← Back to search

Beaver House, Beech Hill Office Campus, Clonskeagh, Dublin 14

GRANT PERMISSION

Planning application D18A/1099

Dublin - Dun Laoghaire Rathdown County Council

Proposed Development

Permission for: 1. The erection of 1 no. internally illuminated fascia sign with

Application Timeline

  1. Application received

    23 Nov 2018

  2. Decision: GRANT PERMISSION

    23 Jan 2019

  3. Decision due

    25 Jan 2019

  4. Grant issued

    26 Feb 2019

Application Details

Location
Beaver House, Beech Hill Office Campus, Clonskeagh, Dublin 14
Applicant
N/A
Application Type
Permission
Planning Authority
Dun Laoghaire Rathdown County Council
Site Area
532 ha

Timeline

Registration Date
23 November 2018
Status
Decision made
Decision
GRANT PERMISSION
Decision Date
23 January 2019
Grant Date
26 February 2019

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

10m
D06A/0548GRANT PERMISSION FOR RETENTION21 Apr 2006

Temporary Retention Permission (five years)

Beaver House, Beech Hill Business Campus, Clonskeagh, Dublin 14.

32m
D18A/0174GRANT PERMISSION FOR RETENTION26 Feb 2018

Retention permission for development at this site. The development will

Beaver House, Beech Hill Office Park, Clonskeagh, Dublin 4

36m
REF15825WITHDRAW THE APPLICATION19 Sept 2025

(1) Whether— (1) the change of use of Boole House, Beech Hill Office Campus, Cl

Boole House, Beech Hill Office Campus, Beech Hill Road, Dublin 4, D04A563

43m
D22A/0149GRANT PERMISSION1 Mar 2022

Permission for development. The development will consist of

Boole House, Beech Hill Office Campus, Clonskeagh, Dublin 4 D04 A563

46m
D20A/0939REFUSE PERMISSION11 Dec 2020

Permission for development consisting of

Site (c. 0.42Ha) at, Boole House, Beech Hill Office Campus, Clonskeagh, Dublin 4

50m
D11A/0462GRANT PERMISSION FOR RETENTION13 Oct 2011

Planning permission for retention of the following developments undertaken

Ericsson Ltd, Beech Hill Campus, Clonskeagh and Ericsson Main Building, Beech Hill Road, Clonskeagh, Dublin 14

53m
D06A/0552GRANT PERMISSION FOR RETENTION21 Apr 2006

For temporary permission (5 years) for the retention

Beech Hill Business Campus, Clonskeagh And Ericsson Main Builing, Beech Hill Road, Clonskeagh, Dublin 14

56m
D06A/1471GRANT PERMISSION16 Oct 2006

For creation of an external plant space on existing car parking at rear

Boole House, Beech Hill Business Campus, Beech Hill Road, Clonskeagh, Dublin 4

59m
D18A/0657REFUSE PERMISSION6 Jul 2018

Permission for the demolition of existing structures and the construction of a

Beech Hill Office Campus, Beech Hill Road, Dublin 4

71m
D14A/0795GRANT PERMISSION9 Dec 2014

Permission for; (a) demolition of existing 2.6 sqm main entrance porch to front

Topaz House, Beech Hill, Clonskeagh, Dublin 4

Planning a project of your own?

Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.

Do I Need Permission?