Unit 95, Lagan Road, Dublin Industrial Estate, Dublin 11, D11 VX90
APPLICATION DECLARED INVAPlanning application 4922/22
Dublin - Dublin City Council
Proposed Development
RETENTION PERMISSION for retention of erecting 326.00m2 of photovoltaic panels on the existing roof of the building in our company trading as Grand Cru Beers, with all associates site works.
Application Timeline
Application received
26 Sept 2022
Decision: APPLICATION DECLARED INVA
29 Sept 2022
Decision due
18 Nov 2022
Application Details
- Location
- Unit 95, Lagan Road, Dublin Industrial Estate, Dublin 11, D11 VX90
- Applicant
- N/A
- Application Type
- Retention Permission
- Planning Authority
- Dublin City Council
- Site Area
- 3700 ha
Timeline
- Registration Date
- 26 September 2022
- Status
- Decision Notice Issued
- Decision
- APPLICATION DECLARED INVA
- Decision Date
- 29 September 2022
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
The Change of use of the property to warehouse with ancillary trade counters, for the sale of building related products principally to trade. Proposed external changes comprise, new metal cladding on east and north elevations; new glazed aluminium entrance door in east elevation which becomes the entrance to the trade counters; new steel clad door to be fitted to existing door opening on the east elevation; existing roller shutter to be removed on double door at north east corner of building; new fire escape door to be inserted into the west elavation and all ancillary works.
103A, Barrow Road, Dublin Industrial Estate, Glasnevin, Dublin 11, D11 HX21
The development will consist of: the change of use of the property to warehouse with ancillary trade counters, for the sale of building related products principally to trade. Proposed external changes comprise, new metal cladding on east and north elevations; new glazed aluminium entrance door in north elevation; new steel clad door to be fitted to existing door ope in north elevation; existing roller shutter to be removed on double door at northeast corner of building; new fire escape door to be inserted into the west elevation and all ancillary works.
103A, Barrow Road, Dublin Industrial Estate, Glasnevin, Dublin 11
Signage associated with the use permitted under PA Ref: 2644/20 and all ancillary works associated with the installation of the signage.
103A, Barrow Road, Dublin Industrial Estate, Glasnevin, Dublin 11
RETENTION: Retention Permission for balcony at first floor level at rear with glazed screening and chrome handrail and fittings.
23, Glasnevin Court, Glasnevin, Dublin 11
Planning Permission to construct dormer window in attic storage area on rear elevation of roof with flat roof finish.
29, Glasnevin Woods, Dublin 11
PERMISSION & RETENTION: The development consists of the Retention Permission to the existing office / industrial unit of alterations to constructed building elevation for additional windows to the north elevation at first floor level and additional 83.32sqm of office floor space constructed to the existing first floor office layout. Application for Planning Permission consisting of construction of a protected stairwell within the unit from the first floor office area to the ground floor with construction of a new fire exit door from the stairwell to the north elevation of the building.
Unit 142A/B, Slaney Close, Dublin Industrial Estate, Glasnevin, Dublin 11
The development will consist of (i) extension to existing industrial building, (ii) a new storage building, (iii) removal of existing trees, (iv) revisions to existing signage and (v) all associated site works.
Unit 145C Slaney Close, Dublin Industrial Estate, Dublin 11
Permission for development at this 0.747 ha site. The development will consist of: the demolition of 4 no. existing dwellings and ancillary buildings known as Nos. 1-4 Rivermount Cottages (320m2) and the construction of a residential development arranged in 3 no. blocks (Block A, B and C) ranging from 4 to 5 no. storeys in height over basement/undercroft level (12,106.2m2, including basement). Blocks A and B incorporate a setback fifth storey. The maximum height of the development, taken from street level is 20.9m, including lift overrun. The development will comprise 99 no. residential units (47 no. 1-bedroom apartments, 50 no. 2-bedroom apartments and 2 no. 3-bedroom apartments); residential amenity areas comprising residents lounge and meeting rooms (296.4m2) and private, communal and public open space provision (including balconies and terraces to be provided on all elevations at all levels for each block). The development also consist of: amendments to the existing northern boundary wall; the provision of a new set-down area on Ballyboggan Road; the provision of 57 no. car parking spaces and 3 no. motorcycle parking spaces at the basement/undercroft level; the provision of bicycle stores providing 162 no. long-stay bicycle parking spaces and 34 no. short-stay (visitor) bicycle parking spaces at basement/undercroft level and 36 no. short-stay bicycle parking spaces adjacent to Ballyboggan Road. The development will also include: New vehicular access arrangements, for residents, emergency/refuse vehicles, and pedestrian access is via Ballyboggan Road; minor upgrade works to Ballyboggan Road; all piped infrastructure and ducting; plant rooms; ESB substation; lift access and stair cores; internal roads and pathways; hard and soft landscaping and boundary treatments; changes in level; waste management areas; attenuation tank; lighting; and all associated site development and excavation works above and below ground. A Natura Impact Statement will be submitted to the planning authority with this application. The Natura Impact Statement will be available for inspection or purchase at a fee not exceeding the reasonable cost of making a copy during office hours at the offices of the relevant planning authority.
1 - 4, Rivermount Cottages, Ballyboggan Road, Finglas, Dublin 11
The development consists of a single storey extension to the front of an existing warehouse unit to provide approximately 125m2 additional storage space. Five car parking spaces on the site will be removed to allow for the development.
Unit 53A, Barrow Road, Dublin Industrial Estate, Glasnevin, Dublin 11
The development consists of a single storey extension to the front of an existing warehouse unit to provide approximately 125m2 additional storage space. Five car parking spaces on the site will be removed to allow for the development.
Unit 53A, Barrow Road, Dublin Industrial Estate, Glasnevin, Dublin 11
Planning a project of your own?
Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.
Do I Need Permission?