No. 2 Ballsbridge Park, Ballsbridge, Dublin 4, D04 YW83
GRANT PERMISSIONPlanning application 4729/22
Dublin - Dublin City Council
Proposed Development
The development will consist of an increase in floor area of the existing office building by providing lateral (to the east and west) and vertical extensions comprising; the lateral extension of the block (from part basement/part undercroft level to fifth floor level) by 6,702 sq m and the vertical extension of the block (provision of a new set back part sixth and seventh floor level) by 2,383 sq m providing an overall height of 8 No. storeys over part basement/part undercroft; replacement of all façades; and internal modifications and reconfigurations. The proposed development will result in an increase in office floor area from 7,093 sq m to 16,178 sq m. The development also includes: the reconfiguration of existing car park layout resulting in a reduction of 17 No. car parking spaces providing a total of 61 No. car parking spaces; bicycle parking: recessed balconies and roof terraces facing all directions; green roof, hard and soft landscaping; substations; generators; plant; photovoltaic panels; boundary treatments and all associated site development works above and below ground.
Application Timeline
Application received
25 Aug 2022
Decision due
19 Oct 2022
Decision: GRANT PERMISSION
19 Oct 2022
Appeal submitted
16 Nov 2022
Grant issued
24 Nov 2023
Appeal decided: GRANT PERMISSION
24 Nov 2023
Application Details
- Location
- No. 2 Ballsbridge Park, Ballsbridge, Dublin 4, D04 YW83
- Applicant
- N/A
- Application Type
- Permission
- Planning Authority
- Dublin City Council
- Site Area
- 4437 ha
Timeline
- Registration Date
- 25 August 2022
- Status
- Appeal Decided
- Decision
- GRANT PERMISSION
- Decision Date
- 19 October 2022
- Grant Date
- 24 November 2023
An Coimisiún Pleanála Appeal
- Appeal Reference
- ABP-315104-22
- Decision
- GRANT PERMISSION
- Submitted
- 16 November 2022
- Decided
- 24 November 2023
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
The construction of an external amenity area on an existing landscaped deck at ground floor level, comprising a single storey unenclosed pergola structure, barbecue / outdoor kitchen units, seating and dining areas and associated services, lighting, hard and soft landscaping, and all associated site and development works. The amenity area will provide a recreational amenity ancillary to the existing office building.
2 Ballsbridge Park, Ballsbridge, Dublin 4, D04 YW83
Construction of 48m² of new floor area on the first floor, located entirely within the existing building. The use of the proposed floor area is commercial office space.
2 Ballsbridge Park, Ballsbridge, Dublin 4, D04 YW83
Construction of an open-air padel court (200 sq. m) at lower ground floor level within the existing car park, comprising a rubberised court surface and a court enclosure of clear glass end walls (4 m high) and welded mesh side walls (3 m high); floodlighting mounted on the court enclosure, the omission of 13 existing car parking spaces (reducing on-site parking provision from 70 to 57 spaces); and all associated site and development works. The padel court will provide a recreational amenity ancillary to the existing office building.
2 Ballsbridge Park, Ballsbridge, Dublin 4, D04 YW83
10 year permission for development on a 1.38 Ha site at Nos. 1-3 Ballsbridge Park, Dublin 4. The development will consist of an increase in floor area of the existing 3 No. office buildings by providing lateral (to the east and west) and vertical extensions comprising: the lateral extension of Block 1 (from basement to fourth floor level) by 5,958 sq.m and the vertical extension (provision of a new set back part fifth floor level) by 1.555 sq.m; the lateral extension of Block 2 (from basement to fifth floor level) by 6.876 sq.m and the vertical extension (provision of a new set back part sixth floor level) by 1,264 sq.m; the lateral extension of Block 3 (from basement to fifth floor level) by 6,052 sq.m and the vertical extension (provision of a new set back part sixth floor level) by 1,201 sq.m; replacement of all facades of Block Nos. 1-3 and internal modifications and reconfigurations. The proposed development will result in an increase in office floor area from 19,696 sq.m to 42,602 sq.m. The development also includes: the reconfiguration of existing car park layout resulting in a reduction of 27 No. car parking spaces providing a total of 174 No. car parking spaces; provision of 408 No. cycle parking spaces; recessed balconies and roof terraces facing north, south, east and west; green roofs; hard and soft landscaping; 3 no. substations, generators; plant, photovoltaic panels; boundary treatments and all associated site development works above and below ground.
Nos. 1-3, Ballsbridge Park, Dublin 4
The development consists of: the demolition of existing 5 storey, 4,105 sq.m. structure on site (formerly known as Zurich House) and the construction of an 8 storey over basement office building of c. 19,154 sq.m. The building will contain a double height entrance reception area at ground floor and set back upper floors and terraces. The basement access/egress is via ramp from Ballsbridge Park. The basement will contain 44 no. car parking spaces, 3 no. of these are accessible, 276 no. bicycle parking spaces, 6 no. cargo/non-standard bike spaces and 22 no. scooter spaces. Changing rooms/showers, gym, bin stores, plant and attenuation tank are also contained within the basement. Green roof, solar panels, ESB substation, landscaping works and a new service access road onto Ballsbridge Park at the north of the site are proposed to be incorporated into the scheme.
1, Ballsbridge Park, Ballsbridge, Dublin 4, D04 E5N4
The development will consist of: -The demolition of existing 5-storey, 4,105 sq.m structure on site (formerly known as Zurich House) and the construction of an 8-storey over basement office building of c. 19,154 sq.m. The building will contain a double height entrance reception area at ground floor and set back upper floors and terraces. -The basement access/ egress is via ramp from Ballsbridge Park. The basement will contain 44 no. car parking spaces, 3 no. of these are accessible, 276 no. bicycle parking spaces, 6 no. cargo/ non-standard bike spaces and 22 no. scooter spaces. Changing rooms/ showers, gym, bin stores, plant and attenuation tank are also contained within the basement. -Green roof, solar panels, ESB substation, landscaping works and a new service access road onto Ballsbridge Park at the north of the site are proposed to be incorporated into the scheme.
1, Ballsbridge Park, Ballsbridge, Dublin 4, D04 E5N4
RETENTION: The development consists of the retention of the existing two-storey extension to the rear of the existing property including the alterations to previously approved planning ref: 3133-14.
No. 22 Dodderview Cottages, Ballsbridge, Dublin 4
RETENTION: The development consists of the retention of the existing two-storey extension to the rear of the existing property including alterations to previously approved planning ref. 3133-14.
22, DodderView Cottages, Ballsbridge, Dublin 4
RETENTION: The development consists of the retention of the existing two-storey extension to the rear of the existing property including alterations to previously approved planning ref. 3313-14
22, Dodderview Cottages, Ballsbridge, Dublin 4
Demolition of an existing single storey extension and derelict out-buildings and the construction of a proposed two storey extension to the rear of the existing semi-detached dwelling house. The proposed extension consists of a kitchen and WC at ground floor level and study at first floor level, bounded by Ballsbridge Avenue and Ballsbridge Park. The works will also include internal alterations and installation of rooflights (3 no.) on the rear pitch of the existing.