding the reasonable cost of making a copy, during office hours at the offices of the planning authority.

The former Diamond Innovations site (Unit 1C), Clonshaugh Business & Technology Park, and adjacent lands, Dublin 17

190m
3803/20Decision Notice Issued25 Nov 2020

The proposed development comprises: 1. 2 no. 2 storey data centre buildings (each 16,576 sqm), which are 16m in height at the main parapet level. Each building to include: Office administration area, data halls, associated electrical and mechanical plant rooms, a loading bay, maintenance and storage spaces, screened plant and solar panel array at roof level, with rainwater harvesting system to support industrial water requirements. 16 no. emergency generators with emission stacks along with a single emergency house supply generator, all contained in a fenced compound adjacent to each building. Diesel storage tank, fuel filling area and associated plant. 2. 1 no. water sprinkler pump room (68 sqm), water storage tanks and humidifier tanks (175 sqm all inclusive). 3. 1 no. single storey client control building (216 sqm) and 2 no. transformers set within a fenced compound. 4. Demolition of 26 sqm substation building. 5. Partial diversion and undergrounding of ESB overhead lines. 6. Construction of internal site road network and circulation areas connecting to existing internal road network to the south, footpaths, provision of 100 no. car parking spaces, 4 no. motorcycle spaces and with 68 no. cycle parking spaces within a bicycle shelter, all accessed via existing campus to the south. 7. Temporary construction access road along western boundary. 8. Landscaping and planting including provision of planted berms to the eastern and northern boundary. 9. Perimeter security fencing, site lighting, bollards, camera poles, bin stores and all associated and ancillary site works including underground utility cables, water supply, foul and storm drainage network & over ground attenuation pond. All on an application site area measuring 11.52 hectares. An Environmental Impact Assessment Report (EIAR) will be submitted to the Planning Authority with the planning application and the EIAR will be available from inspection or purchase, at a fee not exceeding the reasonable cost of making a copy, during public opening hours at the offices of Dublin City Council.

Woodlands & Former Diamond Innovations Site, Clonshaugh Business & Technology Park, Dublin 17

197m
2956/20APPLICATION DECLARED INVA2 Jul 2020

Planning permission to erect 595.21 m2 of photovoltaic panels on the roof of our existing building with all associated site works at Virgin Media Ireland.

West Unit, Willsborough, Clonshaugh Industrial Estate, Dublin 17

234m
2402/19GRANT PERMISSION1 Mar 2019

Permission for development at the former Diamond Innovations site (Unit 1C), Clonshaugh Business & Technology Park and adjacent lands, Dublin D17 V088. The development will consist of: (1) 2 no. satellite antennae, 5.4m in diameter on; (2) 2 no. support towers in galvanised structural steel clad in powder coated steel mesh; (3) Access stairs and platforms behind existing plant screen; (4) 3m 2 tool cabin behind existing plant screen and; (5) 2 no. access roads for maintenance in permeable paving.

Former Diamond Innovations site (Unit 1C), Clonshaugh Business & Technology Park, Dublin 17

246m
5237/22APPLICATION DECLARED INVA16 Nov 2022

Permission to install up to 170kWp (c.800m2) of Roof Mounted Solar PV Panels and all associated works at our building Virgin Media Ireland.

West Corner, Willsborough Industrial Estate, Clonshaugh Business and Technology Park, Dublin 17, D17 F212

246m
5417/22GRANT PERMISSION12 Dec 2022

Permission to install up to 170kWp (c.800m2) of Roof Mounted Solar PV Panels and all associated works at our building.

West Corner, Willsborough Industrial Estate, Clonshaugh Business and Technology Park, Dublin, D17 F212

248m
3280/20APPLICATION DECLARED INVA31 Aug 2020

Retention permission to erect 595.21 m.sq. of photovoltaic panels on the roof of the existing building with all associated site works.

Virgin Media Ireland, West Unit, Willsborough , Clonshaugh Industrial Estate, Dublin 17