Former Parish Centre, 12-14, Carman's Hall, Dublin 8, D08 KX89
APPLICATION DECLARED INVALIDPlanning application WEB5090/25
Dublin - Dublin City Council
Proposed Development
RETENTION: Dublin Simon Community is applying for retention permission for development consisting of: The change of use of the two storey (with third level stair shaft access to paved roof) building from parish centre (originally built as a school) to a hostel for the provision of short term emergency accommodation for homeless persons and associated alterations to the internal layout to provide 20 bedrooms accommodating 51 people, sanitary facilities, dining area, kitchen, offices, counselling rooms, a fire escape stairs, additional doors to the existing courtyard, conversion of the outbuilding to a laundry and plant room, external water storage tanks and associated external works including the provision of ramps to existing and additional access doors to the courtyard, at the former Parish Centre, 12-14 Carman’s Hall, Dublin 8. D08 KX89.
Application Timeline
Application received
9 Sept 2025
Decision: APPLICATION DECLARED INVALID
10 Sept 2025
Decision due
3 Nov 2025
Application Details
- Location
- Former Parish Centre, 12-14, Carman's Hall, Dublin 8, D08 KX89
- Applicant
- N/A
- Application Type
- Retention Permission
- Planning Authority
- Dublin City Council
- Site Area
- 748.62 ha
Timeline
- Registration Date
- 9 September 2025
- Status
- Decision Notice Issued
- Decision
- APPLICATION DECLARED INVALID
- Decision Date
- 10 September 2025
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
RETENTION: PROTECTED STRUCTURE: Dublin Simon Community is applying for retention permission for development consisting of: The change of use of the two storey (with third level stair shaft access to paved roof) building from parish centre (originally built as a school, Saint Nicholas of Myra National School) to a hostel for the provision of short term emergency accommodation for homeless persons and associated alterations to the internal layout to provide 20 bedrooms accommodating 51 people, sanitary facilities, dining area, kitchen, offices, counselling rooms, a fire escape stairs, additional doors to the existing courtyard, conversion of the outbuilding to a laundry and plant room, external water storage tanks and associated external works including the provision of ramps to existing and additional access doors to the courtyard, at the former Parish Centre, 12-14 Carman’s Hall, Dublin 8, which is a PROTECTED STRUCTURE, RPS 8822 (Former Saint Nicholas of Myra National School).
Dublin Simon Community, 12-14 Carman's Hall, Dublin 8, D08 KX89
The development will consist of the installation of an ATM machine to the existing shop front to the East elevation.
102 Francis Street, Dublin 8
The development will consist of the installation of an ATM machine to the existing shop front to the east elevation.
102, Francis Street, Dublin, D08 Y70F
The development will consist of: Demolitions and Construction of 3No. additional apartments (1No. 2-Bedroom apartment & 2No. 1-Bedroom apartments) along with alterations to 2No. existing apartments and all ancillary works in new upward extensions and alterations to the existing building consisting of: (1) Demolition of part of the Existing Set-Back Third Floor Level; (2) Demolition of the Existing Roof Level; (3) Demolition of parts of External Facades/ Fenestration at existing Second Floor Level and Set-Back Third Floor/ Roof Level; (4)Construction of Extensions and Alterations to Third Floor Level incorporating 1No. new additional 1 Bedroom Apartment along with alterations to 2No. existing Apartments & Associated Circulation and Ancillary Areas; (5) Construction of new set-back Fourth Floor Level incorporating 2No. new additional apartments (1 No. 1-Bedroom apartment & 1 No. 2-Bedroom apartment) along with Associated Circulation and Ancillary Areas; (6) Construction of Alterations to Facades/ Fenestration at Second Floor, Third Floor and Fourth Floor Levels; (7) Construction of all Consequent Internal, External and Facade Alterations; & (8) All Ancillary Site Development and Services Works.
101-103, Francis Street, Dublin 8
RETENTION: The development consists of: the temporary use of part of the existing Student Accommodation for tourist or visitor accommodation until 31st May 2022, after which time the development will revert to the originally permitted Student Accommodation use under DCC Reg. Ref. 2827/17. There are no physical changes proposed to the permitted development.
Heyday Student Accommodation, Carman's Hall, The Liberties, Dublin 8
Permission to erect telecommunications antennas and associated equipment concealed within three no. shrouds with fitting apparatus and a cabinet upon the building rooftop.
Heyday, 16-22 Carman's Hall Student Accommodation, Garden Lane, Dublin 8
Permission for the installation of three telecommunication antennae and ancillary equipment on the rooftop of the electricity substation building at ESB's Francis Street 110kV Electricity Substation, Francis Street/Swift's Alley/Garden Lane, Dublin 8. The site is located in an Architectural Conservation Area.
ESB's Francis Street 110kV Electricity Substation, Francis Street/Swift's Alley/Garden Lane, Dublin 8.
Permission for the installation of three telecommunication antennae on the rooftop of the electricity substation building at ESB's Francis Street 110kV Substation, Francis Street / Swift's Alley / Garden Lane. The site is located in an Architectural Conservation Area.
ESB's Francis Street 110kV Substation, Francis Street, Swift's Alley, Dublin 8
RETENTION & PERMISSION: a) The development works to be retained consist of a single storey flat roof extension to the rear, roof terrace at first floor level and all associated alterations, site works and ancillary works b) Permission for a new 2 metre high timber privacy screen at first floor level to replace the existing timber balustrade surround to the roof terrace.
8, Spitalfields, The Coombe , Dublin 8
PERMISSION: The development will consist of the removal of an existing no. 1 modular ballast with support pole and installation of telecommunications equipment including no. 6 ballast mounted shrouded antennas, no. 3 ballast mounted dishes, remote radio units (RRU's), GPS, cable trays, cabinet and all other associated site development works on the building rooftop to provide for high speed wireless data and broadband services.
Heyday, 16-22 Carman's Hall Student Accommodation, Garden Lane, Dublin 8